2025-26 Capital Monitoring Quarter 2

Approved Committee 6 papers

AI summaryPolicy and Resources Committee recommends Council approve a revised 2025/26 Capital Programme of £96.708 million, including an £8 million reallocation to Central Birkenhead and additional Public Sector Decarbonisation match funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised programme, Central Birkenhead reallocation, PSDS top-up
MoneyNot stated
What happens nextDecision referred to CouncilFinal approval needed at Full Council
Who it affectsAll directorates, especially Regeneration and PlaceAnd Neighbourhoods for decarbonisation works

What was decided

Recommend Council approve a revised Capital Programme of £96.708 million for 2025/26, including the virements listed in Appendix 3. Report P2

Recommend Council approve the reallocation of funding to the Central Birkenhead Programme to mitigate an £8.000 million forecast overspend. Report P3, P29

Recommend Council approve additional match funding of £0.403 million for the Public Sector Decarbonisation Scheme 4. Report P4, P50, P51

Why

Regular capital monitoring enables faster decisions and improves financial control, with quarterly reporting being standard practice. Report 1.1, 2.1

Several budget allocations no longer require borrowing and can be vired to cover the Central Birkenhead overspend. Report P29

Match funding is a condition of the £13.757 million PSDS grant for decarbonising council buildings. Report P38, P51

What happens next

The decision is referred to Full Council for final approval. Report P96, P97, P98

Further reductions or reprofiling of budget are expected in future quarters; the Central Birkenhead project is due to complete by 9th March 2026. Report P17, P21, P27

Members will be updated on any reliance on a £7.500 million capitalisation direction for 2025/26 in future monitoring reports. Report P55

The money

  • £96.708 million Revised Capital Programme 2025/26 forecast position at 30 Sep 25 Report P2, P13, P44
  • -£30.664 million Variance between original budget and 30 Sep 25 forecast Report P13, P44
  • £8.000 million Central Birkenhead forecast overspend to be mitigated by virement Report P29
  • £5.250 million Virement from Wirral Waters Investment Fund to Central Birkenhead Programme Report P56
  • £0.403 million Additional match funding for the Public Sector Decarbonisation Scheme 4 Report P50, P51
  • £13.757 million PSDS grant awarded towards decarbonising council buildings Report P38, P51
  • £31.837 million Forecast borrowing required in 2025/26 to finance the Capital Programme Report P44, 4.2

Options considered

  • Chosen: Approve revised Capital Programme and virements. Regular monitoring is standard practice and improves financial control Report 1.1, 2.1
  • Rejected: Other reporting frequencies than quarterly. Quarterly reporting is a standard practice Report 2.1

Implications

  • Financial: Reprofiling reduces 2025/26 borrowing costs but delays MRP into future years; permanent savings only arise if schemes cease. Report P17, P45, 4.4
  • Legal: The Council must set a balanced budget under the Local Government Finance Act 1992 and Local Government Act 2003, and members must consider their fiduciary duty. Report 5.1, 5.2
  • Risk: Central Birkenhead contract carries ongoing risk: the contractor has projected a potential £0.578 million gain payment and £0.345 million risk on remaining works, subject to negotiation. Report P28
  • Risk: Risks of contractor insolvency and inflationary pressures on building materials are monitored on each scheme. Report P24
  • Climate: The Programme supports the Council's Climate Emergency Plan through decarbonisation, energy efficient buildings, sustainable travel, street lighting, tree planting and flood alleviation. Report 10.0, 10.2
  • Staffing: No additional staffing, ICT or asset requirements arise directly; the Programme is managed within existing directorate structures. Report 6.0, 6.1
  • Equalities: Members must consider both fiduciary duty and the public sector equality duty when making budget decisions. Report 9.1, 9.2

Who and where

  • Central Birkenhead area, including Conway Street, Europa Boulevard, Grange Road and Charing Cross junction Report P27
  • Council taxpayers of Wirral (fiduciary duty referenced) Report 5.2
  • Liverpool City Region Combined Authority (joint decarbonisation partner) Report P33, P38
  • People owed homelessness duties by the council (additional temporary accommodation units) Report P35

Timeline

  • 2025/26: Revised Capital Programme of £96.708 million to be delivered Report P2, P13
  • 9th March 2026: Planned completion date for Central Birkenhead Programme, now 80% complete Report P27
  • 2027/28: £0.250 million borrowing attached to PSDS scheme to be incurred (Year 3) Report P39
  • 2025 to 2028: Green Heat Network Fund grant profiled following £0.250 million spend in 2024/25 Report P37
  • To be determined: Whether the £7.500 million capitalisation direction will be used in 2025/26 Report P55

