Wirral Borough Council
Audit and Risk Management Committee, Wednesday 24 June 2026

Risk Management Action Plan Update

Noted Finance 2 papers

AI summaryAudit and Risk Management Committee noted an update on Wirral Council's Risk Management Action Plan, which tracks 64 internal actions and 10 recommendations from an external audit by Cheshire East, with several items still in progress pending risk appetite work.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo substantive decision, report noted only
MoneyNot stated
What happens nextRisk appetite work due June/July 2026Triggers completion of linked actions 1-8 and 36-38
Who it affectsCouncil risk management frameworkCovers policy, registers, appetite, training and reporting

What was decided

The committee noted the Risk Management Action Plan update, which combines 64 internal actions with 10 recommendations from an external audit by Cheshire East. Report P1, P41

Why

The plan responds to internal review and an external risk management audit, and tracks work on the Risk Management Policy, Financial Regulations wording, risk appetite, training and reporting. Report P3, P8, P16, P41, P51

What happens next

Completion of commissioned risk appetite work in June or July 2026 will allow actions 1 to 8 (revised Risk Management Policy) and 36 to 38 (risk appetite in board papers) to be finalised. Report P3, P7, P19

The revised Risk Strategy will go to the Senior Leadership Team and then the Policy and Resources Committee for approval once the risk appetite work is done. Report P7

An Audit and Risk Management Committee training session on the role of audit committees, in line with CIPFA guidance, is planned for July 2026. Report P37

A risk management software options report is due to the Director of Finance by 30 November 2026, with a decision to follow. Report P47

Options considered

  • Chosen: Note the report. Standard way to receive a progress update without a substantive decision.

Implications

  • Governance: The Risk Management Policy is being rewritten to align with Financial Regulations and to include content from the CIPFA/Solace 2016 governance framework. Report P3, P4, P5
  • Governance: Risk appetite work is outstanding; until it is finalised, related actions on policy and board decision templates remain on hold. Report P7, P19
  • Risk: Directors must provide a Directorate Risk Register each quarter, with a standard risk agenda item, under the existing and new Senior Leadership Team structure. Report P13
  • Staffing: Risk management training for staff and members is in initial planning, with a relaunch planned once strategy and risk appetite work is complete. Report P23, P24, P39
  • Equalities: Reminder issued on 26 March 2026 to report writers that equality duty risks should be included in risk sections where required. Report P51
  • Other: Guidance on using AI tools for early risk identification is being drafted alongside the corporate AI policy. Report P46
  • Other: A member risk champion is to be appointed via the Cabinet system, with an Executive Member taking on the role. Report P44

Who and where

  • Senior Leadership Team, responsible for most actions and for quarterly Directorate Risk Register updates Report P13, P52
  • Directors, required to provide quarterly Directorate Risk Registers and nominate risk co-ordinators Report P13
  • Policy and Resources Committee, which will approve the revised Risk Strategy Report P7
  • Audit and Risk Management Committee, receiving training and future assurance updates Report P26, P30, P37
  • Council staff and members, who will receive refreshed risk management training Report P23, P24

Timeline

  • 30 November 2025: Quotations for risk appetite options presented to Director of Finance Report P17
  • 31 January 2026: Risk appetite decision taken; risk co-ordinator nominations and Directorate Risk Register quarterly cycle to begin Report P13, P16, P18
  • 26 March 2026: Email reminder issued to report writers on equality duty risks Report P51
  • 31 March 2026: Revised Risk Strategy and risk appetite to be in place in board decision headers Report P7, P19
  • 31 May 2026: Key Risk Indicators to be defined for each Corporate Risk Register risk Report P22
  • June/July 2026: Commissioned risk appetite work due to be finalised, releasing linked actions Report P19
  • July 2026: ARMC training session on the role of audit committees scheduled Report P37
  • 31 July 2026: Revised wording to be included in Financial Regulations Report P8
  • 31 October 2026: Risk maturity assessment to be completed and reported to Senior Leadership Team Report P42
  • 30 November 2026: Risk management software options report due to Director of Finance Report P47
  • 31 March 2027: Partnership risk arrangements and Service Risk Registers to be in place Report P14, P43
  • 31 March 2028: Risk management audit next scheduled in the Annual Audit Plan Report P31

Plain English for the jargon

  • ARMC: Audit and Risk Management Committee
  • SLT: Senior Leadership Team
  • IRCM: Insurance Risk & Continuity Manager
  • DoF: Director of Finance
  • SRBC: Senior Risk and Business Continuity Officer
  • DMT: Directorate Management Team
  • HoRC: Head of Risk and Compliance
  • CRR: Corporate Risk Register
  • DRR: Directorate Risk Register
  • SRR: Service Risk Register
  • IAR: External audit recommendations from Cheshire East (Internal Audit Recommendations)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

Resolved – That the report be noted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

Appendix 1 – Combined Risk Management Action Plan May 2026

Action Action When Progress May 2026 Owner

1. There should be more details on the responsibilities within the Risk IRCM 15 Feb 2026 Actions 1 - 8 Management Policy Statement which are then aligned to the Financial In progress – linked to work Regulations. commissioned to develop risk appetite statement, see 2. The section on Internal Audit should be re-written to reflect that a regular HOCR 15 Feb 2026 actions 36 – 38. review should be arranged with an external provider.

3. Include a section on crystallization of risk, where a risk has happened, the IRCM 15 Feb 2026 maintenance of risk issues in an issues log and where this should be reported to.

4. Include relevant content from the Delivering Good Governance in Local IRCM 15 Feb 2026 Government: Framework “(CIPFA/Solace 2016) into the risk management policy.

5. The Governance section should be updated to include the Annual Opinion of the Head of Risk and Compliance. IRCM 15 Feb 2026

6. Include how risks in the CRR will be monitored through Key Risk Indicators. IRCM 15 Feb 2026 7. Include a scoring mechanism that defines whether a risk is corporate, IRCM 15 Feb 2026 Scoring mechanism to be directorate or operational risk. revised following completion of risk appetite work. 8. The revised version of the Risk Strategy should be presented to SLT and IRCM 31 March 2026 Policy and Resources Committee for approval.

9. Propose wording should be drafted and provided to the Director of Finance to IRCM 28 Feb 2026 Completed approve. 10. Approve revised wording. DoF 31 Mar 2026 Ongoing discussions on content Action Action When Progress May 2026 Owner 11. Include the revised wording in Financial Regulations DoF 31 July 2026

12. Consider other areas for inclusion in the Corporate Risk Register. SLT 28 Feb 2026 Completed. To continue at and ongoing quarterly reviews. 31 March 26 Currently being arranaged. 13. Carry out Risk Workshops with Policy and Resources Committee and SLT to IRCM/ review existing risk register content and identify risks arising over the horizon. SLT 31 March 2026 Partially completed – to be 14. Develop a risk issues log from discussions with Directors and include with next IRCM included in report to P&R in update on Corporate Risk register to be provided to Policy and Resources July. Committee.

15. Risk Owners to identify Action Owners for the CRR and provide to Risk Team 31 Jan 2026 SLT Completed for each risk in the CRR.

16. Define guidance on how actions should be recorded (SMART) and how they 31 Jan 2026 IRCM Partial completion – planned should individually be scored to individually/ collectively reach the target score. actions linked to Directorate Guidance to be shared with Risk Owners and Action. Business Plan key initiatives and Directorate Risk 31 March 2026 Registers – to be reviewed in SRBC 17. Work with the Action owners to develop the further actions to meet the target Qtr. 1 2026/27 score. The actions should be SMART with action owners and dates to complete. There should be consideration how the actions will individually and collectively reduce the net risk score to the target score.

18. Ensure actions are captured with the Council’s Power BI data visualisation 30 April 2026 In development following SRBC CRR report to SLT in May toolkit to enable monitoring on progress. Exploratory conversation with Wirral Intelligence held. 2026. 19. Ensure that the CRR and potentially DRRs reflects the plan objectives 31 August 2027 Part of the regular quarterly SLT following revision of the Council Plan 2023-27. review process, wholesale review following revision of the Council Plan. Action Action When Progress May 2026 Owner

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 2 for Risk Management Action Plan UpdateReport 107 KB DownloadRead as text
PDF
Risk Management Action Plan UpdateReport 140 KB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
HC
Councillor Helen CameronVice-Chair, present
SK
Councillor Stuart KellySpokesperson, present
JW
Councillor Jerry WilliamsCommittee Member, apologies, sent representative
JS
Councillor James Stewart LaingDeputy, present as substitute
CB
Councillor Colin BaldwinCommittee Member, present
HG
Councillor Harry GormanSpokesperson, present
BH
Councillor Brenda HallChair, present
GW
Councillor Gillian WoodCommittee Member, present

On this subject at Wirral

Search all
  1. Risk Management Action Plan UpdateThis decision
  2. Annual Report of the Audit and Risk Management CommitteeApproved
  3. Annual Report of the Audit and Risk Management CommitteeApproved
  4. Audit and risk management annual self assessmentNoted
  5. Risk Management Assurance UpdateNoted
  6. Corporate Risk Management UpdateDecided

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... Noted Open
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies