Woking Borough Council
Executive, Wednesday 16 September 2026 at 7.30pm

Lakeview Estate Refurbishment Scheme EXE26-057

Decided Executive 1 paper

AI summaryWoking Borough Council's Executive approved awarding a contract to refurbish 14 residential blocks at Lakeview Estate following removal of combustible cladding in 2024, with a 3-year works programme from 2026 to 2029.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedContract awarded to highest scoring tenderer through the London Construction Programme Housing Major Works framework
MoneyNot specified in reportEstimated contract value is in the exempt appendix. Budget is within the HRA Capital Programme 2026/27 and Housing Revenue Account 30-Year Business Plan
What happens nextMobilisation from late September 2026Phase 1 works commence January 2027. Further report on leaseholder support to Executive on 12 November 2026
Who it affects14 residential blocks at Lakeview EstateLeaseholders in 85 affected properties and tenants across the estate

What was decided

The contract for the Lakeview Estate Refurbishment Project works be awarded to the highest scoring tenderer through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3)) Report P10

Authority be delegated to the Strategic Director, People and Communities and Director of Legal and Democratic Services, in consultation with the Portfolio Holder for Housing, to take all necessary steps to effect the decision including entering into relevant contracts Report P11

A further report on support for affected leaseholders at Lakeview be brought to a future meeting of the Executive for consideration Report P12

Why

To fulfil the Council's statutory responsibilities for resident safety and building compliance and ensure the buildings remain habitable through replacement of temporary fire safety measures with permanent solutions Report 3.2

To address end-of-life components such as roofs, windows, and doors alongside external wall systems Report 3.3

What happens next

Mobilisation of Phase 1 works will begin in late September 2026 with full commencement on site from January 2027 Report P19

A Notice of Reasons will be sent to all leaseholders within 21 days of the contract being awarded Report P79

A separate report on additional support for affected leaseholders will come forward to the Executive meeting on 12 November 2026 Report P50

Options considered

  • Rejected: Do nothing or take a decision at a later stage. Temporary measures will fail within a short period, leading to uninhabitable homes, resident safety risks, and escalating costs Report 8.2
  • Rejected: Multiple contractors. Splitting the package would increase risk, reduce efficiency and value for money, and place undue contract management burden on the Council Report 8.3
  • Rejected: Open procurement under the Procurement Act 2023. This would extend the procurement programme, increase internal resource demand, and introduce greater risk and uncertainty from unsuitable bidders Report 8.4
  • Rejected: Use an alternative framework. Several frameworks were reviewed, and LCP MW24-H, Lot 2.3 has been identified as the most advantageous route to market Report 8.5

Implications

  • Legal: The Council is under a duty to carry out these works in accordance with its duties as a landlord under the Landlord and Tenant Act 1985 Report 10.1
  • Legal: The Procurement Act 2023 applies requiring competitive tendering. Mini-competition under the LCP framework is a compliant method ensuring compliance with Contract Standing Orders Report P67
  • Financial: There is a risk that leaseholder contributions may be legally challenged or contested, or recovery may prove unsuccessful, potentially placing additional pressure on the Housing Revenue Account Report P79
  • Financial: The project represents a significant capital cost to the Housing service and Council. Should provisional costs come back higher than expected, this will exert further pressure on the HRA Report P79
  • Risk: Not progressing with the contract award could lead to temporary measures failing within a short period Report 10.9
  • Risk: Contractor underperformance leads to delays in completion of the works, mitigated through framework monitoring and strong contract and project management Report 10.10
  • Environment and climate: The scheme will deliver significant environmental benefits by prolonging the life of the 14 blocks, avoiding the greater carbon impact of demolition and redevelopment Report P91
  • Environment and climate: Works include external wall insulation, high-performance windows and doors, and roof replacements to improve thermal efficiency and bring properties to EPC C rating Report P94
  • Other: The works programme may straddle Local Government Reorganisation. Given fire safety risks, it is imperative this work is commissioned and progressed ahead of LGR Report P96

Who and where

  • 14 residential blocks at Lakeview Estate comprising leaseholders and tenants Report 1.1, 5.1
  • 85 affected leaseholders who were formally consulted Report 7.2
  • Woking Borough Council as landlord with statutory duties Report 10.1

Timeline

  • 2024: Combustible cladding removed from 14 blocks following fire risk assessment. Temporary external covering and insulation system installed Report 5.1
  • 13 November 2025: Executive decision to commence procurement and agreement to waive cladding-related cost elements for leaseholders Report 6.1, 7.1
  • 2 February 2026: Expression of Interest Notice issued for the LCP MW24-H Lot 2.3 framework mini-competition Report 6.2
  • 23 February 2026: Invitation to Tender documentation issued via LCP Framework Portal Report 6.3
  • 13 April 2026: Revised tender return deadline following extension granted to all bidders Report 6.3
  • 23 July 2026: Section 20 Notice of Proposal issued to affected leaseholders Report 7.2
  • 24 August 2026: End of Section 20 consultation period Report 7.2
  • Late September 2026: Mobilisation of Phase 1 works Report P19
  • 12 November 2026: Anticipated date for Executive report on support for affected leaseholders Report P50
  • 2026 to 2029: 3-year works programme across financial years Report P96
  • January 2027: Full commencement of Phase 1 works on site Report P19

Plain English for the jargon

  • HRA: Housing Revenue Account
  • LCP MW24-H Framework (Lot 2.3): London Construction Programme Housing Major Works framework
  • Section 20 consultation: Statutory consultation with leaseholders under the Landlord and Tenant Act 1985 before major works can be charged
  • Qualifying Works: Works that can be recharged to leaseholders
  • EPC C rating: Energy Performance Certificate rating of C, targeted for 2030
  • LGR: Local Government Reorganisation
  • Mini-competition: A competitive procurement process run through an established framework agreement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the highest scoring tenderer through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3)); (ii) authority be delegated to the Strategic Director – People and Communities and Director of Legal and Democratic Services, in consultation with the Portfolio Holder for Housing, to take all necessary steps to effect the decision in ( i ) including entering into relevant contracts; and (iii) a further report on support for affected leaseholders at Lakeview be brought to a future meeting of the Executive for consideration. Reason: To fulfil the Council’s statutory responsibilities for resident safety and building compliance and ensure the buildings remain habitable through replacement of temporary fire safety measures with permanent solutions. To address end-of-life components such as roofs, windows, and doors alongside external wall systems.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Summary

1.1Following a mini-competition via an established framework, this report seeks approval to award the contract for the Lakeview Estate Refurbishment Scheme to the highest scoring bidder. The scheme covers essential refurbishment and remediation works to 14 residential blocks, following removal of combustible cladding.

1.2The works are critical to ensuring the continued safety, compliance, and habitability of the buildings, and to prevent further deterioration of key building elements.

1.3The works associated with this procurement and the resulting project have been included in the forecast of the Housing Revenue Account (HRA) 30 Year Business Plan and Housing Asset Management forecast budgets for future years. It is anticipated that the works will straddle three consecutive financial years.

1.4The works include “Qualifying Works” that will be recharged to Leaseholders within the associated blocks. The statutory Section 20 consultation has been completed with affected leaseholders.

Purpose of report

2.1The purpose of this report is to secure Executive approval to award a contract to the preferred contractor for the Lakeview Estate Refurbishment Scheme in line with the Council’s Contract Standing Orders (CSOs).

EXE26-057 Lakeview Estate Refurbishment Scheme

2.2The contract award will enable the Council to progress essential building safety and fabric upgrades that address statutory landlord duties, safeguard residents, and secure long-term sustainability of the estate.

Recommendations

3.1The Executive is requested to:

Resolve That

(i) The contract for the Lakeview Estate Refurbishment Project works be awarded to the highest scoring tenderer through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3));

(ii) Authority be delegated to the Strategic Director – People and Communities and Director of Legal and Democratic Services, in consultation with the Portfolio Holder for Housing, to take all necessary steps to effect the decision in (i) including entering into relevant contracts; and

(iii) A further report on support for affected leaseholders at Lakeview be brought to a future meeting of the Executive for consideration.

Reason(s) for Decision

3.2To fulfil the Council’s statutory responsibilities for resident safety and building compliance and ensure the buildings remain habitable through replacement of temporary fire safety measures with permanent solutions.

3.3To address end-of-life components such as roofs, windows, and doors alongside external wall systems.

4.0Proposal and Outcome

4.1It is proposed that, following a mini-competition, the Council will award the contract to the selected contractor via the LCP MW24-H Lot 2.3 framework to complete the Lakeview Estate refurbishment scheme.

4.2The intended outcome is:

i. Delivery of a phased, block-by-block programme from late 2026/early 2027.

ii. Replacement of temporary external cladding/insulation measures with long-term compliant solutions.

iii. Significant improvements in building safety, energy efficiency, and asset condition in line with stock condition data.

4.3Success will be measured through cost and programme control, regulatory approval, and resident satisfaction. Lakeview Estate Refurbishment Scheme

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lakeview Estate Refurbishment Scheme EXE26-057Report 109 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 14 attended
AB
Councillor Ann-Marie BarkerChair, present
DH
Councillor Deborah HughesVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
EN
Councillor Ellen NicholsonCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, apologies
SF
Stephen FitzgeraldOfficer, present
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, apologies
LS
Louise StrongitharmOfficer, present

All 14 on the meeting page

On this subject at Woking

Search all
  1. Lakeview Estate Refurbishment Scheme EXE26-057This decision
  2. Lakeview Estate Refurbishment Scheme and Housing Fire Safety Remedial Works Procurement EXE26-029Noted
  3. Lakeview Estate Refurbishment Scheme EXE25-105Approved

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open
16 Sep 2026 Capital Works Programme (General Fund) Procurement EXE26-105The Executive Resolved That (i) the procurement exercise to support future Capital Works Programme (General Fund) pro... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies