2025-26 Quarter Two Strategic Risk Register AUD25-036
AgreedFinance2 papers
AI summaryWoking's Audit and Governance Committee noted the Quarter Two Strategic Risk Register, which lists 12 strategic risks with 7 above the Council's appetite, and passed its comments to the Corporate Leadership Team for formal review.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedPoints raised passed to Corporate Strategy team for CLT review
MoneyNo additional costRisk management within existing staff resources
What happens nextCLT to review commentsCorporate Leadership Team to formally review feedback
Who it affectsCouncil risk managementTwelve strategic risks, seven beyond stated appetite
What was decided
The Committee noted the Quarter Two Strategic Risk Register report. Report P4
Points raised by the Committee will be passed to the Corporate Strategy team for formal review by the Corporate Leadership Team.
The report was last reviewed and updated by CLT on 29 October 2025. Report 1.1
Why
The Strategic Risk Register provides the Committee with the most recent position on threats and opportunities facing Council activities. Report 1.1, 3.1
Twelve strategic risks have been identified, with seven scoring beyond the Council's stated risk appetite and therefore requiring closer monitoring. Report P10, P11, 4.2
No risks are rated at the most significant score of 16, an improvement on the previous quarter when SR03 and SR10 were rated 16, and every risk has mitigatory actions to bring it within acceptable appetite. Report P12, P13
What happens next
Points raised by the Committee will be sent back to the Council's Corporate Strategy team for formal review by the Corporate Leadership Team.
The Strategic Risk Register will continue to be updated quarterly and reviewed at CLT Quarterly Assurance Meetings. Report 3.1, 4.2
The Commercial Team will continue to meet regularly with risk owners for centralised monitoring and has additional recruited capacity for risk management. Report 4.3, 4.4
Options considered
Chosen: Note the report and pass Committee comments to the Corporate Strategy team for CLT review Report P3, P4
Implications
Legal: No specific legal implications arising from the report. Report 5.1
Financial: Risk management is carried out within existing staff resources and will not result in any additional costs. Report 5.2
Equalities: No specific requirements for consultation or Equality Impact Assessments. Report 5.4
Climate: No specific climate change implications arising from this report. Report 5.5
Risk: Seven of twelve strategic risks are beyond the Council's stated risk appetite and require closer monitoring. Report P11
Other: A specific risk relating to Local Government Reorganisation has been identified and recorded on the Strategic Risk Register, but ongoing risk management will have no bearing on the reorganisation. Report 5.6, 5.7
Who and where
Woking Borough Council services covered by the Strategic Risk Register Report 3.1, 4.5
Corporate Leadership Team as risk owners Report 3.1
Commercial Team providing risk management guidance and monitoring Report 3.1, 4.4
Directorate services feeding localised risks into the Strategic Risk Register Report 4.5
Timeline
12 June 2025: Executive received update on risk management; Strategic Risk Register comprehensively revised Report 4.1
29 October 2025: Strategic Risk Register last reviewed and updated by CLT Report 1.1
2025-12-15: Audit and Governance Committee considered Quarter Two Strategic Risk Register
Quarterly: Strategic Risk Register is updated and formally reviewed at CLT Quarterly Assurance Meetings Report 3.1, 4.2
Plain English for the jargon
Strategic Risk Register: A register of the Council's key strategic risks and their mitigations, updated quarterly by the Corporate Leadership Team.
CLT: Corporate Leadership Team, the senior officer group with functional responsibility for risk management.
Risk appetite: The level of risk the Council has agreed it is willing to accept; risks scoring above this require closer monitoring.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
It was agreed that the points raised above would be passed back to the Council’s Corporate Strategy team for formal review by its owner, the Corporate Leadership Team. Resolved That the report be noted and the points raised by the Committee be passed back to the Corporate Strategy team for formal review by the Corporate Leadership Team.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1The purpose of this report is to provide the Audit and Governance Committee with the most recent version of the Strategic Risk Register which was last reviewed and updated by CLT on 29 October 2025 (attached as Appendix 1), following the recent review of the Terms of Reference undertaken by the Monitoring Officer and approved by the Committee.
Recommendations
2.1The Audit and Governance Committee is requested to:
Resolve that
i. The report be noted.
Background
3.1Risk management is the process that enables the organisation to methodically identify and manage the threats and opportunities that might exist within a Council activity. It is not a one-off activity; it is part of a continuous process that runs throughout Council activities, integrated into the culture of the Council with an effective strategy and be led from the top. The functional responsibility for risk management rests with the Corporate Leadership Team (CLT), with all senior managers responsible, with guidance and support from the Commercial Team, for ensuring risk management arrangements are deployed in their functions, services, and areas of responsibility. The arrangements and outputs are formally reviewed by CLT at Quarterly Assurance Meetings.
AUD25-036 2025/26 Quarter Two Strategic Risk Register
4.0Risk Management / Strategic Risk Register
4.1On 12 June 2025, the Executive received an update on risk management progress. Directorate risks across Council services were reviewed and refreshed, while the Strategic Risk Register was comprehensively revised to enhance accessibility, align with best practice, clarify mitigation actions with defined deadlines, and provide improved tracking of risk trends and audit trails.
4.2The Strategic Register is updated quarterly and was last updated by CLT in October 2025 and is attached at Appendix 1. Highlights from the risk register include:
• Twelve strategic risks have been identified.
• Seven risks have a score which is beyond the Council’s stated risk appetite i.e., these risks are higher than agreed appetite levels and will require closer monitoring
• No risks are marked with the most significant risk score (16). This reflects positively on the previous quarter, where there were two risks rated 16; SR03 and SR10.
• Every risk has mitigatory actions to bring its actual score to within acceptable appetite levels.
4.3Additional resource has been recruited to the Commercial Team increasing capacity for, among other things, risk management.
4.4The Commercial team meets regularly with risk owners for centralised monitoring of all risks.
4.5Directorate risk registers feed into the Strategic Risk Register and monitor more localised/operational risks.
5.0Implications
Legal
5.1There are no specific legal implications arising from this report.
Resources (including finance)
5.2The management of risk and business continuity is undertaken within existing staff resources and will not result in any additional costs.
Risks and Mitigation
5.3Strategic risks and associated mitigations are detailed at Appendix 1.
Consultation, Equality Impact Assessments
5.4There are no specific requirements for consultation or Equality Impact Assessments in relation to this report.
Environment and Climate Change
5.5There are no specific climate change implications arising from this report. 2025/26 Quarter Two Strategic Risk Register
Local Government Reorganisation
5.6The ongoing management of business continuity and risk management arrangements will have no bearing on Local Government Reorganisation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.