Resolved
RESOLVED That the six months’ progress since the beginning of the Government intervention on 25 May 2023 be approved.
Council approved this item on Thursday 30 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the six months’ progress since the beginning of the Government intervention on 25 May 2023 be approved.
Following statutory government intervention and the issuing of a Section 114 Notice, the Council was required to put in place an Improvement and Recovery Plan.
The Improvement and Recovery Plan will deliver the expectations detailed in the Secretary of State’s Directions published on 25 May 2023 and will help the Council return to meeting its best value duty. It will also draw upon the recommendations of the non-statutory external assurance review into the Council’s finances, investments and related governance.
The three-to-five-year plan, which was adopted at Council on 22 August 2023, details the actions that the Council will undertake to deliver against the Government directions, together with milestones and delivery targets to measure progress.
The Council is required to report to the Commissioners on the delivery of the Improvement and Recovery Plan after three months, six months and thereafter at six-monthly intervals, or at such intervals as the Commissioners may direct. The first three-month progress report was submitted to Commissioners in August, and this report outlines the progress after six months.
The Chief Executive’s position statement in relation to the Improvement and Recovery Plan is included at appendix A.
The full six-month progress update is included at Appendix B.
Council is asked to consider and approve the progress outlined in the report.
The Council is requested to:
RESOLVE That the six months’ progress since the beginning of the Government intervention on 25 May 2023 be approved.
The Council has authority to determine the recommendation set out above.
Reporting Person: Julie Fisher, Chief Executive Email: [email protected] , Extn: 3333
Contact Person: Lee Danson, Senior Programme Manager Email: [email protected]
Portfolio Holder: Councillor Ann-Marie Barker Email: [email protected]
Date Published: 22 November 2023
WBC23-043 The Improvement and Recovery Plan Progress – September to November 2023 The Improvement and Recovery Plan Progress – September to November 2023
Appendix A – Chief Executive Position Statement
CEX Position Statement
Introduction
1. I am pleased to present the second of Woking Borough Council’s (WBC) Improvement and Recovery Plan (IRP) progress reports, providing an update on how the Council has responded to the Government Directions. The first progress report provided an update on the Council’s immediate response to the Section 114 Notice and the development of the IRP. This second progress report provides an update on the work that has taken place to deliver against our improvement priorities since the IRP was approved in August 2023. In my position statement, I want to recognise the significant progress that has been made so far, whilst also highlighting the key challenges and risks the Council faces going forward.
2. All progress detailed in this position statement must be set against the scale of the challenge that we face here at Woking. The Council is in an extremely difficult financial position due to its historic investment decisions which has left it £2billion in debt. There are also issues with historic governance and record-keeping which means that, in some areas, we may still not fully understand the scale and complexities of the financial deficit. At the same time, the Council lacks the data, systems, and capacity to enable it to respond quickly to many of the challenges it faces.
3. The IRP outlines what the Council will do over a period of three to five years, in order to respond to this significant challenge and the Government Directions. The Plan is divided into four themes, which I shall report on in turn.
Theme 1: Financial Recovery
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Improvement and Recovery Plan Progress Update WBC23-043.Report | 234 KB | DownloadRead as text |
Follow Council at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Minutes.R esolved That the minutes of the meeting of the Council held on 19 May 2026 be approved and signed as a true and cor... | Approved | Open |
| 23 Jul 2026 | Recommendations of the Executive and Committees.The Council had before it a report on the recommendations from the Executive and the Audit and Governance Committee, ... | Decided | Open |
| 23 Jul 2026 | ThamesWey Energy Limited (TEL) EXE26-078Resolved That following the acquisition of the shares of ThamesWey Limited in ThamesWey Energy Limited by the Council... | Approved | Open |
| 23 Jul 2026 | Future of ThamesWey Housing Limited (THL) EXE26-079Resolved That following the proposed acquisition of the shares in ThamesWey Housing Limited by the Council, a debt fo... | Approved | Open |
| 23 Jul 2026 | Town Centre Public Spaces Protection Order (PSPO) - Consultation Outcome and Next Steps EXE26-064Resolved That (i) the results of the public consultation on the draft proposed Woking town centre Public Spaces Prote... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.