That the Cabinet:- 1. authorise Officers to progress a detailed cost estimate and prepare a business case for the ‘extend and refurbish’ option based on a six-lane pool; and 2. note that the original proposal (new build) is not deliverable within the budget provided; that changes to the operation of the business model, alongside government funding cuts fundamentally question the affordability of this level of borrowing.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1The purpose of the report is to provide a progress update on the Perdiswell Swimming Pool & Leisure Centre project, and this report will discuss and summarise information obtained so far in support of the design and delivery of the ‘new build’ facility.
1.2The report will also present a possible variation to the original ‘new build’ option for consideration, which could be more attractive both in terms of general affordability as well as project completion timescales.
1.3There are a number of considerations and risks relating to each of the proposals, and their impacts have been reviewed and refreshed in order to provide a more detailed appraisal prior to progressing to the next stage of delivery.
Background
Programme Team & Review
2.1The significance and complexity of the Swimming Pool and Leisure Centre project is widely acknowledged and understood. In order to drive the delivery of this complicated project, the Council strengthened its existing resource capacity by bringing in a new Programme Management Team in January 2014.
2.2As part of the delivery review that has taken place, concerns have been raised in regard to the viability of the previously agreed approach (new build option), and this has led to the consideration of a number of other options. The encouraging news is that there appears to be an emerging option which could provide a larger and better facility for less money. The merits of this option are outlined further in section 4 below, along with a number of other options which have been discounted at this stage.
Turner & Townsend
2.3Since their appointment in June 2013, Turner & Townsend (T&T) has further evaluated the two new build options presented in the original Deloitte Real Estate (DRE) Feasibility Study (February 2013) in order to address affordability issues and provide a degree of cost certainty.
2.4The T&T review and recommendations have been based on an up to date industry benchmarking of other facilities of a similar size and scale, and they also reflect current construction and costs. Sport England
2.5Discussions with Sport England are continuing, and an application for project funding support is being progressed. Potentially, there is between £500k and £2m available from the Sport England Strategic Facilities Fund. The Swimming Pool project remains eligible for this funding as part of the whole scheme, and the inclusion of additional sports strengthens and improves the overall bid and subsequent amount we may be able to secure. Although early communications with Sport England remain positive, at this stage of the process there is no absolute guarantee that any funding will be secured, and it is therefore not included in the funding options outlined in this report.
Council Financial Position
2.6It is also worth bearing in mind that since the new Swimming Pool project was first initiated in 2011 (Corporate Plan), the landscape within which the Council now operates has changed significantly. Government funding reductions, increased efficiency pressures, resultant service reviews, together with an increasing level of expectation from our citizens, are all influencing and prioritising what will be affordable and sustainable in terms of future service delivery.
2.7Central Government funding for Local Government has significantly reduced in the past few years and this is likely to continue for at least the next few years. The Council has seen its Formula Grant funding reduce by at least 50% (£3.3m) since March 2010, and it is likely that this will continue after the next general election, regardless of which party is in power.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.