RESOLVED That ( i ) the Housing Delivery Test published by the Government on 14 January 2022 with Officers’ response be noted; and (ii) delegated authority be given to the Strategic Director – Place, in consultation with the Portfolio Holder for Planning, to prepare and publish an Action Plan setting out how the Council would improve the prospect of achieving the planned supply of homes. Reason: To ensure that Members of the Executive are informed about the Housing Delivery Test and the actions that the Council must take to address the failure to meet its planned housing requirement and to ensure that the Planning Committee is aware of the need to deliver new sustainable homes in accordance with the Local Plan.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
The purpose of the report is to request the Executive to note the 2021 Housing Delivery Test published by the Government with Officers’ response and to seek authority to publish an Action Plan setting out how the planned Core Strategy housing requirement of 292 dwellings per year would be achieved by the Council in future years. The draft Action Plan is attached as Appendix 1.
The Government published the latest Housing Delivery Test (HDT) on 14 January 2022. The Housing Delivery Test is an annual measurement of housing delivery against the planned housing requirement (or housing need if you have not got an up-to-date local plan). The HDT is measured and published by the Department for Levelling Up, Housing and Communities (DLUHC). It is calculated by the total net homes delivered over 3 years divided by the total number of homes required over the three-year period. The expectation is to deliver the planned housing requirement of 292 dwellings per year in full, equivalent to 100%. Sanctions are applied if a local authority failed to deliver the required number of homes. The sanctions mainly involve identifying more land to improve the prospect of achieving the planned housing supply.
According to the Government’s figures, this year, Woking scored 78%, which comes with a sanction to identify 20% buffer of housing land supply to improve the prospect of achieving the planned housing requirement. The Council will also have to prepare an Action Plan to demonstrate how the planned growth (100% or average of 292 dwellings per year) can be achieved. The Action Plan should be completed and published within 6 months from the date the HDT was published, in this case, by 14 July 2022.
Although the Government’s calculations will be challenged, the requirement of the Housing Delivery Test (HDT) to identify a 20% buffer of housing land supply will apply and the report demonstrates that it can be met from existing allocations and commitments. The Site Allocations DPD already builds in sufficient headroom and cushion to mitigate against the risk of non-implementation, and this would be sufficient to address the requirements of the HDT.
Whilst there are many positive things to encourage housing supply, the challenge to translate land into housing completions cannot be underestimated. The Council will need to work in partnership with stakeholders to sustain housing land delivery into the future. This includes making sure that policy compliant proposals that meets detailed requirements are determined as soon as possible.
Recommendations
The Executive is requested to:
RESOLVE That
(i) the Housing Delivery Test published by the Government on 14 January 2022 with Officers’ response be noted; and
(ii) delegated authority be given to the Strategic Director – Place, in consultation with the Portfolio Holder for Planning, to prepare and publish an Action Plan setting out how the Council would improve the prospect of achieving the planned supply of homes.
EXE22-040 Housing Delivery Test and Action Plan
Reasons for decision
Reason: To ensure that Members of the Executive are informed about the Housing Delivery Test and the actions that the Council must take to address the failure to meet its planned housing requirement and to ensure that the Planning Committee is aware of the need to deliver new sustainable homes in accordance with the Local Plan.
The Executive has the authority to determine the recommendation(s) set out above.
Background Papers: None.
Reporting Person: Giorgio Framalicco, Strategic Director – Place Email: [email protected], Extn: 3440
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.