CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council
Planning Committee, Thursday 6 November 2025

DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - PLANNING ENFORCEMENT

Noted Planning 1 paper

AI summaryWirral Planning Committee notes planning enforcement performance: 278 open cases as of 27th October 2025, with 68% to 73% reaching the 13-week milestone target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlanning Committee noted and endorsed the performance update
MoneyNo direct financial implicationsReport states no direct financial implications
What happens nextNot stated
Who it affectsResidents and property owners in WirralAnyone reporting or subject to planning enforcement

What was decided

Wirral Planning Committee noted and endorsed the planning enforcement performance update for the period. Report P1

The committee accepted performance below the 80% target, with 73% and 68% of cases reaching the 13-week key milestone in the two quarters reported. Report P13, P15, 3.4, 3.5

Why

The update enables members to monitor the Development Management Service's planning enforcement activity.

Enforcement is being carried out in accordance with the Council's Planning Enforcement Policy, and no alternative options are recommended. Report 2.1, 3.1

Retention of officers has eliminated the backlog, allowing progress on long-standing cases, though this has reduced performance against key milestone targets.

What happens next

Officers to continue serving formal notices where negotiation fails, with 11 further Listed Building Enforcement Notices already drafted for service at Hamilton Square. Report 3.8, P22

Resource levels to be kept under review as enforcement demand remains high.

Justifications for any future enforcement notices to be set out in clearly reasoned reports to mitigate appeal risk.

Options considered

  • Chosen: Continue current enforcement approach under the Planning Enforcement Policy. Activity is being carried out in accordance with the policy and no alternative options are recommended Report 2.1, 3.1

Implications

  • Legal: Enforcement action is discretionary under Section 172(1) of the Town and Country Planning Act 1990, as reflected in paragraph 59 of the National Planning Policy Framework.
  • Staffing: Retention of officers has eliminated the backlog, though it has had a negative impact on key milestone targets; resources will be closely monitored.
  • Risk: Enforcement notices may be challenged by appeal to the Planning Inspectorate; mitigation is to ensure decisions follow the development plan and are clearly reasoned.
  • Equalities: No equality implications arise from the report. Report 9.0
  • Climate: The recommendations are expected to have no impact on greenhouse gas emissions. Report 10.0
  • Financial: No direct financial implications arise from this report. Report 4.0

Who and where

  • Residents and property owners in Wirral subject to suspected breaches of planning control Report 3.1, 3.6
  • Owners of listed buildings in and around Hamilton Square, Birkenhead Report P22, P39, P40, P41
  • People reporting possible breaches of planning control and works to protected trees Report 3.1, 3.6

Timeline

  • 1st April 2025 to 30th June 2025: 91 enforcement cases opened, 94 closed; 73% (69 out of 94) reached key milestone within 13 weeks Report 3.4, P12, P13
  • 5th June 2025: Previous performance report presented to Planning Committee, with 283 open cases Report 3.3, P35
  • 1st July 2025 to 30th September 2025: 103 cases opened, 138 closed; 68% (87 out of 128) reached key milestone within 13 weeks Report 3.5, P15
  • 27th October 2025: 278 open enforcement cases under active investigation Report 3.3

Plain English for the jargon

  • Key milestone: A defined point in a case: no breach found, retrospective application submitted, breach remedied through negotiation, formal action taken, deemed not expedient, or time limit passed.
  • LBEN: Listed Building Enforcement Notice, served where works to a listed building are carried out without listed building consent.
  • S106 agreement: A planning obligation agreement under Section 106 of the Town and Country Planning Act, which the enforcement service monitors.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

Resolved – That the report be noted and endorsed.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Planning Committee

Recommendations

Planning Committee recommended to note and endorse the performance update.

SUPPORTING INFORMATION

1.0REASONS FOR RECOMMENDATION 1.1 To enable Members to be updated on the performance of the Development Management Service regarding its planning enforcement activity.

2.0OTHER OPTIONS CONSIDERED

2.1As the Council’s Planning Enforcement activity is being undertaken in accordance with the Council’s Planning Enforcement Policy, no alternative options are recommended. 3.0 BACKGROUND INFORMATION

Performance and Workloads

3.1The Council’s Planning Enforcement Policy sets out how the enforcement service will be delivered and defines the standards to be met. The Council aims to send an acknowledgement letter to the complainant within 5 working days of receipt of the enquiry and to conduct a first site visit within 15 working days.

