Resolved
RESOLVED That the report be received and progress against the 2018-19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Audit and Governance Committee noted this item on Thursday 7 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received and progress against the 2018-19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Financial Regulation 2.8 requires that the Chief Finance Officer shall report regularly to the Standards and Audit Committee on the work undertaken by Internal Audit. This report is accordingly submitted to the Committee for consideration.
This report covers audit activity and performance from 20 November 2018 to 25 February 2019.
The Committee is requested to:
RESOLVE That the report be received and progress against the 2018- 19 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
The Committee has the authority to determine the recommendation(s) set out above.
Background Papers: None.
Reporting Person: James Graham, Head of Internal Audit Email: [email protected]
Contact Person: Leigh Clarke, Finance Director Ext. 3277, E Mail: [email protected]
Date Published: 27 February 2019
STA19-004 Internal Audit Progress Report Internal Audit Progress Report
1.0Introduction
1.1Financial Regulation 2.8 requires that the Chief Finance Officer shall report regularly to the Standards and Audit Committee on the work undertaken by Internal Audit. This report covers audit activity and performance from 20 November 2018 to 25 February 2019.
1.2The Standards and Audit Committee approved the 2018/19 Internal Audit Plan on 8 March 2018.
1.3The purpose of this report is to outline the following in respect of Internal Audit Activity during the period: A description of key audit issues and also of non-audit activity undertaken during the year; Details of reports issued during the period; A list of reports in progress as at 25 February 2019. Any major (i.e. high risk) recommendations made in Internal Audit reports issued between 20 November 2018 and 25 February 2019; and An update on all recommendations that remain outstanding for implementation.
2.0Internal Audit Activity
2.1The table below provides a summary of progress in terms of the number of reports at draft or final stage and those in progress, as at 25 February:
Audit Status Number of Percentage reviews Completion Finalised 8 44 Draft 3 17 Fieldwork in progress 4 22 To be undertaken 3 17 Total 18 100
2.2Table 1 above illustrates that 61% of the plan has been delivered to at least draft report stage as at 25 February, with a further 22% of the plan in progress. A further 3 audits (17% are currently in the process of being scheduled in.
2.3All audits in progress are expected to be completed to at least draft stage by the end of March 2019. The remaining 3 audits not yet scheduled in are expected to be completed by the end of April 2019.
2.4The table below shows the status of all audits on the 2018/19 plan, including the reviews carried forward from 2017/18 not yet at final report stage:
Recommendations by Audit Title Audit Status Priority High Medium Low Final report Grants to Voluntary Organisations 0 2 2 issued Final Report Community Safety 0 1 0 issued Internal Audit Progress Report
Fieldwork in Homelessness - - - progress Fieldwork in New Vision Homes Contract Management - - - progress Draft report Building Control - - - issued Final report Emergency Planning 0 1 5 issued Start date Asset Management - - - agreed Final report Air Quality Monitoring and Management 0 3 3 issued Fieldwork in Freedom of Information Requests 0 2 1 progress Final report Key Financial Control Testing 0 1 0 issued Draft report Sheerwater Regeneration Governance - - - issued Draft report Group Companies - - - issued Fieldwork in Business Continuity - - - progress Final report Supplier Resilience (Advisory) N/A N/A N/A issued Final report HR – Sickness Absence Management 0 2 1 issued Planning in IT Strategy - - - progress SekCheck (Windows Operating System Final report 2 5 1 Network Management) issued Planning in Flexiroute Application - - - progress Carried Forward from 2017/18 Draft report GDPR - - - issued Draft report Victoria Square Development - - - issued Internal Audit Progress Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress Report STA19-004Report | 86 KB | DownloadRead as text |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.