South Worcestershire Building Control Partnership - Strategic Review

Approved Committee 1 paper

South Worcestershire Shared Services Partnership Joint Committee approved this item on Wednesday 25 September 2013. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

That the Joint Committee:- 1. notes the progress made by the SWBCP Project Board with respect to identifying future options for the delivery of the service; and 2. approves the commencement of a procurement process to test the market for interest from the private sector management organisations in developing a Strategic Partnership (Option 4) to deliver the SWBCP and associated business case development.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to South Worcestershire Shared Services Partnership Joint Committee, 6 pages

Purpose of the report

1.1To follow on from the June 2013 strategic review report and apprise the Joint Committee of options for the future delivery of the South Worcestershire Building Control Partnership (SWBCP).

Recommendations

2.1That the Joint Committee note the progress made by the SWBCP Project Board with respect to identifying future options for the delivery of the service.

2.2That the joint Committee approve the commencement of a procurement process to test the market for interest from the private sector management organisations in developing a Strategic Partnership (Option 4) to deliver the SWBCP and associated business case development.

Background

3.1In September 2012, SWBCP Project Board agreed to review the possible options for the future delivery of the service.

3.2In June 2013, a report on future delivery models was presented to the SWBCP Project Board. The report considered a number of models for delivering the service in the future and recommended further exploration of the following options:

• Option1:To remain as existing Local Authority Partnership model (status quo)

• Option 2: To expand the partnership with neighbouring local authorities

• Option 3:To consider forming a Local Authority wholly owned company

• Option 4: To consider forming a strategic partnership with a management/commercial organisation.

3.3To remain viable in this commercially competitive market, SWBCP needs to be strong, resilient and agile enough to compete positively with the private sector Building Control organisations (Approved Inspectors), whilst continuing to meet its obligations under the Building Act.

3.4As explained below the Project Board consider that competition pressures, reducing income and the need to be far more commercial in approach means that a don nothing approach will not be sustainable in even the relatively short term. Therefore innovative action is required with the full support from the three partner authorities to ensure that SWBCP will continue to recover its chargeable service costs, make further savings on its non-chargeable service costs and generate additional income through growth in commercial activities.

3.5SWBCP in its current form is constrained both legislatively, operationally and to a degree financially in its ability to increase the resource, capacity and skills necessary to counter the challenge of competition from the Approved Inspectors. To overcome these constraints, SWBCP needs to continue to identify efficiencies and service improvements whilst seeking opportunities to retain and preferably increase market share and income. To some degree the four options include a degree of overlap in terms of certain flexibilities available to the service and steps it could take to meet its objectives. However, the need to put the service on a much more commercially competitive footing, provide a platform for potentially growing the service and managing risk suggest Option 4 is more likely to address the key objectives for the service on an appropriate timescale.

. 3.6. The key objectives in considering a new delivery model are:

• Secure and maintain a local and reputable building control service which will continue to deliver a quality and impartial service to meet the current and future needs of our local communities.

• Protect the viability of the Building Control service through an innovative and transformational model which enables SWBCP to maintain and grow market share both within and outside South Worcestershire

• Enhance the partner authorities reputation and standing as progressive, forward thinking authorities

• Maximise the potentials to retain our staff, and increase our ability to continue to recruit high caliber surveyors as market conditions improve

• Continue to meet the partner’s non fee earning obligations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
South Worcestershire Building Control Partnership: Strategic ReviewReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. South Worcestershire Building Control Partnership - Strategic ReviewThis decision
  2. Adoption of the South Worcestershire Development Plan ReviewApproved
  3. South Worcestershire Five Year Housing Land Supply Report 2025Noted
  4. Referral Report from Place and Economic Development Committee, 17th December 2025 - South Worcestershire Development Review Main Modifications and ConsultationApproved
  5. Referral Report from Place and Economic Development Committee, 17th December 2025 - South Worcestershire Local Development Scheme 2025-2027Approved
  6. South Worcestershire Development Plan Review Main Modifications and ConsultationAgreed

More from Worcester South Worcestershire Shared Services Partnership Joint Committee

All decisions
MeetingDecisionOutcome
25 Nov 2016 MinutesThat the minutes of the meeting held on 16 th September 2016 be approved as a correct record and signed by the Chairman. Approved Open
25 Nov 2016 Revenues & Benefits Shared Service Performance Report April to October 2016That the Joint Committee note the performance of the Revenue and Benefits Shared Services for the period April – Octo... Noted Open
25 Nov 2016 South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2016-17 and Budget for 2017-2018That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month... Noted Open
25 Nov 2016 Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetThat the Joint Committee: 1. note the operational performance and levels of customer satisfaction for the Worcestersh... Noted Open
25 Nov 2016 IT Shared Service Budget And Strategy ReportThat the Joint Committee: 1. note the Financial and Service Performance for 2016/17 to the end of October 2016; and 2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies