Statement of Accounts 2023-24 and 2024-25. AUD26-001
ApprovedCommittee7 papers
AI summaryWoking Borough Council approves 2023/24 and 2024/25 accounts after Grant Thornton issues disclaimed opinions, with £2.2 billion debt and £500 million government repayment in principle.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth 2023/24 and 2024/25 statements approved
Money£500m government debt repayment agreedCouncil total debt £2.2bn at 31 March 2025
What happens nextWork on 2025/26 accounts and prior BDO audits. Statutory backstop date 27 February 2026
Who it affectsWoking Borough Council and residentsTransition to new unitary arrangements in 2027
What was decided
The Council approved the 2023/24 and 2024/25 statement of accounts following Grant Thornton's audit, received the auditor's annual report and audit findings reports, approved management responses to audit recommendations, and approved the management representation letters for signing by the Strategic Director of Finance and Resources and the Chair of Audit and Governance Committee. Report P3, P4, P5, P6
Grant Thornton expect to issue disclaimed opinions on both the 2023/24 and 2024/25 statement of accounts, continuing the four years of disclaimed audits from BDO covering 2019/20 to 2022/23. Report 4.5, 4.12, P38
Why
Grant Thornton could not conclude the audit mainly due to lack of assurance over prior year balances and the time needed for the Council's finance team to provide audit evidence, with no substantive audit testing having been carried out since 2018/19. Report 3.7, 3.8, P21
No substantive audit testing was undertaken on the 2023/24 statement of accounts due to insufficient time before the 28 February 2025 backstop date, with technical review only. Report 3.4, 4.12
By 31 March 2025 the Council's total debt had risen to £2.2 billion, with the UK Government agreeing in principle on 28 October 2025 to repay £500 million, indicating the debt is too high to manage locally. Report 4.2, P28
What happens next
Work will continue in 2026 to implement Grant Thornton's recommendations, with key changes to the 2025/26 closedown process, to rebuild assurance towards an unqualified audit opinion. Report 3.8, P21, 6.5
Issuance of 2023/24 and 2024/25 audit opinions depends on BDO issuing audit opinions for the 2019/20 to 2022/23 accounts, and work on the Council's capitalisation directions will continue into next year's audit. Report 3.9, 4.7
Completion of the external audits for past accounts will support a smoother transition to new unitary arrangements in 2027 as part of local government reorganisation. Report 6.10, P64
The money
£306,112 Audit scale fee for 2023/24 set by Public Sector Audit Appointments Limited Report 6.6, P57
£326,250 Audit scale fee for 2024/25 set by Public Sector Audit Appointments Limited Report 6.6, P57
£2.2 billion Council's total debt as at 31 March 2025 Report 4.2, P28
£500 million Debt repayment agreed in principle by UK Government on 28 October 2025 Report 4.2, P28
Options considered
Chosen: Approve 2023/24 and 2024/25 statement of accounts following Grant Thornton's audit. Required to meet statutory backstop date of 27 February 2026 and continue the Council's recovery journey to rebuild audit assurance Report 6.4
Chosen: Receive the auditor's annual report and audit findings reports Report P4
Chosen: Approve management responses to audit recommendations in Appendices B and C Report P5
Chosen: Approve the 2023/24 and 2024/25 management representation letters for signing. Formal requirement of the audit process; letter must be signed jointly by the Section 151 Officer and the Chair of the Audit and Governance Committee Report 5.2
Implications
Financial: Council's total debt of £2.2 billion by 31 March 2025, with £500 million government repayment in principle, signals ongoing financial sustainability weakness despite progress on the Improvement and Recovery Plan. Report 4.2, P28
Legal: Approval is required under Section 9(2) of the Accounts and Audit 2015, with Full Council being the correct decision maker as this function has not been delegated. Report 6.2, P52
Risk: Audit opinions for 2023/24 and 2024/25 remain dependent on BDO issuing opinions for 2019/20 to 2022/23, and the capitalisation directions for 2023/24 and 2024/25 remain provisional. Report 3.9, 4.7
Governance: Significant weaknesses in governance and in arrangements for economy, efficiency and effectiveness remain, with issues in regulatory compliance for housing, procurement, loans and contracts during 2024/25. Report 4.2, P28
Other: Completion of the external audits for past accounts will support transition to new unitary arrangements in 2027 under local government reorganisation. Report 6.10, P64
Staffing: An Interim Corporate Restructuring Officer was appointed centrally in July 2025 as part of wider governance changes to the Council's companies following weak commercial recovery. Report 4.2, P28
Who and where
Woking Borough Council as the accountable body for the audited statements and management representation letters Report 5.1
Strategic Director of Finance and Resources and the Chair of Audit and Governance Committee as joint signatories of the management representation letters Report 5.2
