Resolved
Resolved That (i) the External Audit Plan for 2024-25 be received; and (ii) the Audit Progress Report be received.
Audit and Governance Committee decided this item on Thursday 19 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That (i) the External Audit Plan for 2024-25 be received; and (ii) the Audit Progress Report be received.
1.1This report provides an update on the 2024/25 final accounts and presents the External Audit Plan for 2024/25. In accordance with audit regulations, these items must be presented to Committee.
2.1The Committee is requested to:
Resolve that
i. the External Audit Plan for 2024/25 (Appendix 1) be received; and
ii. the Audit Progress Report (Appendix 2) be received.
3.0Final Accounts Update
3.1The Council successfully prepared and published its single entity accounts for the financial year 2023/24 within the Government’s prescribed Backstop Date deadlines. Additionally, elsewhere on the agenda, the group accounts for 2023/24 are presented to this committee.
3.2Regarding the audit of previous financial years, the Council is still awaiting BDO’s final, formal audit opinions on accounts from 2019/20 to 2022/23, which are anticipated to be qualified or disclaimed opinions due to outstanding issues identified during the audit process. Both commissioners and officers continue to press BDO to issue the outstanding opinions, as once issued, Grant Thornton (GT) can proceed to provide their independent audit opinion on the 2023/24 accounts. It is currently expected that this opinion will also be disclaimed, reflecting ongoing challenges in the audit. Update on Statement of Accounts 2024/25 & External Audit Plan
3.3In preparation for the current and upcoming financial years, GT has actively engaged with Council officers during March 2025 to carry out audit planning and initial substantive testing for both the 2023/24 and 2024/25 financial years.
3.4Regarding the 2024/25 final accounts, the draft outturn report for 2024/25 is planned for submission to the Executive on 12 June 2025. The unaudited accounts for 2024/25 are due to be published by the statutory deadline of 30 June 2025. The audited accounts are scheduled to be finalised and published by the Government’s backstop date of 27 February 2026, allowing adequate time for completion of audit procedures and any necessary adjustments.
4.0External Audit Plan & Progress Update
4.1Grant Thornton has prepared an audit plan for the 2024/25 Statement of Accounts (Appendix 1), alongside a progress update at Appendix 2.
4.2The plan outlines the key risks and requirements for 2024/25 and will be presented by a senior officer from Grant Thornton, who will be available at the meeting to answer any questions from Members.
4.3Officers are satisfied that the audit plan addresses the key financial and governance issues.
4.4The Committee is asked to receive the External Audit Plan for 2024/25 (Appendix 1).
4.5Grant Thornton expects to undertake 2024/25’s audit between September to December 2025, with the final audit report to signed off by 31 December.
4.6Grant Thornton will undertake the external audit in accordance with International Standards on Auditing (ISAs). Under ISA240 guidance, Grant Thornton submitted a number of audit queries to management, to inform its risk assessment for the audit.
4.7ISAs emphasise the importance of two-way communication between auditors and audit committees. As such, Grant Thornton has requested that Audit and Scrutiny Committee consider whether the management responses to the audit queries are consistent with members’ understanding and whether there are any further comments the committee wishes to make. The Response to these queries will be reported to the Audit Committee meeting in September 2025. This will be in time to inform the final audit and Grant Thornton have confirmed they are happy with this approach.
5.0Implications
Legal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on 2024-25 Statement of Accounts & External Audit Appendix 1 Audit Plan 24-25Appendix | 2 MB | Download |
PDF |
Update on 2024-25 Statement of Accounts & External Audit Appendix 2 Progress Report June 2025Appendix | 773 KB | Download |
PDF |
Update on Statement of Accounts 2024-25 and External Audit Plan STA25-019Report | 80 KB | DownloadRead as text |
Follow Audit and Governance Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. | Noted | Open |
| 18 Jun 2026 | Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. | Decided | Open |
| 18 Jun 2026 | External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... | Approved | Open |
| 18 Jun 2026 | Internal Audit Annual Report 2025-26 AUD26-014Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received. | Decided | Open |
| 18 Jun 2026 | Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.