3.2The Council also aims for 80% of cases to reach a ‘key milestone’ within 13 weeks of receipt of the initial enquiry. A key milestone is one of the following dates on which:

 It is established that there has been no breach of planning control;  A retrospective planning application is submitted;  A breach of planning control is remedied through negotiation;  It is deemed not to be expedient to take formal enforcement action;  Formal action (such as the service of an enforcement notice) is taken; or  It is established that the time limit has passed for the Council to take enforcement action.

3.3As of 27th October 2025, the total number of open enforcement cases under active investigation was 278 cases. When the last performance report was presented to Planning Committee on 5th June 2025, the total number of open cases was 283 cases.

3.4The following two tables set out the performance of the enforcement service between 1st April 2025 and 30th June 2025

Total number of No. of cases closed enforcement cases opened 91 94

No. of cases reached % of cases reaching key milestone key milestone within 13 weeks 94 73% (69 out of 94)

3.5The following two tables set out the performance of the enforcement service between 1st July 2025 and 30th September 2025 Total number of No. of cases closed enforcement cases opened 103 138

No. of cases reached % of cases reaching key milestone key milestone within 13 weeks 128 68% (87 out of 128)

3.6The majority of the Planning Enforcement work is reactive, responding to reports about possible breaches of planning control, determining applications for works to protected trees, and monitoring of S106 agreements.

Formal Enforcement Action 3.7 Paragraph 60 of the National Planning Policy Framework states ‘Effective enforcement is important to maintain public confidence in the planning system. Enforcement action is discretionary, and local planning authorities should act proportionately in responding to suspected breaches of planning control….’

3.8Formal action should only be taken as a last resort when all attempts to resolve the matter informally have been exhausted. Formal notices (being enforcement notices or breach of condition notices) are therefore, only served in cases where negotiation has not proven successful, and it is expedient to do so. The majority of cases are resolved through negotiation.

3.9Between 1st April 2025 & 30th June 2025, 2 Enforcement Notices and 4 Listed Building Enforcement Notices were issued as listed in Appendix 1 of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE: PLANNING ENFORCEMENTReport 750 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 15 attended
SK
Councillor Stuart KellyChair, present
SF
Councillor Steve FoulkesVice-Chair, present
GM
Councillor Grahame McManusCommittee Member, present
LL
Councillor Louise Luxon-KewleyCommittee Member, present
PS
Councillor Paul StuartCommittee Member, present
TJ
Councillor Tony JonesCommittee Member, expected
GB
Councillor Gary BennettCommittee Member, present
AG
Councillor Andrew GardnerSpokesperson, present
MJ
Councillor Mary JordanCommittee Member, present
HG
Councillor Harry GormanSpokesperson, apologies, sent representative
JW
Councillor Jason Walsh - McDonaldCommittee Member, present
NF
Nicky FolanOfficer, expected

All 15 on the meeting page

On this subject at Wirral

Search all
  1. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - PLANNING ENFORCEMENTThis decision
  2. Development management performance update - planning applicationsDecided
  3. Development management performance update - planning appealsDecided
  4. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - ENFORCEMENT ACTIVITY BETWEEN: 1st OCTOBER 2025 & 31st DECEMBER 2025 AND 1st JANUARY 2026 & 31ST MARCH 2026Decided
  5. Development management performance update - planning applicationsNoted
  6. Development management performance update - planning appealsNoted

More from Wirral Planning Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 MINUTESResolved – That the minutes of the Planning Committee held on 13 August 2026 be approved as a correct record. The Cha... Approved Open
10 Sep 2026 ADV/26/00958 - Corner Of Duke Street and Beckwith Street, Birkenhead, Wirral, CH41 8BBResolved (unanimously) – That the Assistant Director - Chief Planner be authorised to refuse the application, due to ... Refused Open
10 Sep 2026 APPH/26/01027 - 5 Woodcote Bank, Higher Bebington, Birkenhead, Wirral, CH42 4NLResolved – That the Planning Committee was content for the application to be withdrawn from the agenda and returned t... Decided Open
10 Sep 2026 APP/26/00691 - Lighthouse Inn, 228 Wallasey Village, Wallasey, Wirral, CH45 3LPResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open
10 Sep 2026 APP/26/00814 - Grove House Hotel, 45 Grove Road, Wallasey Village, WirralResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies