AI summaryWorcester City Council’s Place and Economic Development Committee approved the South Worcestershire Development Plan Main Modifications and recommended their publication for consultation from 6th January 2026 to 17th February 2026. [1.1] Consultation costs will be met from the existing SWDPR budget. [5.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCouncil approval and publication are recommended. [1.1]
MoneyNo significant financial implications [5.1]Consultation costs come from the existing SWDPR budget. [5.1]
What happens nextConsultation starts 6th January 2026 [1.1]Subject to three council approvals, it ends 17th February 2026. [P26]
Who it affectsPlan policies and future development [P26]Comments will inform the Inspectors' final report. [P26]

What was decided

The Committee approved the Main Modifications schedule and Appendices 2, 3, 4 and 5. It recommended that Council approve and publish them for a statutory six week public consultation from 6th January 2026 to 17th February 2026. Report 1.1

The Committee authorised the Head of Planning and Economic Development, with the Committee Chair and Vice-Chair, to make any necessary minor amendments before publication. Report 1.2

Why

The modifications arose from the updated evidence base and the hearings. The Inspectors agreed they are necessary to secure the plan's soundness, and the Council cannot unilaterally amend them. Report P10

The changes update housing and employment requirements, align the Green Belt policy with the latest national policy, and clarify strategic allocations and implementation. Report 2.7, P13, P17, 2.15

Not consulting would likely delay adoption, leave the Councils unable to demonstrate a five year housing land supply, and expose the area to further speculative development. Report 4.1

What happens next

Subject to approval by all three South Worcestershire Councils, the modifications will be published for a six week consultation from 6th January 2026 until 17th February 2026. Report P26

The Head of Planning and Economic Development may make necessary minor amendments before publication, with the Committee Chair and Vice-Chair. Report 1.2

All consultation comments will be sent to the Inspectors to inform their final report. If the Inspectors recommend the plan sound and legally compliant, each Council will consider adoption in March 2026. Report P26

Options considered

  • Chosen: Authorise the Main Modifications for consultation. The modifications are needed to support a sound and legally compliant plan. Consultation allows the examination to continue and moves towards adoption. Report 3.1, 4.1
  • Rejected: Do not authorise the Main Modifications for consultation. This would delay adoption, prevent a five year housing land supply, and leave the Councils exposed to speculative development. Report 4.1

Implications

  • Financial: No significant financial or budgetary implications arise for the consultation. Its costs will be met from the existing SWDPR budget. Report 5.1
  • Legal: The consultation will meet the relevant legal and regulatory requirements for progression of the Local Plan Examination in Public. The Inspectors have raised no concerns about legal compliance. Report 5.2
  • Risk: Not moving to this stage would prevent progress to plan adoption and leave Worcester and the wider plan area open to speculative development. Policies may carry less weight in planning decisions if considered out of date. Report 5.3
  • Staffing: Officer time is required to administer the consultation, assemble representations and send them to the Inspectors. Existing resources will be used unless additional resources are identified. Report 5.6
  • Equalities: No equality implications are identified. Anyone can make representations during the consultation. Report 5.5
  • Other: The Sustainability Appraisal and Habitats Regulations Assessment were reviewed and updated where needed. The modifications are not considered to significantly change their outcomes or the plan's overall sustainability. Report 2.19, P24
  • Other: The housing requirement would fall from at least 26,360 net additional dwellings to at least 18,852 net additional dwellings. The plan would provide an additional 21,357 dwellings, so no additional new allocations are proposed. The employment land requirement would change from 350.50ha to 313.80ha. The plan would provide an additional 336.18ha through existing commitments and allocations, so no additional new employment allocations are proposed. Report 2.7, P13
  • Other: The Green Belt policy would be updated to align with the latest national planning policy. Throckmorton would no longer be allocated and would become an area of search. The Rushwick travelling showpeople element would move to a separate policy, and a separate Development Plan Document for Gypsies, Travellers and Travelling Showpeople would no longer be needed. New policies would cover significant gaps, areas of informal recreation and four smaller site allocations. Report 2.9, 2.10, 2.12, 2.13, P20

Who and where

  • People wishing to make representations on the modifications Report 5.5
  • The Inspectors Report P26
  • All three South Worcestershire Councils Report P26
  • Officers administering the consultation and preparing representations Report 5.6
  • Worcester and the wider South Worcestershire Development Plan Review area Report 5.3
  • Housing, employment and associated community infrastructure facilities Report 5.8
  • The Throckmorton allocation Report 2.12
  • The Rushwick Expanded Settlement allocation Report 2.13

Timeline

  • September 2023: The South Worcestershire Development Plan Review was submitted for Examination in Public. Report 2.1, P5
  • January 2024 to December 2024: The evidence base was updated. Report P6
  • January 2025: A further examination stage took place before the hearings. Report P7
  • March to May 2025: The first hearing stage took place. Report P8
  • September 2025: The second hearing stage took place. Report P9
  • July/October 2025: Post hearing notes were received. Report P10
  • 6th January 2026 to 17th February 2026: The statutory public consultation runs. Report 1.1, P26
  • March 2026: If the Inspectors' final report recommends a sound and legally compliant plan, each Council will consider adoption. Report P26

Plain English for the jargon

  • Main Modifications: Changes to the submitted plan agreed with the Inspectors as necessary for soundness. The Council cannot amend them unilaterally. [P10]
  • Examination in Public: The process in which appointed Inspectors assess the plan through evidence updates, hearings and post hearing notes. [2.2] [P6] [P8] [P9] [P10]
  • SWDPR: The South Worcestershire Development Plan Review, which is the plan under examination. [2.1] [2.2]
  • NPPF: The national planning policy framework used to assess the plan and Green Belt policy. [2.4] [2.9]
  • Sustainability Appraisal: An assessment integrating social, environmental and economic considerations in plan preparation. [P24]
  • Habitats Regulations Assessment: An assessment of potential effects on the conservation objectives of Habitats and Birds Directive sites. [2.19]
  • Area of search: Land identified for possible consideration in a future plan review. [2.12]
  • Development Plan Document: A separate plan document. The report says one is no longer needed for Gypsies, Travellers and Travelling Showpeople. [2.10]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29

Resolved

That the Committee agree to: 1. approve the Main Modifications schedule, Appendix 1, and supporting documents (Appendices 2, 3, 4 and 5) and recommend to Council that they be approved and published for a statutory six-week public consultation from 6 th January 2026 to 17 th February 2026; and 2. authorise the Head of Planning and Economic Development, in consultation with Chair and Vice-Chair of Place and Economic Development Committee to make any necessary minor amendments to the documents for consultation prior to publication.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 6 pages

Recommendation

1.1The Committee approves and recommends to Council, approval of the Main Modifications schedule, Appendix 1, and supporting documents (Appendices 2, 3, 4 and 5), is published for a statutory six-week public consultation from 6th January 2026 to 17th February 2026; and

1.2Authorises the Head of Planning and Economic Development, in consultation with Chair and Vice-Chair of Place and Economic Development Committee to make any necessary minor amendments to the documents for consultation prior to publication.

Background

2.1The South Worcestershire Development Plan Review was submitted for Examination in Public in September 2023, and the ongoing process of examination has been taking place since.

2.2The Examination in Public process is led by the appointed Inspectors. Early in the process the Inspectors identified that an update to some of the evidence was required. To date the examination has taken place since 2023, according to the following timeline:

Submission September 2023

Updating of the evidence base January 2024- December 2024

MIQs January 2025

Hearings stage 1 March-May 2025

Hearing stage 2 September 2025

Post-hearing notes received July/October 2025 2.3 The Examination is on-going, the proposed Main Modifications, presented in Appendix 1, have been identified through the updated evidence base work and arising from the hearings, they have been agreed with the Inspectors and are considered necessary to secure the soundness of the SWDPR. They are a direct outcome of the examination process. Unlike previous stages of the plan-making process prior to submission and examination, there is no opportunity for the Council to unilaterally amend the modifications as they are specific changes agreed with the Inspectors as necessary to ensure the Plan’s soundness.

2.4The tests of soundness set out in the NPPF are: Local plans and spatial development strategies are examined to assess whether they have been prepared in accordance with legal and procedural requirements, and whether they are sound. Plans are ‘sound’ if they are: a) Positively prepared – providing a strategy which, as a minimum, seeks to meet the area’s objectively assessed needs; and is informed by agreements with other authorities, so that unmet need from neighbouring areas is accommodated where it is practical to do so and is consistent with achieving sustainable development; b) Justified – an appropriate strategy, taking into account the reasonable alternatives, and based on proportionate evidence; c) Effective – deliverable over the plan period, and based on effective joint working on cross-boundary strategic matters that have been dealt with rather than deferred, as evidenced by the statement of common ground; and d) Consistent with national policy – enabling the delivery of sustainable development in accordance with the policies in this Framework and other statements of national planning policy, where relevant.

Schedule of Main Modifications 2.5 The proposed Main Modifications are set out as a schedule in Appendix 1, the modifications are shown in the form of strikethrough for deletions and bold and underlined for additions to the text. The proposed modifications are made to the SWDPR as submitted to the Secretary of State in September 2023. There are a number of modifications that need to be made, but the main changes can be summarised as follows:

Strategic Policies 2.6 The Strategic Policies of the SWDPR provide the overall vision and priorities for the area, guiding long-term growth and addressing major challenges like housing, employment, and infrastructure needs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Schedule of Main ModificationsAppendix 1 278 pages Download
PDF
Schedule of Policies Map ModificationsAppendix 2 109 pages Download
PDF
Schedule of Additional ModificationsAppendix 3 9 pages Download
PDF
Sustainability Appraisal of the Main MdoficationsAppendix 4 409 pages Download
PDF
Habitats Regulations Assessment of the Main ModificationsAppendix 5 327 pages Download
PDF
South Worcestershire Development Plan Review Main Modifications and ConsultationReport 6 pages DownloadRead as text

At this meeting

Whole meeting
29South Worcestershire Development Plan Review Main Modifications and ConsultationThis decision
30South Worcestershire Local Development Scheme 2025-2027Approved

Who was there

12 of 12 attended
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperChair, present
JD
Councillor Jill DesayrahCommittee Member, present
AG
Councillor Adrian GregsonCommittee Member, present
EK
Councillor Ed KimberleyCommittee Member, present
RN
Councillor Robyn NorfolkChair, apologies, sent representative
TP
Councillor Tor PingreeCommittee Member, present
ER
Councillor Elena RoundCommittee Member, present
SS
Councillor Sue SmithCommittee Member, present as substitute
EW
Councillor Elaine WillmoreCommittee Member, present

On this subject at Worcester

Search all
  1. South Worcestershire Development Plan Review Main Modifications and ConsultationThis decision
  2. Adoption of the South Worcestershire Development Plan ReviewApproved
  3. South Worcestershire Five Year Housing Land Supply Report 2025Noted
  4. Referral Report from Place and Economic Development Committee, 17th December 2025 - South Worcestershire Development Review Main Modifications and ConsultationApproved
  5. Referral Report from Place and Economic Development Committee, 17th December 2025 - South Worcestershire Local Development Scheme 2025-2027Approved
  6. South Worcestershire Local Development Scheme 2025-2027Approved

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open