The Executive Resolved That (i) following a competitive open market disposal process, the site be sold freehold to the recommended bidder; and (ii) authority be delegated to the Strategic Director - Corporate Resources, in consultation with the Portfolio Holder, to complete the sale. Reason: To secure the proposed regeneration of the Triangle Site and to realise the capital value as part of the current managed site disposal process.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1Following an open market disposal process, to approve the proposed freehold sale of The Triangle Site, Guildford Road, Woking GU22 7PF.
Recommendations
2.1The Executive is requested to:
Resolve that
i. Following a competitive open market disposal process, the site be sold freehold to the recommended bidder; and
ii. Authority be delegated to the Strategic Director - Corporate Resources, in consultation with the Portfolio Holder, to complete the sale.
Reason for decision
2.2To secure the proposed regeneration of the Triangle Site and to realise the capital value as part of the current managed site disposal process.
3.0Proposal and Outcome
3.1Following an open market sales initiative undertaken on behalf of the authority by Curchod and Seymour’s as the retained agents, we invited interested parties to submit best bids.
3.2The recommended purchaser submitted the highest financial offer on a conditional basis subject to planning and satisfactory ground investigation surveys. Those surveys will be undertaken post acceptance of the offer.
EXE25-080 Asset Disposal – Triangle Site, Woking Centre
Background
4.1The Triangle site was assembled by the authority to regenerate the area, facilitate additional town centre housing and to allow for the potential widening of the Victoria Arch Bridge.
4.2The site is bounded by Victoria Road to the north, Guildford Road to the west and amounts to 0.465 hectare (1.15 acre). The Triangle site is predominately owned by Woking Borough Council and is over 80% cleared.
4.3The site has two smaller landholdings which have not been acquired to date despite attempts to do so. It is considered that in order to complete the land assembly the authority may need to utilise its compulsory purchase powers. We understand that a resolution to support the final land acquisitions through CPO powers was granted previously although this will need to be updated/refreshed at the appropriate time.
4.4As set out in 4.1 above one of the original drivers behind the site assembly was to allow for the widening of the Victoria Arch Bridge.
4.5We have an ongoing dialogue with SCC regarding the future of the Bridge scheme and wider proposals for realigning the immediate road network. A meeting was held with SCC on 7 January 2025 to discuss the safeguarded land which forms part of the Triangle site and to review potential changes to the highways network in the light of our proposed site marketing campaign.
4.6SCC appreciate that this important site needs to be brought forward for redevelopment and have made various suggestions regarding how the site can be redeveloped.
4.7There is no legal obligation to continue to protect part of the site for the bridge widening scheme and Network Rail has indicated there is no appetite to proceed. We believe that for all practical purposes that any scheme to reconstruct the bridge is no longer either financially practicable or supported by key stakeholders.
4.8We have agreed that once the proposed purchasing party undertakes their formal pre-app consultations SCC and other key stakeholders such as Network Rail will be included as important early consultees.
4.9Marketing of the Triangle site commenced in late 2024 and a bidders pack was prepared by the agents and interested parties were invited to submit proposals on the following basis.
4.10Bidders were invited to submit bids on The Triangle and Gateway sites that form the Diamond Portfolio. The agents stipulated that they were inviting bids for the Council’s interest in either or both sites and the following supporting information was to be provided.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.