Executive, Thursday 9 July 2026 at 7.00pm

Recommendation from Audit and Governance Committee - Risk Management Policy Review EXE26-092

Approved Executive 5 papers

AI summaryThe Executive has approved Woking Borough Council's Risk Management Policy 2026, subject to minor amendments to fix typographical errors, clarify risk scoring, and strengthen the explanation of opportunity against risk. The policy will then be finalised.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRisk Management Policy 2026 approved, subject to corrections
MoneyNot stated
What happens nextFinalise with amendmentsOfficers to make corrections before the policy is finalised
Who it affectsCouncil-wide risk managementHow the council identifies, manages and reports risk

What was decided

The Executive approved the Risk Management Policy 2026, as amended following the meeting of the Audit and Governance Committee on 18 June 2026. Report 1.1, 1.4, P5

The approval was given to consider the recommendation from the Audit and Governance Committee, which had reviewed the policy and a tracked-changes version. Report 2.2, 3.1, 3.4

Why

The policy has been refreshed to reflect changes to governance, reporting, risk appetite, and wider improvements to the council's risk management approach. Report 1.2

Members of the Audit and Governance Committee welcomed the refreshed approach but asked for further refinements to improve clarity and accessibility for both members and officers. Report 3.2

Commissioners had taken a close role in strengthening the framework because of historic weaknesses in the council's risk management, with risk awareness to be embedded at all levels. Report P29

What happens next

Officers will correct typographical errors before the policy is finalised. Report P13, P29

Officers will clarify the approach to risk scoring, including that risk scores are derived from probability and impact. Report P14, P29

Officers will strengthen the explanation of how risk management supports the identification and assessment of opportunities, while making clear that opportunity should not justify taking additional or disproportionate risk, and refer to root causes and drivers rather than symptoms. Report P15, P30

Options considered

  • Chosen: Approve the Risk Management Policy 2026, as amended following the Audit and Governance Committee meeting. Recommended by the Audit and Governance Committee after reviewing the refreshed policy and tracked-changes version Report P5, P32, 3.4

Implications

  • Governance: Updates the council's framework for identifying, managing and reporting risk, reflecting governance changes and Commissioner input. Report 1.2, P28
  • Risk: Strengthens risk awareness and embeds risk management at all levels, addressing historic weaknesses noted by Commissioners. Report P29
  • Other: Risks below the escalation threshold remain actively managed with director-level accountability; there is no single corporate issues register, with issues managed through existing service and project governance arrangements. Report P30

Who and where

  • Woking Borough Council members and officers, who will use the updated policy Report 3.2
  • The Audit and Governance Committee, which recommended the policy to the Executive Report 1.3, 1.4
  • Commissioners, who have taken a close role in strengthening the risk management framework Report P29

Timeline

  • 18 June 2026: Audit and Governance Committee reviewed the draft Risk Management Policy 2026 and recommended approval to the Executive, subject to amendments. Report 1.1, P27, P32
  • 2026-07-09: Executive approved the Risk Management Policy 2026, as amended following the Audit and Governance Committee meeting.

Plain English for the jargon

  • Risk appetite: The level and type of risk an organisation is willing to accept in pursuit of its objectives.
  • Risk scoring: A rating derived from combining the probability of a risk occurring with its impact.
  • Escalation threshold: The level at which a risk is considered serious enough to be escalated to senior officers or members.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

The Executive Resolved That the Risk Management Policy 2026 be approved, as amended following the meeting of the Audit and Governance Committee. Reason: To consider the recommendation from the Audit and Governance Committee.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Summary

1.1At its meeting held on 18 June 2026, the Audit and Governance Committee received a report updating the Committee on the Council’s risk management arrangements and setting out the updated Risk Management Policy 2026.

1.2The Policy has been refreshed to reflect changes to governance, reporting, risk appetite, and wider improvements to the Council’s risk management approach.

1.3The Audit and Governance Committee made a recommendation to the Executive for consideration. A copy of the draft minute extract is attached at Appendix A. A copy of the report to the Audit and Governance Committee is attached at Appendix B.

1.4The Audit and Governance Committee recommend to the Executive that:

The Risk Management Policy 2026 be approved, as amended following the meeting of the Audit and Governance Committee.

Recommendations

2.1The Executive is requested to consider the above recommendation from the Audit and Governance Committee and resolve accordingly.

Reason for decision

2.2To consider the recommendation from the Audit and Governance Committee.

EXE26-092 Recommendation from Audit and Governance Committee – Risk Management Policy Review

3.0Officer Comments

3.1The Committee reviewed the updated Risk Management Policy 2026 alongside a tracked-changes version, which highlighted the principal revisions made since the previous policy.

3.2Members welcomed the refreshed approach and requested a small number of further refinements to improve clarity and ensure the Policy is accessible to both Members and officers.

3.3In response to the Committee’s comments, officers will make the following amendments before the Policy is finalised:

i. correct any typographical errors;

ii. clarify the approach to risk scoring; and

iii. strengthen the explanation of how risk management supports the identification and assessment of opportunities, while making clear that opportunity should not justify taking additional or disproportionate risk.

3.4Subject to these amendments, the Committee recommended that the Executive approve the Risk Management Policy 2026.

3.5An updated Risk Management Policy is attached at Appendix C.

Report Ends Recommendation from Audit and Governance Committee – Risk Management Policy Review

Appendix A

DRAFT Minutes

of a Meeting of the

Audit and Governance Committee

held on 18 June 2026

Present: P Jasuja (Chair) Cllr G Cosnahan (V-Chair)

Cllr C Martin Cllr J Pearce Cllr S Oades A Ren

Absent: Councillor S Mukherjee.

7. Risk Management Policy Review AUD26-022

Toby Nash presented the updated Risk Management Policy 2026, which refreshed the Council’s existing arrangements to reflect governance changes, Commissioner input and continued improvement in identifying, managing and reporting risk.

Councillor Oades identified typographical errors and queried the explanation of risk scoring. Toby Nash agreed to correct the errors before the report went to Executive and to clarify that risk scores were derived from probability and impact. Sir Tony Redmond advised that Commissioners had taken a close role in strengthening the framework due to the historic weaknesses in the Council’s risk management and stressed that risk awareness needed to be embedded at all levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXE26-092 Appendix B: AUD26-022 Risk Management Policy ReviewAppendix 89 KB Download
PDF
EXE26-092 Appendix Ba: AUD26-022 Appendix 1: Risk Management Update (tracked changes)Appendix 1.5 MB Download
PDF
EXE26-092 Appendix Bb: AUD26-022 Appendix 2: Risk Management Update (clean version)Appendix 4.9 MB Download
PDF
EXE26-092 Appendix C: Updated Risk Management Policy 2026Appendix 4.9 MB Download
PDF
Recommendation from Audit and Governance Committee: Risk Management Policy Review EXE26-092Report 89 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 16 attended
AB
Councillor Ann-Marie BarkerChair, present
DH
Councillor Deborah HughesVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
EN
Councillor Ellen NicholsonCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, present
BK
Beverley KucharOfficer, apologies
AO
Adesuwa OmoregieOfficer, apologies
LS
Louise StrongitharmOfficer, present

All 16 on the meeting page

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies