Resolved That ( i ) the Finance Director be authorised to draft and submit a bid for Marginal Viability Funding under the for phase 1 of the Sheerwater Regeneration Project; (ii) the Finance Director be authorised to draft and submit a bid for Marginal Viability Funding under the for the Victoria Square Project; and (iii) the Chief Executive be authorised to work with Surrey County Council to draft and submit an expression of interest for Forward Funding under the for the highway network upgrade south of the railway. Reason: To secure external funding to increase the provision of housing within the Borough.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
In July 2017 the DCLG launched the Housing Infrastructure Fund. This is a government capital grant programme of up to £2.3 billion intended to allow the necessary physical infrastructure to be developed to deliver 100,000 new homes. The funding will be awarded to Local Authorities on a highly competitive basis.
It is proposed that Officers submit a bid for the funding as detailed in the report.
Reasons for decision
To secure external funding to increase the provision of housing within the Borough.
Recommendations
The Executive is requested to:
RESOLVE That (i) the Finance Director be authorised to draft and submit a bid for Marginal Viability Funding under the Housing Infrastructure Fund for phase 1 of the Sheerwater Regeneration Project; (ii) the Finance Director be authorised to draft and submit a bid for Marginal Viability Funding under the Housing Infrastructure Fund for the Victoria Square Project; and (iii) the Chief Executive be authorised to work with Surrey County Council to draft and submit an expression of interest for Forward Funding under the Housing Infrastructure Fund for the highway network upgrade south of the railway.
The Executive has the authority to determine the above recommendations.
1.1In July 2017 the DCLG launched the Housing Infrastructure Fund (HIF). This is a government capital grant programme of up to £2.3 billion intended to allow the necessary physical infrastructure to be developed to deliver 100,000 new homes (this equates to £23,000 per dwelling). The funding will be awarded to Local Authorities on a highly competitive basis. A copy of the DCLG guidance is appended to the report at Appendix 1.
1.2A prescriptive definition of physical infrastructure is not provided by the DCLG but they have indicated this could include;
Transport and travel, utilities, schools, community and healthcare facilities, land assembly and site remediation, heritage infrastructure, digital communications, green infrastructure (such as parks) and blue infrastructure (such as flood defences and sustainable drainage systems).
1.3The fund provides two types of grant or intervention;
- Bids can be made of up to £10 million for Marginal Viability proposals.
- Bids can be made of up to £250 million for Forward Funding proposals.
- Higher levels of funding may be awarded to exceptional bids that can demonstrate a robust case for widespread and transformational delivery of new homes.
1.4Officers have reviewed the Council’s existing and proposed development sites across the borough to explore whether this funding source could be utilised. This report proposes that 3 bids are submitted as detailed below.
1.5Bids need to be submitted by 11:59pm on 28th September 2017. Multiple bids can be made but need to be ranked.
Marginal Viability Proposals (Bids Of Up To £10 Million)
1.6This element of the funding is intended for developments which are being held back because the cost of putting in infrastructure and building the homes are too great.
1.7The DCLG places certain conditions on the grant including;
- It intends to provide the final infrastructure funding to enable the project to go ahead and the homes to follow at pace.
- The funding will typically be awarded when planning permission is in place and the DCLG will prioritise strong schemes which can start spending straight away.
- The DCLG intends to award funding to development projects which cannot take place without the assistance of the Fund.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.