Resolved
RESOLVED That the report be received.
Audit and Governance Committee decided this item on Thursday 21 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be received.
1.1To facilitate the Council’s consideration of the Public Interest Report (PIR) into Woking’s historic approach to investments and borrowing and its response to the Report’s findings and recommendations. The report fulfils the statutory duty as set out in Local Audit and Accountability Act 2014 – S24 and Schedule 7 – 5 (5) and (6).
2.1Council is requested to:
RESOLVE THAT
(i) the recommendations set out in the Grant Thornton Public Interest Report be accepted in full;
(ii) the Council’s Improvement and Recovery Plan be reviewed and updated as necessary to take account of the PIR findings and recommendations;
(iii) the Council notes that Commissioners will consider taking forward further enquiries arising from the report; and
(iv) the Council notes that the Chief Executive has contacted Surrey Police already to make clear that, should any evidence emerge of criminality or misfeasance in public office, this will be referred to them for investigation.
3.1In July 2023, the Council commissioned its recently appointed external auditors, Grant Thornton, to review the Council’s historic approach to investment and borrowing. This was to:
WBC24-048 Public Interest Report from Grant Thornton
i. Provide a comprehensive overview of the events and decisions that culminated in the unprecedented financial challenge now facing Woking.
ii. To help the Council ensure it addresses the fundamental weaknesses in its historic approach, so that action can be taken to rectify these to eliminate the risk of any repetition in the future.
3.2The extensive research carried out as part of the review has been brought together by Grant Thornton in the form of a succinct but comprehensive explanation of a complicated sequence of events and decisions over several decades and draws out the key failings.
3.3As Grant Thornton have issued their report ‘in the public interest’, the Council is following the process laid out in paragraphs 8.16 - 8.18 of Appendix A attached. To assist Members’ consideration of the PIR findings, Grant Thornton will be attending the Council meeting itself to answer questions on their report.
3.4As the Council continues its work to address a plethora of legacy decisions and actions, there is the potential for yet more issues to come to light but these are likely to reinforce Grant Thornton’s identification of the fundamental historic weaknesses in governance, financial and risk management and, indeed, organisation culture. These weaknesses were compounded by failings in the external checks and balances that local government relies on but that should not detract from the Borough Council’s culpability for what occurred.
4.1It is difficult to envisage an option that would be appropriate for the Council to consider, other than to accept the recommendations from Grant Thornton in full. In the circumstances, to do otherwise would be irresponsible.
4.2More specifically, it would be appropriate for the Council and Commissioners to review the Improvement and Recovery Plan to assess the degree to which it might need expanding to take account of any of Grant Thornton’s findings generally as well as their specific recommendations covering, for example, the management of audit and some form of skills assessment to check that staff and Members are equipped with the understanding and knowledge they need to discharge their respective roles fully.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public Interest Report from Grant Thornton WBC24-048.Report | 85 KB | DownloadRead as text |
PDF |
WBC24-048 Appendix: Grant Thornton Public Interest ReportAppendix | 666 KB | Download |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.