Resolved
That the overview of the delivery and oversight of the Health and Care Plan programmes to the Wirral Place Based Partnership Board as set out in this report be noted.
Health and Wellbeing Board noted this item on Thursday 14 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the overview of the delivery and oversight of the Health and Care Plan programmes to the Wirral Place Based Partnership Board as set out in this report be noted.
HEALTH AND WELLBEING BOARD 14th March 2024
REPORT TITLE: DELIVERY OF WIRRAL HEALTH AND CARE PLAN REPORT OF: PLACE DIRECTOR (WIRRAL), NHS CHESHIRE AND MERSEYSIDE
REPORT SUMMARY The Wirral Health and Care Plan is a collective plan on Wirral, for how the health and care organisations across Wirral will work together to progress with agreed priorities and areas of work. These priorities are cognisant of, and support, the delivery of a number of key national and Wirral Place level strategic aims, including the Wirral Council Plan 2023-27 and Wirral Health and Wellbeing Strategy 2022-27
This report presents to the Board the delivery dashboard for the programmes within the Wirral Place Health and Care Plan. The dashboard structure has been developed and agreed with the Strategy and Transformation Group (STG), which is a supporting group to the Wirral Place Based Partnership Board (WPBPB). The dashboard is reviewed by the STG and the WPBPB on a monthly basis. The dashboard provides an oversight of the whole programme portfolio, provides a monthly narrative update and Red Amber Green rating of overall programme delivery, benefits, risks, and issues.
This report affects all wards and is not a key decision.
RECOMMENDATION/S
The Health and Wellbeing Board is recommended to note overview of the delivery and oversight of the Health and Care Plan programmes to the Wirral Place Based Partnership Board as set out in this report. SUPPORTING INFORMATION
1. REASON/S FOR RECOMMENDATION/S
1.1The purpose of this report is to provide the Board with information and assurance on the progress of the programmes associated with the Wirral Health and Care Plan 2023-24. There is a requirement to demonstrate progress against the delivery of the priorities within the Plan to evidence the progress made to the Wirral Place Based Partnership Board. The programme dashboard provides that evidence.
2. OTHER OPTIONS CONSIDERED
2.1No other options have been considered as the report is at the request of the Board.
3. BACKGROUND INFORMATION
3.1Following the publication of the Wirral Place Health and Care Plan 2023-24 and its endorsement by the Wirral Place Based Partnership Board (WPBPB) on 22nd June 2023 work has been continued led by the Wirral Improvement Team (WIT), with the Strategy and Transformation Group (STG) to develop the delivery dashboard providing oversight of the whole programme portfolio within the plan, and to ensure that strong governance, monitoring and control processes are in place.
3.2Following review of the programme portfolio of the plan, several changes have been proposed which it is believed will support the delivery of improved outcomes. These specifically are the expansion of the Learning Disabilities and Autism Programme to encompass all age disability, and the establishment of a clear programme plan and oversight board for the Core20+5 approach to driving targeted action for health improvement.
3.3For the avoidance of doubt, the programmes that constitute the portfolio within the Health and Care Plan, including the above changes are summarised in the figure below: 3.4. The data and narrative that constitutes the dashboard is agreed with the Senior Responsible Officers (SROs) and Programme Leads for each constituent programme and the membership of the STG.
3.5Of the programme portfolio within the Health and Care plan; several of the programmes are managed directly through the WIT, whilst others are managed by partner organisation Programme Management Office functions. However, the WIT oversee the collation and reporting of the whole portfolio, working with the SROs and programme leads.
3.6The dashboard forms the information baseline for the monitoring and control of the suite of programmes within the plan. The monitoring process follows a clear timeline for report updating, review and adjustment. It also supports the detailed review of individual programme areas though a schedule of ‘deep dives.’ The monthly process is summarised in the figure below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Wirral Health and Care Plan DashboardAppendix 1 | 611 KB | Download |
PDF |
Delivery of Wirral Health and Care PlanReport | 612 KB | DownloadRead as text |
Follow Health and Wellbeing Board at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | Annual Report on the Joint Strategic Needs Assessment ProgrammeIt was agreed across Cheshire and Merseyside to monitor the Marmot indicators overtime. These indicators were aligned... | Agreed | Open |
| 20 Jul 2026 | Work ProgrammeResolved – That subject to the above additional item, the proposed Health and Wellbeing Board work programme for the ... | Noted | Open |
| 12 Mar 2026 | Send improvementResolved – That the progress of the Local Area SEND Partnership Board in progressing system improvement as required b... | Noted | Open |
| 12 Mar 2026 | Work ProgrammeResolved – That the Health and Wellbeing Board notes the proposed Health and Wellbeing Board work programme for the r... | Decided | Open |
| 11 Dec 2025 | Better Care Fund Q2 UpdateResolved – That 1. The continued compliance with the requirements of the Better Care Fund (BCF) be noted and that NHS... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.