Resolved
RESOLVED That the report be received and progress against the 2023-24 Internal Audit Plan be noted.
Audit and Governance Committee noted this item on Thursday 20 June 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received and progress against the 2023-24 Internal Audit Plan be noted.
Woking Borough Council
Internal Audit Progress Report
Audit & Governance Committee – 20 June 2024 Date Prepared: 6 June 2024 Contents
01 Snapshot of Internal Audit Activity 02 Reports Issued Since Last Committee 03 Overview of Internal Audit Plan 2023/24 04 Outstanding work from 2022/23 Audit Plan 05 Overview of Internal Audit Plan 2024/25 06 Definitions of Assurance
Disclaimer This report (“Report”) was prepared by Forvis Mazars LLP at the request of Woking Borough Council and terms for the preparation and scope of the Report have been agreed with them. The matters raised in this Report are only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information provided in this Report is as accurate as possible, Internal Audit have only been able to base findings on the information and documentation provided and consequently no complete guarantee can be given that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required.
The Report was prepared solely for the use and benefit of Woking Borough Council and to the fullest extent permitted by law Forvis Mazars LLP accepts no responsibility and disclaims all liability to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. Please refer to the Statement of Responsibility in this report for further information about responsibilities, limitations and confidentiality.
2 Woking Borough Council - Internal Audit Progress Report – June 2024 01 Snapshot of Internal Audit Activity Introduction Internal Audit Progress – 2023/24 Plan Internal Audit is required to provide a regular report on progress and key findings Since the last Committee in April 2024, significant progress has been made with to the Audit and Governance Committee (Committee). This report covers internal the remaining work involved in the 2023/24 Plan. audit activity and performance since our last report to the Committee in April 2024 and includes: Fieldwork for all reviews has now been fully completed.
• An update on progress in delivering the revised 2023/24 Plan followed by a Three of the reports which had been issued in draft the last meeting have now summary of reports issued, and recommendations raised; been finalised. One of these, Income Management and Systems Reconciliations, • An update on outstanding work from the 2022/23 Plan reported at the last is still outstanding. The draft report arising from the Accounts Payable review Committee. All outstanding reports for the 2022/23 Audit Plan have now been has now also been issued. finalised; and • An update on progress with the 2024/25 Plan. We expect to receive responses and finalise the three remaining draft reports issued by the end of June 2024. The revised 2023/24 Plan was approved in September 2023. It comprised 11 audits and 257 audit days. The table below provides a summary of current progress relevant to the 2023/24 Plan. Details of reports issued since the last Committee (including outstanding 2022/23 reports) is provided at 03 and status of the Plan as it relates to the table at 04.
Audit Status Number of reviews Percentage % Finalised 5 45% Draft report (issued) 4 36% Fieldwork in progress 0 0% Cancelled/Deferred 2 19% Total 11 100%
Woking Borough Council - Internal Audit Progress Report – June 2024 02 02 Reports Issued Since Last Committee – 2023/24 Audit Plan We have four categories by which we classify internal audit assurance over the processes we examine: Substantial, Limited, Moderate and Unsatisfactory.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress Report June 2024Report | 551 KB | DownloadRead as text |
PDF |
Internal Audit Progress Report STA24-015Report | 72 KB | Download |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.