Plain English for the jargon

  • MRP (Minimum Revenue Provision): Amount the Council must set aside each year from revenue to repay borrowing used to fund capital expenditure.
  • Virement: Reallocation of budget from one scheme or heading to another within the Capital Programme.
  • PSDS (Public Sector Decarbonisation Scheme): Government grant programme funding decarbonisation works on public sector buildings.
  • UKSPF (UK Shared Prosperity Fund): Government fund supporting local growth and community projects.
  • Capitalisation direction: Exceptional approval allowing a council to treat some revenue spending as capital, financed by borrowing.
  • Annuity Method: Approach to MRP calculation adopted by Wirral Council, producing principal repayments that start low and increase each year.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item65

Resolved

Resolved – that, Council be recommended to approve: 1. the revised Capital Programme of £96.708 million for 2025/26, including the virements of budget referred to in Appendix 3 of this report. 2. the reallocation of funding to the Central Birkenhead Programme referred to in section 3.3.7 in this report. 3. additional funding for the scheme referred to in section 3.8 in this report.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendations

The Policy and Resources Committee is requested to recommend to Council the approval of:

1 the revised Capital Programme of £96.708 million for 2025/26, including the virements of budget referred to in Appendix 3 of this report.

2 the reallocation of funding to the Central Birkenhead Programme referred to in section 3.3.7 in this report.

3 additional funding for the scheme referred to in section 3.8 in this report. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Borough Council.

2.0OTHER OPTIONS CONSIDERED

2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.

3.0BACKGROUND INFORMATION

3.1Tables 1 and 2 provide an update on the 2025/26 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed in March 2025. These include the reprofiling of expenditure into and out of financial years, inclusion of additional grant funded schemes and variations to spend forecasts. Appendix 1 of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.

3.1.1 Capital Programme 2025/26 Position by Directorate

Table 1: Wirral Council 2025/26 Forecast Position

Budget Budget Actuals Variance Programme 1 Apr 25 30 Sep 25 30 Sep 25 £m £m £m £m Adult Care & Health 1.675 0.283 -1.392 0.078 Children, Families & Education 13.992 9.373 -4.619 2.908 Finance 5.883 5.802 -0.081 0.648 Neighbourhoods 18.100 18.926 0.826 6.208 Regeneration & Place 87.722 62.324 -25.398 25.848 Total 127.372 96.708 -30.664 35.690 Capital Programme 2025/26 Position by Committee

Table 2: Wirral Council 2025/26 Forecast Position

Budget Budget Actuals Variance Programme 1 Apr 25 30 Sep 25 30 Sep 25 £m £m £m £m Adult Social Care & Health 1.675 0.283 -1.392 0.078 Children, Young People & Education 13.992 9.373 -4.619 2.908 Economy, Regeneration & Housing 83.310 61.344 -21.966 25.827 Environment, Climate Emergency & Transport 21.081 18.924 -2.157 6.142 Policy & Resources 5.883 5.802 -0.081 0.648 Tourism, Communities, Culture & Leisure 1.431 0.982 -0.449 0.086 Total 127.372 96.708 -30.664 35.690

3.1.2 As noted above, the main movements in this year’s Programme are in respect of reprofiling of budget into future years along with the inclusion of new funding and schemes into the Programme. A full breakdown can be found in Appendix 1.

3.1.3 It is anticipated that further reductions and/or reprofiling of budget will be made in future quarters. Such reprofiling reduce the borrowing costs incurred during the year (2025/26) and also delays the resultant Minimum Revenue Provision charges into future years. Any delay in outputs will be monitored by project managers and practical implications reported to the appropriate committee.

3.2Reprofiling of expenditure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-26 Capital Monitoring Quarter 2Report 200 KB DownloadRead as text
PDF
Capital Programme MovementsAppendix 1 57 KB Download
PDF
Scheme UpdatesAppendix 2 107 KB Download
PDF
Virements Within Quarter 2Appendix 3 69 KB Download
PDF
Revised Capital Programme 2025/26Appendix 4 183 KB Download
PDF
Future ActivityAppendix 5 58 KB Download

At this meeting

Whole meeting

Who was there

21 of 21 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, present
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 21 on the meeting page

On this subject at Wirral

Search all
  1. 2025-26 Capital Monitoring Quarter 2This decision
  2. Capital Monitoring Quarter 1 (2026/27)Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. Capital Monitoring Quarter 3 2025/26Approved
  5. 2025-26 capital monitoring quarter 2Approved
  6. Capital Monitoring Quarter 1 2025/26Approved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open