Scrutiny Committee, Wednesday 16 July 2014 at 7.00pm

Flooding in February 2014

Noted Scrutiny 1 paper

Scrutiny Committee noted this item on Wednesday 16 July 2014. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

That the Committee note the report.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Scrutiny Committee, 6 pages

Purpose of report

1.1To provide an overview of the flooding in Worcester city in February 2014, the response of the City Council, and the impact that this flooding had on residents and businesses.

Background

2.1Worcester has experienced regular flood events in previous years, with some flooding seen most winters (for example flooding of the Riverside pathways, Worcester Racecourse and the Cricket Club). A relatively small number of residential and business premises are within the lower lying areas which are affected most frequently.

2.2The years 2000 and 2007 both saw significant flood events with homes and businesses flooded. Following the 2007 event substantial improvements were made at the national and local level in terms of flood warning and forecasting, and flood prevention and resilience measures.

2.3A number of Worcester homes have had alterations such as raised floors and flood barriers meaning that they can cope with this regular flooding with minimal disruption. This “target hardening” approach has protected these properties many times during lower level events but all flood defences have a maximum level of protection above which flooding will occur.

3. Summary of the recent flood event

3.1February 2014 saw the most severe flood incident in Worcester city since 2007. The river levels peaked on 13th February, with the Worcester gauge at Barbourne reaching its 2007 peak of 5.74 meters. The 2014 event differed from 2007 in that river levels remained high for a period of nearly two weeks, following persistent heavy rainfall across the country. In 2007 intense localised storms caused a much shorter peak in the River Severn, although this was also accompanied by surface water flooding in numerous locations.

3.2At its peak the River Severn flooded Dolday and Croft Road, and crossed Tybridge Street and Hylton Road, with water flowing through Cripplegate Park and across New Road. This required the closure of those roads and therefore Worcester Bridge.

3.3Worcestershire Highways maintained traffic flows across the bridge by redirecting the one way system around Cripplegate and Dolday to operate New Road and Bridge Street with two way traffic. As the River reached its peak, New Road was closed to traffic and a shuttle bus operated through the water to maintain access for pedestrians. 3.4 Buses were redirected from Crowngate for a short period and the road surface at the bottom of The Butts was raised to enable amended services to continue.

3.5Five City Council owned car parks were closed (Pitchcroft & The Moors, Cattlemarket, Croft Road, Newport Street and Tybridge Street), from 9th February through for some until19th February. The privately owned Crowngate car park was also closed from 10th to 18th February. Worcestershire County Council provided the Perdiswell Park and Ride free of charge on Sat 15th and Sun 16th February. Free parking was offered at St Martin’s Gate car park from 20th Feb to the 23rd.

3.6A small number of schools were closed for a short period due to access issues and both Cripplegate and Gheluvelt Parks were closed for around eight days.

3.7There were a number of individual homes and businesses that were directly affected. Further details are given in sections 5 and 6 of this report.

4. Worcester City Council response to the Emergency

4.1The incident first developed over the weekend of 8th February, and officers attended a multi agency response team meeting at Castle Street Police Station on the Sunday. At this early meeting river level and rainfall predictions were reviewed along with response plans. Similar meetings were held initially on a daily basis and City Council senior managers attended these meetings ensuring a joined up response.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Flooding in February 2014Report 6 pages DownloadRead as text

More from Worcester Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Mar 2017 MinutesThat the minutes of the meeting held on 1 st February 2017 be approved as a correct record and signed by the Chairman. Approved Open
8 Mar 2017 Scrutiny Review - Impact of Individual Electoral Registration - Final ReportThat the Cabinet be recommended to consider the report and approve the recommendations of the Review Group, as set ou... Approved Open
8 Mar 2017 Scrutiny Review - Street Cleansing - Final ReportThat the Cabinet be recommended to consider the report and approve the recommendations of the Review Group and the ad... Approved Open
8 Mar 2017 Service Review - HeritageThat Committee note the presentations and the responses to questions. Noted Open
8 Mar 2017 Service Review - Planning (Development Management)That Committee note the presentation and the responses to questions. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies