That the Cabinet:- 1. approve the proposals developed for enhancement of the public realm at Diglis, specifically those detailed within section three and Appendix 5 of the report; 2. note that parking options are an important element of this project that requires further consideration and development; 3. approve the development of final proposals and a project plan as proposed within the report; and 4. request that the Cabinet Member for Cleaner and Greener City presents the final proposals and outline project plan in the form of a report to Cabinet.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1To advise Cabinet of the progress made to date.
1.2To request that Cabinet approve of the proposals for enhancement of the public realm and the continued development of the project as detailed within this report.
Background
2.1The Diglis area is an historic part of the City, that is becoming increasingly important due to recent and future residential development, and the enhancement and promotion of the linear riverside park as an amenity and as a green transport link.
2.2The Canal opened in 1815 followed by the river locks in the 1840s when the area was home to clay and gravel pits and a brickworks. The 1928 map shows a saw mill and recreation ground, with an Oil storage depot appearing in the 1940s. The model railway, today operated by the Worcester and District model engineers first appeared in the 1964 maps.
2.3In the latter part of the 20th Century the area was characterised by industrial estates, the southern parts of which remain whilst the northern sections are the site of recent and ongoing residential developments.
2.4Currently the major public open space consists of Diglis playing fields, a large and relatively featureless open space, and the Cherry Orchard Nature Reserve. This links with a section of the Worcester Bridge to Diglis Bridge loop adjacent to the Diglis River lock.
2.5The City Council has entered into five s106 agreements relating to developments in the area, as listed at Appendix 1. The County Council is also party to these agreements, with highways, transport and education contributions payable. County Council managed contributions are not covered within this report.
2.6S106 agreements are the commonly used term for Planning obligations under Section 106 of the Town and Country Planning Act 1990 (as amended). They a mechanism which make a development proposal acceptable in planning terms, that would not otherwise be acceptable. They are focused on site specific mitigation of the impact of development and commonly relate to provision for open space and works to the highway network.
2.7The total sum payable to the City Council is £912k, of which £457k has been received. The remainder is expected to be paid to the City Council in a number of phases over the next 7 years, subject to completion, sale and/or occupation of the remainder of the developments to which they relate. 2.8 Whilst the individual agreements vary, the funding can be categorised under a broad heading of improvements to public open space under which the Council has discretion to fund works within the terms of the agreements. There is a total of £150k allocated for public art, which can include both commissioned pieces and artistic design of open space.
2.9To date £85k has been spent on footpath improvements, play area improvements, and landscape design.
2.10It should be noted that it may be appropriate to allocate some of the £912k to projects outside the scope of this report. If this is the case, these will be relatively small sums, will fall within existing delegations, and will not detract from the Diglis public realm project.
2.11Given the level of expenditure, and the complexities of phasing of receipt and expiry dates for the funding, there is a requirement for a coordinated approach to deliver improvements to the public realm within the qualifying areas.
2.12Officers have formed a multi-disciplinary project team, which reports to the Strategic Programme Board. This team has carried out the scoping and consultation work detailed within the main body of this report.
3 Progress to date
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.