AI summaryWirral Planning Committee notes and endorses planning application performance report, showing 100% of major applications decided on time in the first two quarters of 2025/26.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlanning performance update for information
MoneyNo financial sums in the report
What happens nextPerformance kept under reviewContinued monitoring against designation thresholds
Who it affectsAll wards in the boroughCouncil-wide planning performance

What was decided

The Planning Committee noted and endorsed the development management performance report covering the speed of determining planning applications. Report P5

The report confirmed the local planning authority is not at risk of designation for underperformance, as the speed of decision thresholds are being comfortably exceeded. Report 3.9, 5.0

Why

Members needed an update on the performance of the Development Management Service in processing planning applications against government targets. Report P4

If an authority is designated as underperforming, applicants could submit planning applications directly to the Secretary of State, so the risk is actively monitored. Report 4.0, 5.0

What happens next

Performance will continue to be tracked against statutory and extended timescales, with priorities adjusted as needed to reduce designation risk. Report 4.0

Quality of decisions is reported separately in the accompanying Planning Appeals Performance Report, also before this Committee.

Options considered

  • Chosen: Note and endorse the performance report. Report is for information, no alternative options are recommended Report P5, 2.0

Implications

  • Risk: Designation as an underperforming authority would let applicants submit applications direct to the Secretary of State; current performance is well above thresholds. Report 3.9, 5.0
  • Legal: The Government monitors planning performance on speed and quality; minimum standards must be met or special measures are applied. Report 5.0
  • Staffing: No resource implications arising from this report. Report 6.0
  • Equalities: No equality implications arising from the proposals. Report 9.0
  • Climate: Recommendations are expected to have no impact on greenhouse gas emissions. Report 10.0
  • Other: No direct community wealth implications arising from this report. Report 11.0

Who and where

  • Applicants for planning permission across all wards in the borough Report P4
  • The Development Management Service at Wirral Council Report P4

Timeline

  • 2023/24 year: Majors decided on time 81%; Non-Majors 85%; All 85%. Report 3.8, P11, P12, P13
  • 2024/25 year: Majors decided on time 88%; Non-Majors 90%; All 90%. Report 3.8, P11, P12, P13
  • 2024/25 Q3: Majors 50% (2/4); Non-Majors 92% (243/265). Report 3.8, P11, P12
  • 2024/25 Q4: Majors 85% (23/27); Non-Majors 92% (222/246). Report 3.8, P11, P12
  • 2025/26 Q1: Majors 100% (2/2); Non-Majors 95% (245/257); All 95% (247/259). Report 3.8, P11, P12, P13
  • 2025/26 Q2: Majors 100% (4/4); Non-Majors 96% (214/223); All 96% (218/227). Report 3.8, P11, P12, P13
  • 5th June 2025: Previous report to Planning Committee. Report P23

Plain English for the jargon

  • Major application: Residential development of 10 or more units, or retail or commercial development of 1,000 square metres or more of additional floor area. Determined within 13 weeks.
  • Minor and Other applications: Residential of fewer than 10 units, retail or commercial under 1,000 square metres, plus advertisements, listed building and householder proposals. Determined within 8 weeks.
  • EIA applications: Applications subject to an Environmental Impact Assessment, determined within 16 weeks.
  • Designation: Status applied by government to underperforming authorities, allowing applicants to submit applications direct to the Secretary of State.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

Resolved – That the report be noted and endorsed.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Planning Committee

PLANNING COMMITTEE 6 NOVEMBER 2025

REPORT TITLE DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - PLANNING APPLICATIONS

REPORT OF ASSISTANT DIRECTOR – CHIEF PLANNER

REPORT SUMMARY The purpose of this report is to update Members on the performance of the Development Management Service with regard to determining planning applications. The report outlines performance against government targets in terms of the speed of processing all applications. This matter affects all Wards within the Borough.

RECOMMENDATION Planning Committee is recommended to note and endorse the performance report.

SUPPORTING INFORMATION

1.0REASONS FOR RECOMMENDATION 1.1 To enable Members to be updated on the performance of the Development Management Service with regard to the speed of determination of planning applications.

2.0OTHER OPTIONS CONSIDERED 2.1 As this report is for information no alternative options are recommended.

