1.1The purpose of this report is to set out progress made by SWBC Partnership in 2012/13 in accordance with the initial business case and the shared service’s 5 year business plan.
1.2The shared service has responded positively to the economic downturn and drop in income by reducing cost and maintaining expenditure well below income generated through charges:
• The actual expenditure has been maintained well below those set out in the initial business case; • The service continues to generate income levels exceeding direct costs for each partner authority despite continuing recession and downturn in the economy; • The service remains self financing with no contribution from tax payers;
1.3Final Expenditure against budget indicates an underspend, primarily due to not recruiting to full staffing levels. However, this has been offset by a shortfall in the shared service’s income in 2012/13. This shortfall has been primarily due to:
• Continuing economic downturn and drop in construction output;
• Increased private sector competition and drop in number of applications in domestic sector;
• Developers and builders seeking more competitive and cheaper application fees on housing and commercial projects.
1.4The service continues to make good progress against the proposals set out in the business case with little disruptions to customers and service users. Although the gradual reduction in staffing levels have ensured financial viability but at the same time this has impacted on the shared service’s resilience and ability to be more responsive to changes in the market conditions and workload demands. Resilience is a key factor in the future success of the service and must be considered as we exit the recession at some times in the future and move into economic growth.
1.5Performance shown in Appendix C is well above target with year end figures indicating levels above targets despite the teams continuing issues surrounding staff retention and resources.
Page 1 of 10 2. RECOMMENDATIONS
2.1That the annual Performance and Finance report is noted by the Joint Committee.
3.1It is just over four years since South Worcestershire Building Control Partnership was first established. 2012/13 has probably been the most challenging year since the establishment of the shared service with continuing economic downturn and little sign of recovery in construction activity.
3.2In 2012/13 SWBCP continued to face increased competition from the private sector building control bodies (Approved Inspectors) in all construction sectors but increasingly from a number of local independent approved inspectors in the domestic and small commercial sectors.
3.3Retention and recruitment of qualified staff continue to be challenging with a further two experienced surveyors leaving the partnership and moving to private sector BC bodies. As a result of staff shortages, the team was unable to achieve all its marketing objectives including the annual SWBCP Building Excellence awards.
3.4The service has responded positively to both increased competition and economic downturn and demonstrated a high degree of flexibility in mitigating financial pressures.
3.5However, there are still areas of work to be done in terms of marketing and customer interaction. A marketing forward plan is in place and there are plans for a number of agents/builders forums to be held in 2013/14 with the first one scheduled for early July.
3.6The service continues to make good progress against its 5 year business plan (currently under review) and initial business case which set out the the shared service at the first instance.
4. Progress in 2012/13 ( refer to appendix D )
4.1Progress and achievements in 2012/13:
4.2Implementation of the revised standard charges with an average fee increase of 5% from January 2013
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
South Worcestershire Building Control Partnership Annual Report 2012/13Report | 10 pages | DownloadRead as text |
Follow South Worcestershire Shared Services Partnership Joint Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Nov 2016 | MinutesThat the minutes of the meeting held on 16 th September 2016 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 25 Nov 2016 | Revenues & Benefits Shared Service Performance Report April to October 2016That the Joint Committee note the performance of the Revenue and Benefits Shared Services for the period April – Octo... | Noted | Open |
| 25 Nov 2016 | South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2016-17 and Budget for 2017-2018That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month... | Noted | Open |
| 25 Nov 2016 | Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetThat the Joint Committee: 1. note the operational performance and levels of customer satisfaction for the Worcestersh... | Noted | Open |
| 25 Nov 2016 | IT Shared Service Budget And Strategy ReportThat the Joint Committee: 1. note the Financial and Service Performance for 2016/17 to the end of October 2016; and 2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.