CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council
Policy and Resources Committee, Wednesday 17 December 2025

Local Government Association Corporate Peer Challenge Progress Review

Decided Committee 3 papers

AI summaryWirral Policy and Resources Committee accepts the Local Government Association's peer challenge progress review, which flags the severity of the council's financial position and the risk of a section 114 notice.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFeedback and recommendations from 1 October visit accepted
MoneyNot stated
What happens nextImplement peer challenge recommendationsCouncil expected to act on review findings
Who it affectsWirral Council finances and governanceLinked to council improvement and financial recovery

What was decided

The committee accepted the LGA Corporate Peer Challenge progress review feedback from the 1 October re-visit and its recommendations.

The committee formally thanked the Local Government Association for its peer challenge work and support for the council.

Why

The progress review emphasises the severity of the council's financial position and the need to address financial resilience. Report 4.1

The council is urged to put in place a financial recovery plan and make urgent decisions to address its financial challenges. Report 4.1

The original CPC process gathered views from 180 stakeholders across 50 interviews and focus groups between 4 and 7 November. Report 8.1

What happens next

Future policy changes brought forward as part of council improvement will be subject to an equality impact statement. Report 9.2

The council is expected to act on the LGA's recommendations to improve its financial standing and avoid a section 114 notice. Report 7.1, 4.1

Implications

  • Financial: The review highlights the severity of the council's financial position and the need for a financial recovery plan. Report 4.1
  • Risk: There is a potential risk of needing to declare a section 114 notice if the council cannot balance its budget. Report 7.1
  • Legal: No direct legal implications arise from this report. Report 5.1
  • Equalities: No direct equality implications, but future policy changes will require equality impact assessments. Report 9.1, 9.2
  • Climate: No environment, biodiversity or climate change implications arise directly from this report. Report 10.1

Who and where

  • Wirral Council, its elected members and staff Report 8.1
  • Public, private and voluntary sector partners Report 8.1
  • Council taxpayers and residents, given the financial position and potential service impacts Report 4.1, 7.1

Timeline

  • March 2022: Original Corporate Peer Challenge Feedback Report published Report P19
  • 4 to 7 November: CPC team held 50 interviews and focus groups with approximately 180 stakeholders Report 8.1
  • March 2025: LGA Corporate Peer Challenge Feedback Report and Improvement Action Plan published Report P19
  • 19 March 2025: Previous consideration by Policy and Resources Committee Report P22
  • 1 October: CPC progress review re-visit to the council Report 8.1
  • 17 December 2025: Policy and Resources Committee accepts the progress review feedback

Plain English for the jargon

  • Corporate Peer Challenge (CPC): An LGA-led improvement review where peers assess a council's performance, finances and governance.
  • Section 114 notice: A formal declaration by a council's chief finance officer that the authority cannot balance its budget, signalling serious financial distress.
  • Financial recovery plan: A structured plan to restore a council's financial sustainability and balance its budget.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item84

Resolved

Resolved – that the Local Government Association be thanked for its peer challenge work and support for the Council, and the feedback from the CPC progress review visit on 1 October and its recommendations be accepted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

POLICY AND RESOURCES COMMITTEE Wednesday, 17 December 2025

REPORT TITLE: LOCAL GOVERNMENT ASSOCIATION CORPORATE PEER CHALLENGE PROGRESS REVIEW REPORT OF: DIRECTOR OF LAW & CORPORATE SERVICES

REPORT SUMMARY

The Council invited the Local Government Association (LGA) to undertake a Corporate Peer Challenge (CPC) in November 2024. This was done as part of the Council’s on-going commitment to continuous improvement in the context of the Council requiring an External Assurance Panel (2022-24) to support delivery of its improvement plan.

Councils are recommended to undertake a CPC every 5 years. The CPC process is not an inspection but a peer-led review of organisational health. As part of the process, members of the CPC Panel will also undertake a follow up visit within 12 months to review a Council’s progress in implementing its improvement action plan.

The LGA conducted their progress review of Wirral Council on 1 October 2025. This report provides committee with an update on the outcome and recommendations arising from it. The LGA report providing feedback from the progress review session is included as Appendix 1.

The report supports Council improvement and therefore all the themes and priorities of the Council Plan. This is not a key decision.

RECOMMENDATION/S

The Policy & Resources Committee is requested to:

Thank the Local Government Association for its peer challenge work and support for the Council and accept the feedback from the CPC progress review visit on 1 October and its recommendations. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1The Corporate Peer Challenge is a critical element of the Council’s commitment to continuous improvement. The progress review feedback report, included as Appendix 1 to this report, highlights the improvement priorities for the Council over the short to medium term. Members of the Policy and Resources committee are required to consider the contents of the report and its implications in relation to the Council’s financial position and improvement.

2.0OTHER OPTIONS CONSIDERED

2.1The Corporate Peer Challenge process is a standard LGA support offer to Councils and was a condition of the Independent Assurance Panel when it stood down its support for the Council in March 2024. As such, no other options have been considered as part of this report.

3.0BACKGROUND INFORMATION

3.1The Autumn 2024 Peer Challenge was requested by the Council as it had been a condition of the decision by the LGA External Assurance Panel (2022 – 2024) to step down its support to the Council to allow the Council to manage its own improvement progress going forward.

3.2The CPC was undertaken on 4-7 November 2024 and included a team of 3 Peer Members, 3 Peer Officers and 2 LGA staff. The feedback report from the challenge process highlighted the governance progress the Council had made since the previous Peer Review in 2022. However, it also highlighted significant, continuing financial challenges the Council was facing as a result of increasing demand for services and the lack of financial resilience. The feedback report from the November 2024 CPC was reported to this committee in March 2025 and is included as Appendix 2.

3.3A standard element of the CPC process involves a follow up visit within 12 months to assess the Council’s progress in responding to the recommendations from the peer challenge process. The report from the follow up visit (included as Appendix 1) notes the progress the Council has made against those recommendations. It also highlights the following themes as key to the Council’s on-going improvement priorities:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LGA Peer Challenge Progress Review Outcome ReportAppendix 1 770 KB Download
PDF
LGA Peer Challenge Review Feedback ReportAppendix 2 369 KB Download
PDF
Local Government Association Corporate Peer Challenge Progress ReviewReport 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 21 attended
PB
Councillor Paula BasnettChair, in attendance
JM
Councillor Julie McManusVice-Chair, apologies, sent representative
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 21 on the meeting page

On this subject at Wirral

Search all
  1. Local Government Association Corporate Peer Challenge Progress ReviewThis decision
  2. Local government pension scheme (lgps) access for councillors & mayorsNoted
  3. Update on fit for the future: local government pension scheme (lgps) regulations & guidance, and northern lgpsNoted
  4. Local government pension scheme (lgps) access for councillors & mayorsNoted
  5. Update on fit for the future: local government pension scheme (lgps) regulations & guidance, and northern lgpsNoted
  6. Local government pension scheme (lgps) consultation response: scheme improvements (access and fairness)Noted

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open