Refuse Collection & Street Cleansing Contract Review - Outline Business Case
NotedCommittee2 papers
Environment, Climate Emergency and Transport Committee noted this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved – That (1) the attached Outline Business Case be noted. (2) the Director of Neighbourhoods be instructed to prepare a Full Business Case with focus on exploring a fully outsourced provision, a full LATCo provision and outsourced waste collection with in-house street cleansing provision, to be presented to Committee later this year.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
ENVIRONMENT, CLIMATE EMERGENCY AND TRANSPORT COMMITTEE Monday, 15th July 2024
REPORT TITLE: REFUSE COLLECTION & STREET CLEANSING CONTRACT REVIEW – OUTLINE BUSINESS CASE REPORT OF: DIRECTOR OF NEIGHBOURHOOD SERVICES
REPORT SUMMARY
This report provides members of the Environment, Climate Emergency and Transport Committee with recommendations for the future service delivery of waste collection and street cleansing services for Wirral.
Wirral Council has a legal duty to collect household waste and to carry out street cleansing activity. A contract is in place for delivery of waste collection and street cleansing services, which expires in August 2027 with no further option to extend. As such, the Council commissioned Eunomia Research and Consulting Ltd (Eunomia) to support a review of its waste collection and street cleansing contract, to thoroughly assess the options for waste collection and street cleansing service provision from August 2027.
This report and appendices pertained present the Outline Business Case (OBC), following a detailed assessment of the different service delivery options, below: Full in-house provision. A fully outsourced contract. Delivery via a local authority trading company (LATCo). or a combination of one or other of the above. The OBC focuses on the service delivery aspect of the waste collection and street cleansing review. Its purpose is to outline the service delivery options available, whilst considering the risks and financial implications of the options, to allow Members to selectively review which options to proceed with to a Full Business Case (FBC).
Following both financial and qualitative assessment of each the options, the fully outsourced option is ranked as the most favourable, with the full LATCo option second. The spilt service delivery options were the least favourable.
As part of the FBC, a second phase, beginning in June 2024, will focus on the service specification, including how waste and recycling will be collected from households in Wirral and the street cleansing services required. The FBC will be presented to this Committee, later this year.
This report aligns to the following themes within the Council’s strategic plan - ‘Wirral Working Together: A Council Plan for 2023 – 2027:
Theme 1: ‘Working Together to create a more efficient, effective and accessible Council’. Theme 5: ‘Working Together to protect our environment’.
This matter affects all Wards within the Borough. This is a key decision.
RECOMMENDATION/S
The Environment, Climate Emergency and Transport Committee is requested to:
1. Note the attached Outline Business Case.
2. Instruct the Director of Neighbourhoods to prepare a Full Business Case with focus on exploring a fully outsourced provision, a full LATCo provision and outsourced waste collection with in-house street cleansing provision, to be presented to Committee later this year. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Based on the analysis carried out, considering costs and risks, the most favourable options to take forward for further consideration to Full Business Case are the fully outsourced option and the full LATCo option.
1.2The Officer recommendation to exclude both the fully in-house provision (Option B), as well as Retender Waste Services, bring Cleansing into a LATCo (Option E) from the phase 2 Full Business Case, are based on both the financial performance, and associated risks as identified in the OBC.
1.3The option to bring street cleansing in-house, while keeping waste collection outsourced (Option D), is a locally favoured option, that will be investigated further, to provide Committee with a full range of options.
2.0OTHER OPTIONS CONSIDERED
2.1The current waste collection and street cleansing contract expires in August 2027, with no option to extend. As such, the Council must either re-tender the services or provide the services in-house or via a LATCo, to continue to meet our legal obligations as a waste collection authority.
3.0BACKGROUND INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.