Resolved
That the minutes of the meeting held on 10 th March 2014 be approved as a correct record and signed by the Chairman.
Audit and Governance Committee approved this item on Thursday 12 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 10 th March 2014 be approved as a correct record and signed by the Chairman.
AUDIT COMMITTEE
10th March 2014
Present: Councillor Andrew Roberts in the Chair
Councillors Cawthorne (for Councillor Udall), Hodges (Vice-Chairman), Mitchell, G. Squires, J. Squires (for Councillor Cronin), Tarbuck and Whitehouse Also in Attendance: Councillor Boorn
Officers: Andy Bromage, Service Manager, Worcestershire Internal Audit Shared Service Lesley Meagher, Corporate Director – Resources Julie Slatter, Service Manager, Performance, Improvement and Efficiency
Apologies: Councillor Carpenter
24 Declarations of Interest
None.
25 Public Participation
None.
26 Minutes
With reference to minute 21 (Review of Scrutiny Arrangements), the Service Manager, Performance, Improvement and Efficiency stated that the updated CIPFA Guidance on Audit Committees had now been published and a report on the main points would be presented at the next meeting.
With reference to minute 22 (Annual Governance Statement – Half Yearly Review), the Corporate Director – Resources stated that a list of organisations that receive grant funding from the Council has been prepared and can be circulated to all Members.
RESOLVED: That the minutes of the meeting held on 11th November 2013 be approved as a correct record and signed by the Chairman.
27 External Audit - Certification Report 2012-13
The Committee considered the Certification Report 2012/13, which provided details of the work carried out by Grant Thornton on the Council’s Housing Benefit & Council Tax Benefit claim and National Non-Domestic Rates return for 2011/12. 10th March 2014 2
The report in summary had found that the Council submitted its claims on time and in the required format. Grant Thornton had no significant issues to bring to the Council’s attention regarding these claims and were able to certify the claims in accordance with the Audit Commission requirements and deadlines.
There were a small number of discrepancies highlighted in the claims totalling £799. Grant Thornton will advise the Department of Work and Pensions (DWP) of this and the amount of subsidy the Council is able to claim from DWP will be reduced by this amount for 2012/13.
In the ensuing discussion, the following main points were made:
• The DWP may require further testing work to be carried out. However, it is felt that the risk of this happening is small. The number of discrepancies and their value is insignificant compared to the value of the claims submitted.
• It was noted that the fee for certification work has reduced since 2011, when this work was being undertaken by the Audit Commission.
RESOLVED: That the Committee are pleased with the overall findings and note the report.
28 Corporate Risk Management Report
It was agreed in January 2012 that, as part of the new risk management framework and reporting process, Cabinet and Audit Committee should receive six-monthly risk reports. The Committee considered the second six-monthly Corporate Risk Management Report. The Service Manager, Performance, Improvement and Efficiency summarised the key findings.
In the ensuing discussion, the following main points were made:
• It may be possible to put a financial value on some risks and this can be considered for future reports.
• In response to a question about the fluctuating ratings in respect of CR15 - Worcestershire Home Improvement Agency Service, it was explained that this is a county-wide project that has been subject to external changes due to the uncertainty over government funding for disabled facility grants.
• The potential for establishing an opportunities register had been raised in the Risk Management Review that was undertaken by Zurich Municipal in 2012. This can be explored but does not currently form part of the framework.
• Data security had not been compromised by the recent incidents involving disruption to BT services.
RESOLVED: That the Committee note the report. 10th March 2014 3
29 Internal Audit Progress Report to 31st January 2014
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 4 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.