Resolved
Resolved – That the comprehensive arrangements in place within the Regeneration and Place Directorate for managing all Directorate risks be noted.
Audit and Risk Management Committee noted this item on Tuesday 26 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the comprehensive arrangements in place within the Regeneration and Place Directorate for managing all Directorate risks be noted.
AUDIT AND RISK MANAGEMENT COMMITTEE
Tuesday, 26 March 2024
REPORT TITLE: REGENERATION AND PLACE RISK MANAGEMENT REPORT OF: DIRECTOR OF REGENERATION AND PLACE
REPORT SUMMARY
The Director of Regeneration and Place was requested by the Audit and Risk Management Committee at their meeting on 15 January 2024 to attend the next meeting of this Committee in March 2024 to present a risk report on all Directorate risks. This report provides the information requested by that Committee.
The report supports the Council Plan: Wirral Working Together 2023-27, specifically the People-Focussed Regeneration theme.
The report is not a key decision.
RECOMMENDATION/S
The Audit and Risk Management Committee is recommended to note the comprehensive arrangements in place within the Regeneration and Place Directorate for managing all Directorate risks. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To provide the Members of the Audit and Risk Management Committee with the opportunity to review all Regeneration and Place risks and their management.
2.0OTHER OPTIONS CONSIDERED
2.1No other options were considered as this is a specific request from Committee for information.
3.0BACKGROUND INFORMATION
3.1Audit and Risk Management Committee at their meeting on 15 January 2024 resolved that the Director of Regeneration and Place be requested to attend the next meeting of the Committee in March 2024 to present a risk report on all Directorate risks.
3.2Specifically, this request was understood to include: 1. a review of the Directorate Risk Register, 2. information on how risks are managed (the mitigation in place or planned), 3. the process for managing new risks when they arise and how these are communicated and documented and 4. the outcomes which should be expected from current programmes as a result of delivery.
3.3Regeneration and Place is a diverse Directorate managing and delivering a range of services, programmes and projects. It is organised into five service areas: - Housing (including Strategic Housing, Homelessness and delivery of housing with partners) - Planning (including Local Plan, Forward Planning, Development Management and Building Control) - Regeneration Strategy (including economic growth, Strategic Infrastructure and Transport, Culture and Heritage, Places and Partnerships) - Property and Regeneration Investment/Delivery (including Asset and Facilities Management, Corporate Landlord, and Regeneration Delivery) - Special projects (including Regeneration of New Ferry, co-location of services, and implementing community asset transfer)
3.4The Directorate’s Risk Register, at March 2024 is attached to this report at Appendix 1. It follows the Council’s corporate format in setting out all the Directorate risks, scoring these and identifying managed and mitigation measures in place or planned. It is included in the annual Directorate Business Plan which is reported to the Economic, Regeneration and Housing Committee on an annual basis. The date for this report for 2024/25 is being discussed with the Chair of that Committee. 3.5 The Risk Register is formally reviewed by the Departmental Management Team (Director, Assistant Directors with the support of the Corporate Risk Lead Officer on a quarterly basis and is informally reviewed more regularly.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regeneration and Place Directorate Risk RegisterAppendix 1 | 432 KB | Download |
PDF |
Regeneration and Place Risk ManagementReport | 391 KB | DownloadRead as text |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.