Resolved – That the Director of Law and Corporate Services be authorised to: (a) finalise and enter into a Grant Funding Agreement (GFA) with Homes England and a GFA with Liverpool City Region Combined Authority (LCRCA) to secure the funding required to implement the primary enabling works for the Hind Street Urban Village project as detailed at paragraph 3.2 of this report. (b) enter into a contract for the delivery of the primary enabling works with John Sisk & Son Ltd pursuant to the Procure Partnerships Framework - Infrastructure Lot £15m +; (c) enter into a development management agreement with Ion Property Developments Ltd (Ion) through the Pagabo framework (Lot 3 – Reserved Suppliers – Development Management Services) to enable Ion Property Developments Ltd to manage the implementation of the primary enabling works on behalf of the council; (d) to enter into a legal agreement with Cadent Gas Limited (Cadent) in relation to the relocation of the gas infrastructure, subject to the costs of the arrangement being within the estimates detailed in the Full Business Case (FBC) submitted to Homes England and Liverpool City Region Combined Authority.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
POLICY & RESOURCES COMMITTEE Wednesday 2 October 2024
REPORT TITLE: HIND STREET - PRIMARY ENABLING WORKS REPORT OF: DIRECTOR OF REGENERATION AND PLACE
REPORT SUMMARY
The Hind Street Urban Village project will see the development of around 1,500 new homes over the next 10 to 15 years. This ambitious and transformational project will effectively create a new community adjacent to the town centre. The development will be a model of urban living, well connected to Liverpool City Centre through the proximity of Birkenhead Central and Green Lane Station, and provided with quality open spaces, public realm and active travel routes. The development is expected to attract people who are existing Wirral residents looking for a modern housing offer and a different lifestyle afforded by the proximity of Hind Street to so many local and city centre facilities, along with new residents from outside the borough. This is a landmark scheme for the council and fundamental to the delivery of the Council’s brownfield-first Local Plan.
The Council submitted a Full Business Case (FBC) for Hind Street South (the area south of Hind Street) on 9th July 2024, requesting £50.1 million of funding from Homes England (HE) and Liverpool City Region Combined Authority (LCRCA). The FBC is attached as appendix 1. This funding will unlock phases A and B of the development, a site comprising of 10.9 ha of brownfield land, for which planning permission is sought for the delivery of 633 homes and 1,330sqm (Net Internal Area – NIA) of ancillary commercial floorspace. The package of works set out in the FBC (referred to as the Primary Enabling Works) will support the creation of development plots, with identified works relating to:
1. Site preparation – programme of remediation and ground works to address issues associated with former industrial uses; 2. Utilities infrastructure – relocation of active gas Pressure Reduction Infrastructure (PRI); 3. Highway infrastructure – a network of streets finished with high quality materials, including high quality routes for pedestrians and cyclists and bus infrastructure; and 4. Delivery of Dock Branch Park South and the Kings Square Link – active travel and open space interventions including the southern sections of Dock Branch Park.
The proposed primary enabling works package will be implemented following a detailed design stage, with works expected to start in early 2025 and to be completed in Spring 2027. Plot development in Hind Street South is expected to commence in summer 2027 and developed out over the following 6 years (2033).
This report seeks the required authorisations to enable the council to secure the external grant funding required to undertake the primary enabling works and to enter into the various contracts and land deals that will enable the works to be implemented.
Wirral Working Together – A Council Plan 2023 - 2027 sets out the Council’s vision to secure the best possible future for our residents. The Hind Street – Primary Enabling Works supports the delivery of the following key themes through its role in enabling the development of new homes, new green spaces and active travel links on a site that is currently derelict and contaminated:
• Promoting independence and healthier lives • People focussed regeneration • Protect our environment • Safe, resilient and engaged communities
This matter affects Birkenhead & Tranmere ward.
This is a Key Decision.
Appendices 1 and 2 of this report contains exempt information as defined in Schedule 12A of the Local Government Act 1972. It is in the public interest to exclude the press and public under Paragraph 3 ‘Information relating to the financial or business affairs of any particular person (including the authority holding the information).
RECOMMENDATION/S
The Policy and Resources Committee is requested to:
1. Authorise the Director of Law and Corporate Services to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.