Woking Borough Council
Executive, Wednesday 16 September 2026 at 7.30pm

Capital Works Programme (General Fund) Procurement EXE26-105

Agreed Executive 1 paper

AI summaryWoking Borough Council's Executive approved commencing procurement using the Southern Construction Framework for the four year Capital Works Programme with an indicative value of approximately £20.3 million.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUsing Southern Construction Framework
Money£20.3 millionIndicative value over four years
What happens nextContract award reportFurther Executive report after procurement
Who it affectsOperational property assetsCouncil estate requiring works

What was decided

Commenced procurement using Southern Construction Framework Intermediate Framework for Capital Works Programme Report P13

Delegated authority to Strategic Director Finance and Resources to select alternative framework if SCF unavailable unsuitable or unable to support requirements Report P14

Why

Establishes a compliant procurement route for Capital Works Programme projects that require Executive approval as Key Decisions Report 3.2

The Council has previously used Southern Construction Framework successfully and has direct experience with three of the four contractors on the framework Report 6.2

Pre-procurement market engagement confirmed market interest and supported the use of framework based procurement approaches Report 6.3

What happens next

A separate report will be submitted to the Executive following completion of the procurement exercise seeking approval to award any resulting contract(s) Report 4.4, 7.3

The procurement will be managed through existing resources within Property Services with support from the Procurement Team Report 8.5

The money

  • £20.3 million Indicative value of Capital Works Programme over four years Report 5.1

Options considered

  • Rejected: NHS Hard Facilities Management 2 Framework. Framework expires before governance process would allow contract award approval to be obtained Report P27
  • Rejected: Crown Commercial Service Framework. Supplier base primarily larger national contractors, considered less aligned with scale and profile of anticipated projects Report P28
  • Rejected: Standalone procurement exercise. Would increase timescales, resource requirements and costs compared with using an existing compliant framework Report P29
  • Rejected: Delay the decision. Would defer commencement and reduce ability to progress approved capital projects Report 6.4
  • Chosen: Southern Construction Framework Intermediate Framework. Most suitable route; Council previously used SCF successfully and has direct experience with three of four contractors Report 6.2

Implications

  • Legal: Use of framework is compliant with Procurement Act 2023 and Contract Standing Orders; competitive tendering process ensures best value Report 8.1
  • Financial: Approval commits only to procurement exercise; does not commit expenditure beyond officer resources; spend is within budget and medium term financial strategy Report 8.3, 8.4
  • Staffing: Procurement will be managed through existing resources within Property Services, Procurement Team and framework support team Report 8.5
  • Risk: Principal risk is delay in establishing procurement route; mitigated through review of three frameworks, market engagement and use of established framework Report 8.6, 8.7
  • Environment and climate: Environmental considerations will be incorporated into the procurement process where appropriate and proportionate to requirements Report 8.11
  • Other: Procurement designed to support continuity beyond local government reorganisation vesting day, with contract term and extension provisions for successor authority flexibility Report 8.12

Who and where

  • Operational property estate Report 5.1
  • Capital programme delivery Report 5.2

Timeline

  • 16 September 2026: Executive meeting approved procurement commencement
  • Four years: Duration of Capital Works Programme Report 5.1
  • After procurement completion: Separate Executive report for contract award approval Report 4.4

Plain English for the jargon

  • Southern Construction Framework Intermediate Framework: A compliant framework agreement for public sector construction procurement
  • Key Decision: A decision requiring Executive approval
  • Capital Works Programme General Fund: Council investment in operational property assets
  • Contract Standing Order 12.1: Governance requirement for procurement exercises resulting in Key Decisions
  • Procurement Act 2023: Legislation governing public procurement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

The Executive Resolved That (i) the procurement exercise to support future Capital Works Programme (General Fund) projects be commenced using the Southern Construction Framework (SCF) Intermediate Framework; and (ii) authority be delegated to the Strategic Director – Finance and Resources, in consultation with the Portfolio Holder, to take all necessary steps to undertake and complete the procurement exercise, including selecting and utilising an alternative compliant framework agreement should the Southern Construction Framework (SCF) Intermediate Framework become unavailable, unsuitable, or otherwise unable to support the Council's procurement requirements. Reason: To establish a compliant procurement route for future Capital Works Programme projects that require Executive approval as Key Decisions, whilst providing flexibility to utilise an alternative framework agreement should issues arise during the procurement process.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Summary

1.1The Council has approved a four-year Capital Works Programme with an indicative value of approximately £20.3 million. The programme provides investment in the Council's operational property assets and includes:

a) Statutory compliance and health and safety works.

b) Replacement of building elements and equipment that have reached the end of their service life.

c) Energy efficiency works.

1.2To deliver these works, the Council must establish an appropriate procurement route for the appointment of contractors.

1.3This report seeks approval to commence a procurement exercise using the Southern Construction Framework (SCF).

1.4No contracts are being awarded at this stage. A further report will be submitted to Executive seeking approval to award any resulting contract(s).

Purpose of report

2.1In accordance with Contract Standing Order 12.1, Executive approval is required before commencing a procurement exercise where the procurement will result in a Key Decision.

EXE26-105 Capital Works Programme (General Fund) Procurement

2.2This report seeks approval to commence the procurement exercise only. A further report will be submitted to the Executive following completion of the procurement process seeking contract award approval.

Recommendations

3.1The Executive is requested to:

Resolve That

(i) The procurement exercise to support future Capital Works Programme (General Fund) projects be commenced using the Southern Construction Framework (SCF) Intermediate Framework; and

(ii) Authority be delegated to the Strategic Director – Finance and Resources, in consultation with the Portfolio Holder, to take all necessary steps to undertake and complete the procurement exercise, including selecting and utilising an alternative compliant framework agreement should the Southern Construction Framework (SCF) Intermediate Framework become unavailable, unsuitable, or otherwise unable to support the Council's procurement requirements.

Reason(s) for Decision

3.2To establish a compliant procurement route for future Capital Works Programme projects that require Executive approval as Key Decisions, whilst providing flexibility to utilise an alternative framework agreement should issues arise during the procurement process.

4.0Proposal and Outcome

4.1It is proposed to undertake a procurement exercise using the Southern Construction Framework (SCF) Intermediate Framework to support the future delivery of Capital Works Programme (General Fund) projects.

4.2The procurement will establish a compliant route for the delivery of approved capital projects across the Council's estate, including statutory compliance, lifecycle replacement, decarbonisation and other capital investment works.

4.3The recommendation includes delegated authority to utilise an alternative compliant framework agreement should the Southern Construction Framework (SCF) Intermediate Framework become unavailable, unsuitable or otherwise unable to support the Council's procurement requirements.

4.4Approval of this report will enable the procurement exercise to commence. A separate report will be submitted following completion of the procurement process seeking approval to award any resulting contract(s).

4.5Success will be measured through the establishment of a compliant procurement arrangement that provides access to suitably qualified contractors, supports the delivery of approved capital projects and demonstrates value for money. Capital Works Programme (General Fund) Procurement

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Works Programme (General Fund) Procurement EXE26-105Report 92 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 14 attended
AB
Councillor Ann-Marie BarkerChair, present
DH
Councillor Deborah HughesVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
EN
Councillor Ellen NicholsonCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, apologies
SF
Stephen FitzgeraldOfficer, present
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, apologies
LS
Louise StrongitharmOfficer, present

All 14 on the meeting page

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open