Electrical - Schedule of Rates Contract

Approved Committee 1 paper

AI summaryWirral Policy and Resources Committee approved a procurement exercise for electrical services on council land and property, using a dynamic purchasing system worth an estimated £3m over up to four years, with a focus on local suppliers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedElectrical services via dynamic purchasing system
Money£3m estimated contract valueOver up to four years
What happens nextTender process to beginAward by Assistant Director of Property and Investment
Who it affectsCouncil land and propertyPlanned, reactive and emergency electrical works

What was decided

The committee approved the start of a compliant procurement exercise using a dynamic purchasing system for electrical services covering planned preventive maintenance, reactive repairs and emergency repairs on council land and property. Report 5.1

The estimated contract value is £3m over a period of up to four years, with an emphasis on encouraging local organisations to participate. Report 11.1

The Assistant Director of Property and Investment was authorised to award the new contract to the most economically advantageous tenderer. Report 5.2

Why

A contract in place reduces significant risks and provides certainty for service provision, particularly reactive maintenance. Report 7.1

Procurement and renewal of the contract will support compliance with statutory obligations including Health and Safety and Construction Design Management regulations. Report 7.4

The approach supports the Corporate Landlord Model, shifting delivery away from a reactive model towards a more planned and proactive one, with priority response times for emergency work. Report 7.4

What happens next

A compliant procurement exercise will commence using a dynamic purchasing system, with the option to use existing public sector framework arrangements where possible. Report 5.1, 5.4

The Assistant Director of Property and Investment will award the new contract to the most economically advantageous tenderer, with a formal contract drawn up by the council legal team. Report 5.2, 5.3

The contract will be managed through monthly meetings between the council and the selected contractors, on site checks and inspections, and Key Performance Indicators on response times. Report 6.2

The money

  • £3m Estimated contract value over up to four years for electrical services

Options considered

  • Chosen: Procure electrical services via a dynamic purchasing system with an estimated £3m value over up to four years. Allows flexible and inclusive procurement, encourages local participation, and reduces risks of non-compliance Report 5.1, 7.4, 11.1

Implications

  • Legal: Commissioning will follow the Public Contract Regulations 2015 and the Council's Contract Procedure Rules, with a formal contract drawn up by the legal team. Report 5.1, 5.3
  • Risk: Risks managed through the procurement process, including bidders' approach to Health and Safety and Construction Design Management compliance. Report 7.2, 7.3
  • Equalities: No specific equality implications identified, though absence of a contract could affect availability of assets for some groups. Report 9.2
  • Climate: A compliant contractor will be used to remove and dispose of waste, safeguarding land and reducing risk to public health, and works will align with environment, biodiversity and climate change duties. Report 10.1, 10.2
  • Staffing: Procurement will be managed within existing resources, with monthly meetings, on site checks and Key Performance Indicators in place. Report 6.1, 6.2
  • Other: Social Value will be measured through the National Themes, Outcomes and Measures framework, with tenderers proposing credible targets aligned to Wirral Working Together 2023-2027, the Local Plan 2022-2040 and the Social Value Policy. Report 11.2, P21

Who and where

  • Owners and users of council land and property
  • Local electrical contractors and suppliers, who are encouraged to participate Report 11.1
  • The council's asset management service, which will manage the contract Report 6.2

Timeline

  • 15th February 2023: Previous Policy and Resources Committee meeting referenced in subject history Report P26
  • Up to four years: Length of the new electrical works schedule of rates contract

Plain English for the jargon

  • DPS (Dynamic Purchasing System): A flexible electronic procurement process open to qualifying suppliers throughout its life.
  • Most Economically Advantageous Tenderer (MEAT): The bidder judged to offer the best combination of price, quality and other criteria.
  • Corporate Landlord Model: An approach in which the council manages its property portfolio as a single, strategic asset.
  • CDM regulations: Construction Design and Management regulations covering health and safety duties for construction work.
  • National TOMs: The National Themes, Outcomes and Measures framework used to measure Social Value.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item70

Resolved

Resolved – That, 1. the commencement of a compliant procurement exercise, utilising a dynamic purchasing system (DPS) to enable flexible and inclusive procurement, with a particular emphasis on encouraging local organisations to participate, for the provision of electrical services for planned preventive maintenance, reactive repairs and emergency repairs in relation to the Council's land and property with an estimated contract value of £3m, over a period of up to four years be approved; and 2. the Assistant Director of Property and Investment be approved to award the new Electrical Works Schedule of Rates contract to the Most Economically Advantageous Tenderer.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

POLICY AND RESOURCES COMMITTEE 19 November 2025

REPORT TITLE: ELECTRICAL WORKS SCHEDULES OF RATES CONTRACT REPORT OF: ASSISTANT DIRECTOR: PROPERTY AND INVESTMENT

REPORT SUMMARY

The purpose of this report is to seek approval to procure a provider for the provision of electrical works, following a compliant procurement process. The process identified is a dynamic purchasing system. Following identification of the preferred bidder, it would be appointed. It is proposed that the contract period would be for two years with the option to extend for a further year on two occasions. A contract for electrical works is a key component to the management of the Council's land and property.

The procurement process and subsequent award of the new electrical works schedule of rates contract will allow the Council's Facilities Management team to deliver electrical services, emergency repairs, reactive repairs, planned preventative maintenance work and planned servicing/testing on the Council's land and property portfolio. This includes minor capital maintenance works.

As this contract will impact the whole of the Council's asset portfolio it supports all of the themes of the Council Plan, Wirral working together 2023-27.

This report relates to maintenance of the Council's assets, which are across the borough. Therefore, this report affects all wards. Due to the potential contract value, this is a key decision.

RECOMMENDATION/S

The Policy and Resources Committee is recommended to:

1. approve the commencement of a compliant procurement exercise, utilising a dynamic purchasing system (DPS) to enable flexible and inclusive procurement, with a particular emphasis on encouraging local organisations to participate, for the provision of electrical services for planned preventive maintenance, reactive repairs and emergency repairs in relation to the Council's land and property with an estimated contract value of £3m, over a period of up to four years; and 2. authorise the Assistant Director of Property and Investment to award the new Electrical Works Schedule of Rates contract to the Most Economically Advantageous Tenderer. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATIONS

1.1Wirral Borough Council has a vast array of ageing properties across its portfolio. This proposed contract is for the planned service, Electrical Installation Condition Report (EICR) 5 yearly testing rolling programme, repair, and maintenance of all electrical installations, including out of hours emergency working, to buildings owned by the Council or in which the Council has an interest e.g., libraries, leisure centres and schools within the administrative boundaries of the Council. The Contract ensures lighting is managed correctly and accordingly in line with current Health and Safety Legislation. Ensuring that the Council has the ability to appoint contractors to do this work is an essential step to take.

1.2Presently the Facilities Management team provide planned and reactive maintenance services for the Council's land and property either directly or on behalf of the Council's service areas. In addition, the Council is implementing a Corporate Landlord Model, whereby ultimately this team will be responsible for the maintenance of Council owned land and buildings in the future, excepting schools, which have differing management arrangements. The Council's property portfolio is comprised of a mixture of operational and non-operational assets, ranging from offices and publicly accessed venues, commercial and retail properties, assets held for regeneration and schools.

1.3The Council has a statutory duty to ensure that its assets comply with relevant Health and Safety legislation and Regulations. Not having a solution in place to deal with this type of work would negatively impact the Council's ability to comply with its obligations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electrical: Schedule of Rates ContractReport 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 21 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, present
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 21 on the meeting page

On this subject at Wirral

Search all
  1. Electrical - Schedule of Rates ContractThis decision
  2. Schedule of Rates Contract for Electrical WorksApproved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies