SANG Delivery Programme EXE25-087

Agreed Executive 1 paper

Executive agreed this item on Monday 21 July 2025. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

The Executive Resolved That (i) the project to deliver Suitable Alternative Natural Green Space (SANG) be agreed; and (ii) the funding requested be agreed. Reason: The decision is made in the context of the urgent need to increase SANG capacity to allow new, much needed homes to be brought forward, and to mitigate the risks associated with current limited available capacity.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To agree the scope and funding for a project to design and deliver Suitable Alternative Natural Green Space (SANG) to mitigate the impact of all new housing development in Woking.

Recommendations

2.1The Executive is requested to:

Resolve that

i. The project to deliver Suitable Alternative Natural Green Space (SANG) be agreed; and

ii. The funding requested be agreed.

Reason for decision

2.2The decision is made in the context of the urgent need to increase SANG capacity to allow new, much needed homes to be brought forward, and to mitigate the risks associated with current limited available capacity.

EXE25-087 SANG Delivery Programme

3.0Proposal and Outcome

3.1The proposal is to initiate a project to design and deliver SANG, initially focussing on those sites identified in the Site Allocations Development Plan Document (SADPD), which is legally required to mitigate the impact of new housing development in the Thames Basin Heath Special Protection Area (TBHSPA) which covers the whole Borough. The principal aim of the project is to ensure sufficient SANG is available to mitigate already consented schemes as well as to build capacity for future approvals.

Background

4.1In order to grant planning permission for any new residential development in the Borough, SANG needs to be allocated to each new dwelling. To date that allocation has taken place when development commences and there has been sufficient SANG to meet the requirements. However, in the last 2 years we have seen a significant increase in the number of homes consented, mainly within Woking Town Centre, and the available capacity within existing SANGs is limited. Furthermore, Woking housing targets, set by Government, are set to increase from 292 homes per year to 786, so it is critical that we build capacity to allow these new homes to come forward, and for existing consented schemes to commence development. In the absence of SANG being delivered, Natural England will object to all new applications coming forward, and will also have the option of putting injunctions on consented schemes from commencing until such time as SANG can be allocated to them. So there is an urgent need for this work to take place.

4.2Alongside this, we are also consulting on an updated TBHSPA avoidance strategy, as agreed by the Executive at its meeting on 12 June 2025. The updates to the strategy mean that we will move to allocating SANG to grant of planning permission rather than commencement of development, giving greater certainty on the delivery of new much needed new homes, and also to review the financial mechanism for funding SANG delivery and long term maintenance. The SANG delivery project, in addition to meeting a current capacity challenge, will allow for the transition to this new model which would bring us in line with the way other authorities within the TBHSPA manage their SANG.

4.3The allocated sites within the SADPD that would be prioritised include the Byfleet SANG (land to the south of Parvis Road) (GB12), the second SANG at Gresham Mill (GB16) and an extension to the Brookwood Farm SANG (GB13).

4.4The project will be managed internally, but will need an additional dedicated resource, as there is very limited capacity within the existing structure. The resource could be an existing officer, whose role is then backfilled to ensure existing service commitments are met. Alternatively, a consultant could be brought in to run the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SANG Delivery Programme EXE25-087Report 96 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
AB
Councillor Ann-Marie BarkerChair, present
EN
Councillor Ellen NicholsonVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LL
Councillor Liam LyonsCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, present
KF
Kevin FosterOfficer, present
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, present

All 15 on the meeting page

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open