Refuse Collection & Street Cleansing Contract Award

Refused Committee 3 papers

AI summaryWirral Policy and Resources Committee awards a refuse, recycling and street cleansing contract to Biffa, with a 16-year maximum value of £348.6m and a 27 August 2027 start.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRefusedMost Advantageous Tenderer under a Competitive Flexible Procedure
MoneyNot stated
What happens nextDirector of Operations to finalise termsIncluding depot works and depot acquisition with lease-back
Who it affectsWirral residents receiving waste servicesPlus Dock Road South depot operations and commercial waste customers

What was decided

A new refuse, recycling and street cleansing contract, 8 years with an 8-year extension option, was awarded to Biffa Waste Services Ltd as the Most Advantageous Tenderer, with a maximum total estimated value of £348.6m over the 16-year term.

The Director of Operations was authorised to negotiate and finalise ancillary arrangements to bring Dock Road South Depot up to standard for the new contract, at an estimated cost of £1.9m.

The Director of Operations was authorised to finalise the Council's acquisition of Dock Road South depot, with Biffa continuing to operate there for its own commercial waste work via lease-back or similar.

Why

The committee awarded the contract to Biffa on the basis that it was the Most Advantageous Tenderer under a Competitive Flexible Procedure.

Financial, legal, resource, risk, engagement, equality, environment, community wealth and crime and disorder implications were all considered via the minutes and report of the Environment, Climate Emergency and Transport Committee. Report 4.1, 5.1, 6.1, 7.1, 8.1, 10.1, 11.1, 12.1

What happens next

The Director of Operations will negotiate and finalise the depot ancillary arrangements, the depot acquisition and the lease-back terms.

The new contract is scheduled to commence on 27 August 2027.

The money

  • £348.6m Maximum total estimated value of the refuse, recycling and street cleansing contract over the full 16-year term
  • £1.9m Estimated cost of ancillary works to bring Dock Road South Depot up to standard for the new contract

Options considered

  • Chosen: Award the contract to Biffa Waste Services Ltd for 8 years with an 8-year extension option. Identified as the Most Advantageous Tenderer under a Competitive Flexible Procedure

Implications

  • Legal: The Council is under a legal duty to ensure its policies and decisions do not discriminate, and an Equality Impact Assessment is to be used to identify steps to secure equality for those affected. Report 9.1

Who and where

  • Residents of Wirral receiving refuse, recycling and street cleansing services
  • Biffa Waste Services Ltd, as incoming contractor
  • Dock Road South Depot, subject to acquisition and lease-back arrangements
  • Biffa's commercial waste customers at Dock Road South

Timeline

  • 22 July 2026: Policy and Resources Committee decision to award the contract
  • 27 August 2027: New refuse, recycling and street cleansing contract commences

Plain English for the jargon

  • Competitive Flexible Procedure: A procurement procedure under the Procurement Act allowing competitive tenders with flexibility on how the process is run.
  • Most Advantageous Tenderer: The bidder judged to offer the best overall value to the Council under the competitive procedure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32

Resolved

Resolved – that, 1. A new contract for the provision of refuse and recycling collection and street cleansing services within Wirral on an 8 year contract (with the option to extend for a further 8 years) commencing on 27 August 2027 be awarded to Biffa Waste Services Ltd (Biffa) as the Most Advantageous Tenderer pursuant to a Competitive Flexible Procedure with a maximum total estimated contract value of £348.6m based on a 16-year term be approved; 2. The Director of Operations be authorised to negotiate and finalise terms for: a. Ancillary contractual arrangements to be entered into with Biffa to bring Dock Road South Depot up to the necessary standard for the purposes of a new contract at an estimated cost of £1.9m; and b. The acquisition by the Council of Dock Road South depot at the estimated acquisition cost as set out in the exempt Appendix 3 to the report on terms that enable Biffa to continue to operate at the depot for the purpose its own commercial waste operations by way of lease back or analogous arrangements.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Financial implications

4.1Financial implications has been considered as reported within the minutes of the Environment, Climate Emergency and Transport Committee and appended report.

5.1Financial implications has been considered as reported within the minutes of the Environment, Climate Emergency and Transport Committee and appended report.

6.0RESOURCE IMPLICATIONS: STAFFING, ICT AND ASSETS

6.1Resource Implications has been considered at as reported within the minutes of the Environment, Climate Emergency and Transport Committee and appended report.

7.0RELEVANT RISKS

7.1Relevant Risks has been considered at as reported within the minutes of the Environment, Climate Emergency and Transport Committee and appended report. 8.0 ENGAGEMENT/CONSULTATION

8.1Engagement and Consultation has been considered at as reported within the minutes of the Environment, Climate Emergency and Transport Committee and appended report.

Equality implications

9.1Wirral Council has a legal requirement to make sure its policies, and the way it carries out its work, do not discriminate against anyone. An Equality Impact Assessment is a tool to help council services identify steps they can take to ensure equality for anyone who might be affected by a particular policy, decision or activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refuse Collection & Street Cleansing Contract Award: Minute ExtractAppendix 1 68 KB Download
PDF
Refuse Collection and Street Cleansing Contract Award report, 15/06/2026 Environment, Climate Emergency and Transport CommitteeAppendix 2 161 KB Download
PDF
Refuse Collection & Street Cleansing Contract AwardReport 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 20 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, apologies, sent representative
RM
Councillor Ruth MolyneuxSpokesperson, present
SR
Councillor Simon R MountneySpokesperson, present
CC
Councillor Chris CarubiaSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
SF
Councillor Steve FoulkesCommittee Member, present
TM
Councillor Tony MurphyCommittee Member, present
SP
Councillor Sue Powell-WildeCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 20 on the meeting page

On this subject at Wirral

Search all
  1. Refuse Collection & Street Cleansing Contract AwardThis decision
  2. Refuse collection & street cleansing service review - full business caseRefused
  3. Refuse Collection & Street Cleansing Contract Review - Outline Business CaseNoted
  4. Domestic Refuse Collection Service UpdateNoted
  5. Domestic Refuse Collection Outline Business CaseDecided

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies