Resolved
RESOLVED That the report be received. Reason: To monitor the position of active projects on SharePoint.
Executive decided this item on Thursday 4 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received. Reason: To monitor the position of active projects on SharePoint.
The Executive receives regular reports on the progress of projects in the interests of financial prudence and to ensure open and transparent corporate governance.
This report details the status of projects as at the end of December 2020, incorporating capital and revenue projects, and is attached at Appendix 1.
As requested by the Executive, the attached list includes only active projects and those closed during this reporting period. The agreed reporting protocol stipulates that projects overdue against the published end date will be classified as amber if the over-run is less than 25% of total project schedule and red if above this level.
The project management methodology includes a formal approval process to extend project timescales, where there are clear practical and business reasons to do so. Appendix 1 includes a column showing revised end date, reflecting application of the approval process. For completeness the original end date is retained on the report.
A new column has also been added to Appendix 1 called ‘Overview Status’, which provides a quick visual prompt to show if the status of a project has changed (better, worse or the same) since the previous report;
There are no specific areas for concern or action by the Executive.
The Executive is requested to:
RESOLVE That
the report be received.
Reason: To monitor the position of active projects on SharePoint.
The Executive has the authority to determine the recommendation(s) set out above.
EXE21-005 Monitoring Reports - Projects
Background Papers: None.
Reporting Person: Ray Morgan, Chief Executive Email: [email protected], Extn: 3333
Contact Person: Pino Mastromarco, Senior Policy Officer Email: [email protected], Extn: 3464 Dawn George, Business Improvement Officer Email: [email protected], Extn: 3407
Portfolio Holder: Councillor Ayesha Azad Email: [email protected]
Shadow Portfolio Holder: Councillor Ann-Marie Barker Email: [email protected]
Date Published: 29 January 2021 Monitoring Reports - Projects
1.0Introduction
1.1Attached at Appendix 1 is the report on projects at the end of December 2020 (produced from the SharePoint system).
1.2All active projects continue to be included in the report for completeness. Members will note a number of projects are listed as showing delays in the project being closed. This is to reflect the requirement that evaluation and closure of the project is necessary after it has been completed (normally after the defect period, which may be some time from completion of the actual delivery).
1.3Projects completed during the period are included at the end of Appendix 1. These projects will be removed from the report next time it is published, as no further reporting is required on projects that have been formally closed.
2.0Exception items
2.1In accordance with Financial Regulations, the following projects are being reported to the Executive because project costs exceed the original or approved revised budget by the greater of £10k or 5%.
2.2Project No. 10297. Local Development Framework. No change since first on the exception report at 19/11/20 Executive.
2.3Project No. 10785. Leisure Management Contract Investment Scheme. No change since the exception report at 20/11/2014 Executive.
2.4Project No. 10911. Goldwater Lodge Fire Reinstatement Works. No change since the exception report at the 21/07/2016 Executive.
2.5Project No. 10930. Goldsworth Park Rec Public Toilets. No change since first on the exception report at 4/02/2016 Executive.
2.6Project No. 20061. Export House - WC and Lift Lobby Upgrade - Floors 2-14. No change since first on the exception report at 11/02/2018 Executive.
2.7Project No. 20124. Woking Integrated Transport. No change since first on the exception report at 19/11/20 Executive.
2.8Project No. 20126. Leisure Centre - Upgrade of External Cladding. No change since first on the exception report at 10/10/19 Executive.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXE21-005 Appendix 1: Project Monitoring Report as at Dec2020Appendix | 422 KB | Download |
PDF |
Monitoring Reports: Projects EXE21-005Report | 67 KB | DownloadRead as text |
Follow Executive at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... | Noted | Open |
| 16 Sep 2026 | Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... | Approved | Open |
| 16 Sep 2026 | Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... | Decided | Open |
| 16 Sep 2026 | Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... | Approved | Open |
| 16 Sep 2026 | Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.