Grant Thornton as the current external auditor issuing the disclaimed opinions Report 3.7, 4.5
BDO as the previous external auditor whose outstanding opinions for 2019/20 to 2022/23 are a precondition for current audit opinions Report 3.9
Council-owned companies and residents of the borough affected by the Council's financial position and reorganisation to new unitary arrangements in 2027 Report 4.2, 6.10
Timeline
June 2023: Section 114 Notice issued, leading to the need for capitalisation directions Report 5.3
28 February 2025: Statutory backstop date for the 2023/24 audit, before which no substantive testing could be completed Report 4.12
31 March 2025: Closing balance date for the 2024/25 financial year and Council's total debt of £2.2 billion Report 3.4, 4.2
18 September 2025: Audit and Governance Committee meeting at which Members requested changes to the 2024/25 statement of accounts Report 3.6
28 October 2025: UK Government agreed in principle to repay £500 million of the Council's debt Report 4.2, P28
Late December 2025: Grant Thornton continued working on the 2024/25 audit until this point Report 3.7
12 February 2026: Council meeting at which the statements of accounts and management representation letters were approved
27 February 2026: Statutory backstop date for publication of the audited 2024/25 statement of accounts Report 5.5, 6.4
2027: Expected transition to new unitary council arrangements under local government reorganisation Report 6.10, P64
Plain English for the jargon
Disclaimed opinion: An audit opinion issued when the auditor is unable to gather sufficient evidence to form an opinion on the financial statements.
Backstop date: Statutory deadline by which audited accounts must be published, after which a disclaimer is required if the audit is not complete.
Capitalisation direction: Government approval allowing a council to treat certain revenue expenditure as capital, used here following the June 2023 Section 114 Notice.
Section 114 Notice: A formal notice issued by a council's chief finance officer when the council's spending is likely to exceed its resources, as happened at Woking in June 2023.
Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of the council's financial affairs, equivalent to the Strategic Director of Finance and Resources at Woking.
Managing Director Commissioner: A commissioner appointed by central government to lead a financially distressed council, taking on the role of the council's most senior officer.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9i
Resolved
Resolved That, noting the limitations, recommendations and risks set out in the External Auditor’s report, (i) the 2023/24 and 2024/25 statement of accounts be approved following Grant Thornton’s audit; (ii) the auditor’s annual report and audit findings reports be received; (iii) the management responses to the audit recommendations in the auditor’s annual report 2023/24 and 2024/25 (at Appendix B), and in the audit findings report 2024/25 (at Appendix C) be approved; and (iv) the 2023/24 and 2024/25 management representation letters (at Appendices E and F, respectively) be approved and then the Strategic Director of Finance and Resources and the Chair of Audit and Governance Committee sign it on behalf of the Council.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
(i) the 2023/24 and 2024/25 statement of accounts be approved following Grant Thornton’s audit;
(ii) the auditor’s annual report and audit findings reports be received;
(iii) the management responses to the audit recommendations in the auditor’s annual report 2023/24 and 2024/25 (at Appendix B), and in the audit findings report 2024/25 (at Appendix C) be approved; and
(iv) the 2023/24 and 2024/25 management representation letters (at Appendices E and F, respectively) be approved and then the Strategic Director of Finance and Resources and the Chair of Audit and Governance Committee sign it on behalf of the Council.
3.0Statement of Accounts
3.1The audited statement of accounts for 2024/25 is attached in Appendix A. The prior year 2023/24 statement of accounts can be viewed using the link below:
Statement of Accounts 2023-24
3.2The statement of accounts have been prepared following the "Code of Practice on Local Authority Accounting in the United Kingdom based on International Financial Reporting Standards" issued by the Chartered Institute of Public Finance and Statement of Accounts 2023/24 and 2024/25 - External Audit
Accountancy and the Local Authority (Scotland) Accounts Advisory Committee (‘’the Code’’).
3.3The Code constitutes the “proper accounting practices” required by Section 21(2) of the Local Government Act 2003 and deviations from it will usually lead to a qualified audit opinion. The Council is required to prepare a statement of accounts in compliance with the Accounts and Audit Regulations made under section 32 of the Local Audit and Accountability Act 2014 and therefore has a statutory duty to comply with the Code requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
ThamesWey Energy Limited (TEL) EXE26-078Resolved That following the acquisition of the shares of ThamesWey Limited in ThamesWey Energy Limited by the Council...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.