The Executive RESOLVED That the Improvement and Recovery Plan progress report to Commissioners be approved. Reason: Following statutory government intervention and the issuing of a Section 114 Notice, the Council was required to put in place an Improvement and Recovery Plan and to report to the Commissioners on its delivery.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
Following the issuing of a Section 114 Notice and Government intervention, the Council was required to put in place an Improvement and Recovery Plan.
The Improvement and Recovery Plan (IRP) responds to the Secretary of State’s Directions published on 25 May 2023 and will help the Council discharge its Best Value duty. It will also draw upon the recommendations of the non-statutory external assurance review into the Council’s finances, investments and related governance.
The three-to-five-year Improvement and Recovery Plan, which was adopted by the Council on 22 August 2023, details the actions that the Council will undertake to address the Government Directions, together with milestones and delivery targets to measure progress.
The Council is required to report to the Commissioners on the delivery of the Improvement and Recovery Plan after three months, six months and thereafter at six-monthly intervals, or at such intervals as the Commissioners may direct. This is the fourth progress report to be submitted to Commissioners and reflects the position one year since the adoption of the Improvement and Recovery Plan.
In the context of the Directions, Commissioners have sought to define the outcomes they would expect to result from the delivery of the Council’s IRP.
Therefore, this progress report consists of three documents:
Appendix A: An outcome-based review of progress against the IRP. This is focussed on where the Council has evidenced changed outcomes as a result of IRP activity.
Appendix B: A programme-based review of progress against the IRP.
Appendix C: The IRP high level risks.
The Executive is asked to consider and approve the progress outlined in the report.
Recommendations
The Executive is requested to:
RESOLVE That
the Improvement and Recovery Plan progress report to Commissioners be approved.
The Executive has the authority to determine the recommendation(s) set out above.
EXE24-059 Improvement and Recovery Plan Progress – March to September 2024
Date Published: 4 September 2024 Improvement and Recovery Plan Progress – March to September 2024
Appendix A - Outcome Based Review of IRP Progress
Background
1.1The Improvement and Recovery Board (IRB) is chaired by the Lead Commissioner, Sir Tony Redmond. At the IRB on 22 July 2024, the Board agreed the Chair’s ‘Focus of Attention’ report. The aim of this report was to ensure that the Improvement and Recovery Plan results in tangible outcomes that help with the assessment of the Council’s progress in discharging its Best Value responsibilities.
1.2This report provides an update of progress against the priorities of the ‘Focus of Attention’ document.
2.0Overall Position statement
2.1Woking Borough’s Council (WBC) Improvement and Recovery Programme (IRP) has now been in place for one year (following its adoption in August 2023). During that period, the Council has put in place the foundations to enable WBC to manage its own affairs appropriately in the future. The Council recognises that, although important progress has been made, there is still significant work required to deliver in full the workstreams within the IRP and evidence the success measures outlined in this report. Capacity remains a challenge and the Council is developing a clearer focus on the sequencing of actions within the IRP to ensure that priority improvements are delivered. In addition, the scale and complexity of the legacy issues, particularly as a result of the commercial arrangements the Council involved itself in historically, should not be underestimated.
3.0Governance
Position statement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.