Resolved
Resolved – that shareholder approval be granted for Edsential CIC to enter into the purchase agreement for the acquisition of office accommodation as referred to in the exempt Appendix 1.
Policy and Resources Committee approved this item on Wednesday 2 October 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – that shareholder approval be granted for Edsential CIC to enter into the purchase agreement for the acquisition of office accommodation as referred to in the exempt Appendix 1.
The Policy and Resources Committee is recommended to grant shareholder approval for Edsential CIC to enter into the purchase agreement for the acquisition of office accommodation as referred to in the exempt Appendix 1. SUPPORTING INFORMATION
1.1This recommendation ensures that Edsential can continue to access a high quality, long term central office solution which will accommodate the company’s growth ambitions.
2.0OTHER OPTIONS CONSIDERED
2.1Prior to selecting a preferred option, Edsential explored various alternatives for new office space.
3.0BACKGROUND INFORMATION
3.1On 9 July 2024 Edsential received communication from CWaC that it is required to leave Whitby Hall Lodge within 6 months. The Lodge is required by CWaC to facilitate regeneration of Ellesmere Port.
3.2Edsential conducted a search of office facilities within 3 miles of Ellesmere Port to identify potential units that are currently available in the area. A preferred site was identified as referred to in the exempt Appendix 1, providing a significant quality upgrade on current accommodation. The Edsential board delegated authority to its Managing Director to conduct negotiations to make an offer to purchase this office.
3.3Negotiations and due diligence were undertaken during August 24 and the vendor has accepted Edsential’s offer (as set out in the exempt Appendix 1) subject to contract. The proposed completion date is the 29 November 24.
3.4This option provides Edsential with a high quality, long term central office solution, whilst also providing a physical asset on the balance sheet, which is part of Edsential’s longer-term strategy, to create a business with a positive net book value. It will also reduce future risk around increasing rent costs in a geographic area that is underserved with quality office space.
3.6The purchase requires shareholder approval as it is of a value of over £250k. Engagement meetings have already been held separately with officers from CWaC and Wirral Borough Council. CWaC has stated that the decision is likely to be granted by Officer Decision Notice and no potential issues are foreseen in this regard.
4.1Edsential has confirmed that cash is available to secure the office purchase. This cash has been made available by delaying the repayment of the working capital facility for 1-2 years. The working capital agreement does not have any requirement for reducing the balance to zero before its expiry, therefore this approach is compatible with the company’s contractual responsibilities. The company will also temporarily reduce its target minimum cash holding to c.£200k. 4.2 The building lease will sit on the Edsential balance sheet as a depreciating asset.
4.3The previous office accommodation rental was £24k per annum. This cost will be replaced with a depreciation charge of either £7.25k or £3.2k, depending upon the auditors view on the depreciation period.
4.4Edsential operates independently of its shareholders, receiving income from schools and parents. Should it encounter financial difficulties which threaten its long-term viability the Council would have exposure to risk such as any outstanding cash flows.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Edsential office AccommodationReport | 112 KB | DownloadRead as text |
Follow Policy and Resources Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2026 | New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... | Approved | Open |
| 22 Jul 2026 | Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... | Approved | Open |
| 22 Jul 2026 | Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... | Decided | Open |
| 22 Jul 2026 | Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... | Noted | Open |
| 22 Jul 2026 | Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.