The Executive Resolved That (i) the project to deliver Suitable Alternative Natural Green Space (SANG) be agreed; and (ii) the funding requested be agreed. Reason: The decision is made in the context of the urgent need to increase SANG capacity to allow new, much needed homes to be brought forward, and to mitigate the risks associated with current limited available capacity.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1To agree the scope and funding for a project to design and deliver Suitable Alternative Natural Green Space (SANG) to mitigate the impact of all new housing development in Woking.
Recommendations
2.1The Executive is requested to:
Resolve that
i. The project to deliver Suitable Alternative Natural Green Space (SANG) be agreed; and
ii. The funding requested be agreed.
Reason for decision
2.2The decision is made in the context of the urgent need to increase SANG capacity to allow new, much needed homes to be brought forward, and to mitigate the risks associated with current limited available capacity.
EXE25-087 SANG Delivery Programme
3.0Proposal and Outcome
3.1The proposal is to initiate a project to design and deliver SANG, initially focussing on those sites identified in the Site Allocations Development Plan Document (SADPD), which is legally required to mitigate the impact of new housing development in the Thames Basin Heath Special Protection Area (TBHSPA) which covers the whole Borough. The principal aim of the project is to ensure sufficient SANG is available to mitigate already consented schemes as well as to build capacity for future approvals.
Background
4.1In order to grant planning permission for any new residential development in the Borough, SANG needs to be allocated to each new dwelling. To date that allocation has taken place when development commences and there has been sufficient SANG to meet the requirements. However, in the last 2 years we have seen a significant increase in the number of homes consented, mainly within Woking Town Centre, and the available capacity within existing SANGs is limited. Furthermore, Woking housing targets, set by Government, are set to increase from 292 homes per year to 786, so it is critical that we build capacity to allow these new homes to come forward, and for existing consented schemes to commence development. In the absence of SANG being delivered, Natural England will object to all new applications coming forward, and will also have the option of putting injunctions on consented schemes from commencing until such time as SANG can be allocated to them. So there is an urgent need for this work to take place.
4.2Alongside this, we are also consulting on an updated TBHSPA avoidance strategy, as agreed by the Executive at its meeting on 12 June 2025. The updates to the strategy mean that we will move to allocating SANG to grant of planning permission rather than commencement of development, giving greater certainty on the delivery of new much needed new homes, and also to review the financial mechanism for funding SANG delivery and long term maintenance. The SANG delivery project, in addition to meeting a current capacity challenge, will allow for the transition to this new model which would bring us in line with the way other authorities within the TBHSPA manage their SANG.
4.3The allocated sites within the SADPD that would be prioritised include the Byfleet SANG (land to the south of Parvis Road) (GB12), the second SANG at Gresham Mill (GB16) and an extension to the Brookwood Farm SANG (GB13).
4.4The project will be managed internally, but will need an additional dedicated resource, as there is very limited capacity within the existing structure. The resource could be an existing officer, whose role is then backfilled to ensure existing service commitments are met. Alternatively, a consultant could be brought in to run the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.