3.0BACKGROUND INFORMATION Development Management Performance 3.1 The statutory time limits for planning applications are set out in the Town and Country Planning (Development Management Procedure (England)) Order 2015 (as amended). These time limits are as follows: (a) Major Applications Major applications should be determined within 13 weeks. Major applications are defined as residential development of 10 or more units or retail/ commercial development of 1,000 square metres or more of additional floor area. (b) Minor & Other Applications Minor and Other applications should be determined in 8 weeks. Minor applications are defined as residential development of less than 10 units or retail/commercial development of less than 1,000 square metres of additional floor area; Other applications include advertisements, listed building and householder proposals. (c) Applications subject to an Environmental Impact Assessment These applications should be determined within 16 weeks. Measures to address issues with underperforming Authorities 3.2 Section 62A of the Town and Country Planning Act 1990 allows underperforming Authorities to be ‘designated’, which could result in applications being made directly to the Secretary of State for Housing Communities and Local Government. The two criteria used to assess whether Local Authorities are performing to the required standard are Speed of Decisions and Quality of Decisions. Speed of Decisions 3.3 The measure to be used is the percentage of decisions on applications made: (i) within the statutory determination period; or (ii) within such extended period as has been agreed in writing between the applicant and the local planning authority. 3.4 Currently, 60% of Major applications must be determined within 13 weeks or within the extended period agreed with the applicant; and 70% of non-major applications should be determined within 8 weeks or within the extended period agreed with the applicant. Quality of Decisions 3.5 The measure to be used is the percentage of decisions on applications for Major development that have been overturned at appeal, once nine months have elapsed following the end of the assessment periods recorded in the data collected by the Department of Housing Communities and Local Government. 3.6 Currently the threshold for designation is 10% or more of all an authority’s decisions on applications for Major and Non-Major applications being overturned on appeal. Performance – Speed of Decisions 3.7 In line with the Criteria for Designation, applications are now recorded in two categories - Major and Non-Major applications.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE: PLANNING APPLICATIONSReport 411 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 15 attended
SK
Councillor Stuart KellyChair, present
SF
Councillor Steve FoulkesVice-Chair, present
GM
Councillor Grahame McManusCommittee Member, present
LL
Councillor Louise Luxon-KewleyCommittee Member, present
PS
Councillor Paul StuartCommittee Member, present
TJ
Councillor Tony JonesCommittee Member, expected
GB
Councillor Gary BennettCommittee Member, present
AG
Councillor Andrew GardnerSpokesperson, present
MJ
Councillor Mary JordanCommittee Member, present
HG
Councillor Harry GormanSpokesperson, apologies, sent representative
JW
Councillor Jason Walsh - McDonaldCommittee Member, present
NF
Nicky FolanOfficer, expected

All 15 on the meeting page

On this subject at Wirral

Search all
  1. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - PLANNING APPLICATIONSThis decision
  2. Development management performance update - planning applicationsDecided
  3. Development management performance update - planning appealsDecided
  4. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - ENFORCEMENT ACTIVITY BETWEEN: 1st OCTOBER 2025 & 31st DECEMBER 2025 AND 1st JANUARY 2026 & 31ST MARCH 2026Decided
  5. Development management performance update - planning enforcementNoted
  6. Development management performance update - planning appealsNoted

More from Wirral Planning Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 MINUTESResolved – That the minutes of the Planning Committee held on 13 August 2026 be approved as a correct record. The Cha... Approved Open
10 Sep 2026 ADV/26/00958 - Corner Of Duke Street and Beckwith Street, Birkenhead, Wirral, CH41 8BBResolved (unanimously) – That the Assistant Director - Chief Planner be authorised to refuse the application, due to ... Refused Open
10 Sep 2026 APPH/26/01027 - 5 Woodcote Bank, Higher Bebington, Birkenhead, Wirral, CH42 4NLResolved – That the Planning Committee was content for the application to be withdrawn from the agenda and returned t... Decided Open
10 Sep 2026 APP/26/00691 - Lighthouse Inn, 228 Wallasey Village, Wallasey, Wirral, CH45 3LPResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open
10 Sep 2026 APP/26/00814 - Grove House Hotel, 45 Grove Road, Wallasey Village, WirralResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open