Resolved
RESOLVED That the report be received and progress against the 2018/19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Audit and Governance Committee noted this item on Thursday 20 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received and progress against the 2018/19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Financial Regulation 2.8 requires that the Chief Finance Officer shall report regularly to the Standards and Audit Committee on the work undertaken by Internal Audit. This report is accordingly submitted to the Committee for consideration.
This report covers audit activity and performance from April to September 2018.
The Committee is requested to:
RESOLVE That the report be received and progress against the 2018-19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
The Committee has the authority to determine the recommendation(s) set out above.
Background Papers: None.
Reporting Person: James Graham, Head of Internal Audit Email: [email protected]
Contact Person: Leigh Clarke, Finance Director Ext. 3277, E Mail: [email protected]
Date Published: 12 September 2018
STA18-001 Internal Audit Charter
1.0Introduction
1.1Financial Regulation 2.8 requires that the Chief Finance Officer shall report regularly to the Standards and Audit Committee on the work undertaken by Internal Audit. This report covers audit activity and performance from 1 April to 12 September 2018.
1.2The Standards and Audit Committee approved the 2018/19 Internal Auit Plan on 8 March 2018.
1.3The purpose of this report is to outline the following in respect of Internal Audit Activity during the period: A description of key audit issues and also of non-audit activity undertaken during the year; details of reports issued during the period; a list of reports in progress as at 12 September 2018. any major (ie. high risk) recommendations made in Internal Audit reports issued between 1 April and 21 September 2018; and an update on all recommendations that remain outstanding for implementation.
2.0Internal Audit Activity 1 April to 12 September 2018
2.1Table 1 below provides a summary of progress in terms of the number of reports at draft or final stage and those in progress, as at 7 September: Table 1
Audit Status Number of Percentage reviews Completion Finalised 0 0 Draft 4 21 In Progress 4 21 To be undertaken 11 58 Deferred to 18/19 0 0 Total 19 100
2.2Table 1 above illustrates that 21% of the plan has been delivered to at least draft report stage as at 7 September, with a further 21% of the plan in progress. A further 6 audits (32% are currently in the process of being scoped and scheduled in to start before the end of December 2018)
2.3All audits are expected to be completed to at least draft stage by the end of March 2018. No audits have been deferred to 2018/19.
2.4The table below shows the status of all audits on the 2018/19 plan, including the reviews carried forward from 2017/18:
Recommendations by Priority Audit Title Audit Status High Medium Low
Grants to Voluntary Draft report issued - - - Organisations Internal Audit Charter
Community Safety In progress - - - Planning in Homelessness progress - - - HMO and Selective Planning in Housing Licensing progress - - -
New Vision Homes Planning in Contract Management progress - - -
Building Control - - - -
Emergency Planning Draft report issued - - -
Planning in Asset Management progress - - - Air Quality Monitoring and Planning in Management progress - - - Freedom of Information Planning in Requests progress - - - Key Financial Control Draft report issued Testing - AP, AR, GL, - - - Payroll, Treasury, Sheerwater Ctax, Regeneration In progress NNDR Governance - - - Planning in Group Companies progress - - - Business Continuity - - - - Supplier Resilience Draft report issued - - - HR - - - - IT Strategy - - - - SekCheck (Windows OS Draft report issued Network Management) Application Audit (TBC) - Carried Forward from 2017/18 GDPR In Progress - - - Commercial Property Draft Report Issued Estate - - - Victoria Square In Progress Development - - - Internal Audit Charter
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Service Progress UpdateReport | 87 KB | DownloadRead as text |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.