Resolved
RESOLVED That the report be received and progress against the 2020-21 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Audit and Governance Committee noted this item on Thursday 4 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received and progress against the 2020-21 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
Financial Regulation 2.8 requires that the Chief Finance Officer shall regularly report to the Standards and Audit Committee (Committee) on the work undertaken by Internal Audit. Similarly, it is a requirement under the Internal Audit Charter approved by the Committee that Internal Audit provides a quarterly report on internal audit progress and key findings to the Committee.
This report covers internal audit activity and performance from 11 November to 22 February 2021.
The Committee is requested to:
RESOLVE That the report be received and progress against the 2020- 21 Internal Audit Plan and implementation of Internal Audit recommendations be noted.
The Committee has the authority to determine the recommendation(s) set out above.
Background Papers: None.
Reporting Person: Graeme Clarke, Director, Mazars LLP E-Mail: [email removed] Juan Fosco, Manager, Mazars LLP E-Mail: [email removed]
Contact Person: Leigh Clarke, Finance Director Ext. 3277, E-Mail: [email protected]
Date Published: 24 February 2021
STA21-004 Internal Audit Progress Report Internal Audit Progress Report
1.0Introduction
1.1Financial Regulation 2.8 requires that the Chief Finance Officer shall regularly report to the Standards and Audit Committee (Committee) on the work undertaken by Internal Audit. Similarly, the Internal Audit Charter approved by the Committee requires that Internal Audit provide a quarterly report on internal audit progress and key findings to the Committee.
1.2The Committee approved the 2020/21 Internal Audit Plan (Plan) on 5 March 2020.
1.3The purpose of this report is to outline the following in respect of Internal Audit Activity during the period: An update on progress in delivering the Plan; A summary of any Limited/Nil Assurance reports issued, and high priority recommendations raised; and An update on follow up activity and any recommendations outstanding for implementation.
1.4This report covers internal audit activity and performance from 11 November 2020 to 22 February 2021.
2.0Internal Audit Progress
2.1Since the last Committee despite the continued Covid-19 pandemic and strict lockdown measures, progress against the Plan remains on track. All audits planned for Q2 and Q3 are either finalised or at draft report stage in line with the expectations from Corporate Management Group (CMG). Also, of the ten audits planned for Q4, three are at draft report stage, and three are in progress.
2.2This is considered to be a good position considering the last 12 months have been particularly challenging with the impact of Covid-19, the need to complete 2019/20 Plan work post the first lockdown and associated measures whilst also only commencing the new Plan in July 2020.
2.3The remaining four reviews in the Plan are confirmed, two of which are scheduled to start before April 2021. The two remaining are related to IT audits beginning in May 2021. Although this is after the March deadline, they will be delivered in time to be considered for the Internal Audit Annual Opinion for the year.
2.4Following discussions with the Finance Director and the ICT Manager, the Office 365 audit will be included in the 2021/22 Plan and will be replaced with a Remote Working Security/Resilience audit to be delivered in May 2021.
2.5Monthly meetings are held with the Finance Director to consider progress on the Plan, escalate any issues as well as keep abreast of developments at the Council. Following further discussion with the Finance Director there are three non-IT audits to be deferred to the 2021/22 Plan which the Committee is asked to note:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 183 KB | DownloadRead as text |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.