City Region Sustainable Transport Settlement – Highway Structural Maintenance Programme 2025-26
ApprovedCommittee5 papers
Environment, Climate Emergency and Transport Committee approved this item on Tuesday 11 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved – That (1) the proposed programme of works for Wirral’s Carriageways, Footway Improvements and Bridge Maintenance for 2025/26 be approved, using any relevant grant funding allocated to the Council by the Liverpool City Region Combined Authority in the City Region Sustainable Transport Settlement - Highways Structural Maintenance allocation, and the spending of the associated grant funding on these works, once accepted by the Council’s Section 151 Officer, as set out in Appendix 2 to this report; (2) the indicative Red, Amber, Green rated highway network condition matrix as set out in Appendix 4 to this report be approved, to be used by the Director of Neighbourhood Services as one of the decision tools when developing the Council’s highway structural maintenance programmes. (3) the Director of Neighbourhood Services be authorised to revise or amend the delivery or implementation of the work programmes, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee; and (4) the Director of Law and Corporate Services be authorised to negotiate and finalise any grant funding agreements on behalf of the council, amongst the relevant subject areas over the next 3 years, as set out in Appendix 1 to this report and for any additional grant funding received during this period relevant to the subject area.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
ENVIRONMENT, CLIMATE EMERGENCY AND TRANSPORT COMMITTEE Tuesday, 11 March 2025
REPORT TITLE: CITY REGION SUSTAINABLE TRANSPORT SETTLEMENT – HIGHWAY STRUCTURAL MAINTENANCE PROGRAMME 2025-26 REPORT OF: DIRECTOR OF NEIGHBOURHOOD SERVICES
REPORT SUMMARY
This report requests approval for the disbursement of grant funding from the Liverpool City Region Combined Authority’s (LCRCA) City Region Sustainable Transport Settlement (CRSTS) for 2025/26 into the Council’s Capital Programme for Highways Structural Maintenance and Bridge Maintenance. The report also recommends acceptance of an indicative highway condition matrix that will be used to inform future programme investment decisions.
The report supports the Council Plan Wirral Working Together 2023-27, specifically the themes: People-Focussed Regeneration and Safe, Resilient and Engaged Communities and Protecting Our Environment.
This is a Key Decision because of the value of the programme of works and the services carried out under this programme of works affects all wards.
RECOMMENDATION/S
The Environment, Climate Emergency and Transport Committee is recommended to approve:
1. the proposed programme of works for Wirral’s Carriageways, Footway Improvements and Bridge Maintenance for 2025/26, using any relevant grant funding allocated to the Council by the Liverpool City Region Combined Authority in the City Region Sustainable Transport Settlement - Highways Structural Maintenance allocation, and the spending of the associated grant funding on these works, once accepted by the Council’s Section 151 Officer, as set out in Appendix 2 to this report;
2. the indicative Red, Amber, Green rated highway network condition matrix as set out in Appendix 4 to this report, to be used by the Director of Neighbourhood Services as one of the decision tools when developing the Council’s highway structural maintenance programmes;
3. that the Director of Neighbourhood Services be authorised to revise or amend the delivery or implementation of the work programmes, as deemed necessary, having due regard for the available resources and applicable risk-based prioritisation of locations selected for intervention and treatment, in consultation with the Chair and Party Spokespersons of the Environment, Climate Emergency and Transport Committee; and
4. that the Director of Law and Corporate Services be authorised to negotiate and finalise any grant funding agreements on behalf of the council, amongst the relevant subject areas over the next 3 years, as set out in Appendix 1 to this report and for any additional grant funding received during this period relevant to the subject area. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The recommendations within this report are designed to ensure that the Council can comply with its statutory duty, to maintain the public highway in Wirral, as set out in the Highways Act 1980, the Road Traffic Regulations Act 1984, the Road Traffic Act 1988, the Local Government Act 2000, and the Traffic Management Act 2004.
1.2An element of this funding will be specifically allocated to the Council for delivery of schemes on the Liverpool City Region’s Key Route Network, supporting the Council’s main strategic routes providing links to economic growth and regeneration sites and cannot be used for any other purpose. The Council will inevitably incur risk reputational damage should it not accept funding specifically allocated to invest in the Key Route Network.
2.0OTHER OPTIONS CONSIDERED
2.1The Committee could decide to not utilise the grant funding offered. This is not considered to be an appropriate option given that the programme identified within this report enables the Council to comply with its statutory duties.
3.0BACKGROUND INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.