Wirral Borough Council
Policy and Resources Committee, Wednesday 17 December 2025

Regeneration Action Plan

Noted Committee 2 papers

AI summaryWirral's Policy and Resources Committee has endorsed a regeneration action plan to reset the Birkenhead 2040 programme, with no new funding approved and structural changes over 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlan in Appendix 1 noted and endorsed
MoneyNo new moneyFunded from existing allocations, investment, grants
What happens nextRefresh 2040 visionNew operating model for capital schemes
Who it affectsBirkenhead Left BankResidents, partners, and council staff

What was decided

The committee noted the report and endorsed the action plan set out in Appendix 1. Report P1

The plan resets regeneration delivery against the existing 2040 framework, covering short, medium and longer term actions. Report 3.3, 3.1

The Birkenhead 2040 Vision and Framework will be refreshed, alongside a review of the Wirral Growth Company and options such as a Mayoral Development Company. Report 3.14

Why

To address governance weaknesses and financial risks highlighted in the Regeneration Review and the internal audit of November 2025. Report 1.1, 3.1

To ensure regeneration activity aligns with the council's financial recovery plan and statutory duties. Report 1.1, 3.37

To bring clarity and stability to governance and delivery of complex regeneration projects. Report 1.2

What happens next

Refresh the Birkenhead 2040 Vision and Framework, with workshops for Group Leaders and the Economy, Regeneration and Housing Committee. Report 3.15, 8.1

Implement a revised operating model and governance for capital scheme delivery over the next six months. Report 3.31

Appoint an Executive Director for Place and an Assistant Director for Capital Programmes, and restructure the Regeneration and Place directorate. Report 3.17, 3.18, 6.1

Options considered

  • Rejected: Continue the existing regeneration approach. Identified governance weaknesses and financial risks Report 2.1
  • Rejected: Develop new masterplans. Discounted in favour of realistic delivery plans for priority areas Report 2.2, 3.39
  • Chosen: Focus on realistic delivery plans for priority areas. Aligns ambition with available funding Report 2.2, 3.36, 3.39

Implications

  • Financial: Plans must be scaled to available resources, with no capacity for additional borrowing or unfunded commitments. Report 4.1, 3.36
  • Legal: Plan supports compliance with statutory duties on local plan making and governance of public funds. Report 5.1
  • Staffing: Restructuring within the Regeneration and Place directorate, with new senior roles and the Regeneration PMO integrated into the Capital Programme team. Report 6.1, 3.17, 3.18, 3.19
  • Risk: Financial, governance, operational and reputational risks identified, with mitigations through strengthened governance and transparent reporting. Report 7.1, 7.2, 7.3, 7.4
  • Equalities: No specific equality implications, with ongoing assessment during planning and implementation. Report 9.2, 9.3
  • Climate: Aligned with the council's commitment to sustainability and the 2040 Framework's emphasis on low carbon communities. Report 10.1

Who and where

  • Birkenhead Left Bank area and its communities Report P11, 3.12
  • Liverpool City Region Combined Authority, Homes England and other strategic partners Report 3.5, 3.9
  • Registered Providers and housing partners Report 3.10
  • Private sector partners and investors Report 3.5
  • Wirral Growth Company
  • Council staff in the Regeneration and Place directorate and the Corporate PMO Report 6.1, 3.19

Timeline

  • 4 November 2025: Audit and Risk Management Committee considered the internal audit report on the Birkenhead Town Centre scheme. Report 3.1
  • 19 November 2025: Previous Policy and Resources Committee considered the Regeneration Review. Report P82, 3.1
  • 17 December 2025: This committee endorsed the regeneration action plan.
  • Next six months: Short term actions on operating model and governance for capital scheme delivery. Report 3.31
  • During 2026: Refresh of the 2040 vision, partnership model review, and development of member and officer relationships. Report 3.14, 3.32
  • By summer 2026: Consideration of a new operating model for regeneration expected to conclude, with implementation likely taking longer. Report 3.28
  • Next 15 years: Timeframe for the long term regeneration of the Left Bank under the 2040 vision. Report 3.7

Plain English for the jargon

  • Left Bank: The Birkenhead Left Bank area, the focus of the council's 2040 regeneration vision.
  • 2040 Framework: The long term vision for Birkenhead regeneration, originally adopted by the council.
  • PMO: Programme Management Office, the team that oversees project delivery and assurance.
  • RP: Registered Provider, a social housing organisation working with the council.
  • ARMC: Audit and Risk Management Committee, which considered the internal audit report on 4 November 2025.
  • Section 151 Officer: The council's chief finance officer with statutory duties for financial administration.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item82

Resolved

Resolved – that the report be noted and the action plan summarised in Appendix 1 be endorsed.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendations

It is recommended that the Policy & Resources Committee: 1. Endorse the report and the action plan summarised in Appendix 1 SUPPORTING INFORMATION

Reasons for recommendations

1.1To address deficiencies highlighted in the Regeneration Review and internal audit findings and to ensure regeneration activity aligns with the Council’s financial recovery plan and statutory obligations.

1.2To provide clarity and stability in governance and delivery arrangements for complex regeneration projects and to maintain momentum on key schemes while managing risk and resource constraints effectively.

2.0OTHER OPTIONS CONSIDERED

2.1Continuing with the existing regeneration approach was rejected due to identified governance weaknesses and financial risks.

2.2Developing new masterplans was considered but discounted in favour of focusing on realistic delivery plans for priority areas.

3.0BACKGROUND INFORMATION

3.1The internal audit report presented to Audit and Risk Management Committee on the 4 November 2025 in respect of the Birkenhead Town Centre scheme highlighted and crystallised a number of the issues referred to within the Regeneration Review around the framework, mechanisms and controls in place in respect of the delivery of major capital schemes.

3.2The action plan within this report incorporates a number of the actions already proposed in relation to the Birkenhead Town Centre Scheme.

3.3The actions within this report cover short-, medium- and longer-term actions that are required to reset the regeneration programme and detail the approach that will be taken to future schemes to deliver against the previously agreed 2040 framework. The recommendations have been split into the three key areas within the report and the associated actions are summarised in the Appendix 1. The key themes are: • An Approach for Place • Creating the Conditions for Successful Regeneration • Recovery and Financial Implications

Theme 1: An Approach for Place 3.4 The regeneration of the Left Bank through delivery of the 2040 vision should remain the key focus for the Council. The review identified that this vision is still relevant, focussing on the economic and physical transformation of the Left Bank that will deliver significant socio-economic and community benefits in this area and for the Borough overall.

3.5Partnerships with the Liverpool City Region, Homes England, housing providers, private sector organisations, and local communities need to be strengthened, with a revised vision and related strategies, overseen by robust and transparent governance arrangements. The Regeneration Review emphasises the need for this to be a long-term approach, which is thoroughly developed through collaboration with key stakeholders.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Actions and TimescalesAppendix 1 54 KB Download
PDF
Regeneration Action PlanReport 150 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 21 attended
PB
Councillor Paula BasnettChair, in attendance
JM
Councillor Julie McManusVice-Chair, apologies, sent representative
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 21 on the meeting page

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open