CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Audit and Governance Committee, Thursday 12 June 2014 at 7.00pm

Internal Audit 2013/2014 Annual Report Including the Audit Opinion and Commentary

Noted Finance 1 paper

Audit and Governance Committee noted this item on Thursday 12 June 2014. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That the Committee note the results of Internal Audit’s work during 2013/2014 and the audit opinion and commentary.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Audit and Governance Committee, 13 pages

Purpose of report

1.1To provide: • the overall results in terms of meeting Internal Audit's (IA's) objectives as set out in the internal audit plan for 2013/2014, and, • provide an audit opinion and commentary (Appendix 4).

Background

2.1The Council is required under Regulation 6 of the Accounts and Audit Regulations 2011 to “undertake an adequate and effective internal audit of its accounting records and of its system of internal control in accordance with the proper practices in relation to internal control”.

3. Policy, Legal, Financial, Equalities and Risk Management Implications

3.1This section of the report provides commentary on Internal Audit’s performance for the period 1 April 2013 to 31st March 2014 against the performance indicators agreed for the service for 2013/14 and summarises the work of the Worcestershire Internal Audit Shared Service (WIASS) throughout 2013/14.

3.2The Internal Audit(IA) plan was approved by the Audit Committee on the 11th March 2013. WIASS has delivered the audit programme in conformance with the UK Public Sector Internal Audit Standards as published by the Institute of Internal Auditors.

3.3A summary of the prime features include:

2013/2014 Key Internal Audit Inputs

A summary of the position is provided at Appendix 1

2013/2014 Key Internal Audit planned Outputs

During 2013/14 Internal Audit were required to:-

- complete a minimum of 15 full systems audits of which 5 must suitably assist the External Auditor reach their “opinion”.

- provide sufficient audit resources for other operational areas which assist the Council maintaining / improving its control systems and risk management processes or implementing / reinforcing its oversight of such systems, i.e.

provide an on-going consultancy to managers on internal control, for example where system changes are being made; carry out investigations into any suspected instances of fraud;

service the Accounts Panel and, on internal audit and value for money matters, the Audit Committee and any other Committee requiring input from Internal Audit

meet Internal Audit’s external work requirements;

achieve a benchmark delivery target for 2013/2014 of 90% of operational days over the year as a whole.

2013/2014 Internal Audit actual outputs

2013/14 was a demanding year for the Internal Audit team with the loss of two Auditors early in the year, managing a return to work after long term sickness as well as training and mentoring two new auditors who joined the team. There was a need to vacancy manage posts for a significant proportion of the year in order to offset the interim resource that was used to ensure WIASS could deliver the risk based internal audit plan. Internal Audit has carefully managed its resource and worked with partners to deliver the full audit programme (as revised) for Worcester City Council for 2013/14 including the change part way through the year with regard to providing assurance on the work that Civica are undertaking for Revenues and Benefits.

At the request of the s151 Officer and to accommodate the requirement for the Civica assurance work within the plan days 3 audits were postponed or deferred. Voluntary Sector Coordination (12 days), Value for Money (15 days) were dropped from the plan and Corporate Governance(part)(10 days) and Risk Management(part)(3 days) reduced. An additional audit was also included due to information received with regard to cash handling at The Hive. The revised plan has been delivered and provided the required coverage to allow the s151 as well as the Internal Audit Service Manager to form an overall opinion in respect of the Annual Governance Statement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit 2013/2014 Annual Report Including the Audit Opinion and CommentaryReport 13 pages DownloadRead as text

At this meeting

Whole meeting
3MinutesApproved 42013-14 External Audit Plan and the Proposed Audit Fees For 2014-15Noted
5Internal Audit 2013/2014 Annual Report Including the Audit Opinion and CommentaryThis decision
6Annual Governance Statement 2013/14Approved

On this subject at Worcester

Search all
  1. Internal Audit 2013/2014 Annual Report Including the Audit Opinion and CommentaryThis decision
  2. Annual Report of Internal Audit for 2025/26Agreed
  3. Internal Audit Progress ReportAgreed
  4. Internal Audit Plan for 2026/27Approved
  5. Internal Audit Strategy, Charter and MandateApproved
  6. Internal Audit Progress ReportAgreed

More from Worcester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Jun 2026 MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Jun 2026 External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. Agreed Open
16 Jun 2026 Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... Decided Open
16 Jun 2026 Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... Agreed Open
16 Jun 2026 Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies