CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council

Assurance Mapping Against the Corporate Risk Register

Noted Finance 2 papers

AI summaryWirral Audit and Risk Management Committee notes first assurance mapping of its Corporate Risk Register, with eight of ten risks rated green and work underway on two weaker areas.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo resolution to act, item received
MoneyNoneNo direct financial implications from report
What happens nextMarch 2027Next assurance mapping exercise report back
Who it affectsCouncil-wide risk managementAll 10 corporate risks assessed

What was decided

The Committee noted the report on assurance mapping against the Corporate Risk Register, the first time this exercise has been carried out at the Council. Report P1, 3.11

The mapping used the Institute of Internal Auditors' Three Lines Model to assess ten corporate risks as of October 2025, producing a green, amber or red rating for each. Report 3.1, 3.10, 3.13

The Committee accepted that gaps in the framework are expected on this first exercise and that further work is needed to strengthen assurance. Report 3.11, P39

Why

To give senior management and members confidence that assurance is in place for each risk, with no duplicated effort or hidden gaps, and to help target Internal Audit plans. Report 3.8

The Council has a statutory duty under the Accounts and Audit Regulations 2015 to manage risk, and CIPFA and SOLACE guidance supports this work. Report 5.2

The Global Internal Audit Standards for the UK Public Sector require the Chief Audit Executive to coordinate assurance work; assurance mapping is a suggested method. Report 3.5

What happens next

The Risk and Compliance Service will use the mapping to refresh the Corporate Risk Register, including the regeneration delivery risk and the first and second lines of defence. Report 3.21, 3.22

Findings will be fed into the next regular review and reported to the Senior Leadership Team, with further deep dives planned for 2026/2027 and a repeat exercise reported back in March 2027. Report P43, 3.23, 3.25

The Corporate Risk Register should be updated with the Birkenhead Town Centre Review Movement Scheme Contract Governance review recommendations and the related Internal Audit report. Report 3.19

Options considered

  • Chosen: Note the report. Recommended approach; the only option considered appropriate, as not reporting would show weak governance. Report P1, 2.1

Implications

  • Financial: No direct financial implications; failure to manage risks could threaten the Council's financial resilience. Report 4.1, 7.1
  • Legal: No direct legal implications; the Council must comply with Part 2 of the Accounts and Audit Regulations (England) 2015 and CIPFA/SOLACE governance principles. Report 5.1, 5.2
  • Staffing: No resource implications arising directly from this report. Report 6.1
  • Risk: Without the assessment there is a danger of failing to identify, understand and monitor key strategic and operational risks, with possible financial, reputational and resource impacts. Report 7.1
  • Equalities: The report sets out the Council's general duty on equalities but does not require an Equality Impact Assessment for this item. Report 9.1
  • Climate: No impact on greenhouse gas emissions expected from the report. Report 10.1, P56
  • Other: No direct crime and disorder implications, and no direct community wealth implications, though stronger risk management is said to support economic, social and environmental justice. Report 11.1, 12.1

Who and where

  • Senior Leadership Team, which will receive the refreshed Corporate Risk Register Report P43
  • Audit and Risk Management Committee, which will receive the next mapping in March 2027 Report 3.23
  • First line operational teams, including Adults Social Care, Neighbourhood Services and Children's Social Care Report P10
  • Second line oversight teams, including Risk and Compliance, Data Protection and Information Governance, Cyber Security, and Health and Safety Report P12
  • Internal Audit, which provides independent assurance as the third line Report P13, P16
  • Assistant Directors and Senior Managers interviewed for deep dives on Safeguarding, Health and Safety, Climate Response and Cyber Security

Timeline

  • October 2025: Cut-off date for the Corporate Risk Register used in the mapping exercise Report 3.10, P35
  • 2026/2027 year: Further deep dives into selected corporate risks planned Report 3.23
  • March 2027: Next assurance mapping exercise due to be reported back to the Audit and Risk Management Committee Report 3.23

Plain English for the jargon

  • Three Lines Model: A risk and governance framework from the Institute of Internal Auditors (2020), split into operational management (first line), oversight and compliance (second line), and independent internal audit (third line).
  • Corporate Risk Register: The Council's list of its main strategic risks, scored and used to direct assurance and audit work.
  • Deep dive: A detailed review using interviews and written submissions with senior managers to evidence controls and assurance for a specific risk.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item65

Resolved

Resolved – That the report be noted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

Recommendation

The Audit and Risk Management Committee is recommended to note the report. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1To improve the Committee’s understanding of and confidence that the governance risk and control arrangements that are in place are operating as intended and will help deliver organisational objectives. Thereby making the most of a range of assurances strengthens both internal and external accountability.

2.0OTHER OPTIONS CONSIDERED

2.1No other options considered appropriate as failure to report this information would demonstrate ineffective governance and non-compliance with professional best practice.

3.0BACKGROUND INFORMATION

3.1The Institute of Internal Auditors developed the Three Lines Model (formerly the "Three Lines of Defence"), officially defining it in 2013. It was updated in July 2020 to focus more on collaboration, accountability, and value creation in risk management and governance. It helps organisations clarify roles and responsibilities for managing risks and ensuring effective oversight as it distinguishes between those who own and manage risks, those who provide oversight, and those who provide independent assurance

3.2The three lines are divided into:

• First Line: Operational management who own and manage the risk as part of day- to-day business activities. Key responsibilities include: - identify, assess and manage risks for their operational area. - Implement and maintain effective controls within the operational area. - Comply with policies, standards and regulations. - Report and escalate risk issues promptly.

Examples of teams within the Council include resident facing teams such as Adults Social Care, Neighbourhood Services and Children’s Social Care.

• Second line: Oversight and compliance teams who provide specialist support, oversight, and constructive challenge to the first line. The key responsibilities include: - develop and maintain risk and compliance frameworks, - provide advice and guidance to operational management - monitor the effectiveness of first line controls.

The teams should perform thematic reviews and compliance monitoring to determine the effectiveness of their guidance and provide risk reporting to senior management and committees. Examples of teams within the Council include Risk and Compliance, Data Protection and Information Governance, Cyber Security, Health and Safety.

• Third Line: Internal Audit who provide independent, objective assurance to senior leadership and the Committee to assess the adequacy and effectiveness of governance, risk management, and internal controls. Other responsibilities include to evaluate whether first and second lines operate as intended and to make improvement recommendations. This line can also include assurance obtained from outside third-party organisations such as Ofsted and external auditors.

3.3The following table outlines in summary the three lines model framework, their role and key output.

Table 1 Summary table outlining the three lines model, the functions, their role and key output

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Assurance Mapping Against the Corporate Risk RegisterPlan 170 KB DownloadRead as text
PDF
Enc. 2 for Assurance Mapping Against the Corporate Risk RegisterPlan 103 KB Download

At this meeting

Whole meeting

Who was there

7 of 9 attended
HC
Councillor Helen CameronChair, present
MS
Councillor Mike SullivanVice-Chair, apologies
JB
Councillor Jo BirdSpokesperson, present
SK
Councillor Stuart KellySpokesperson, present
SP
Councillor Sue Powell-WildeCommittee Member, present
JW
Councillor Jerry WilliamsCommittee Member, present
JJ
Councillor Jennifer JohnsonCommittee Member, present
JB
Joanne ByrneIndependent Persons, absent
PJ
Councillor Paul JobsonDeputy, present as substitute

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... Noted Open
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies