Worcester City Council
Cabinet, Tuesday 29 July 2014 at 7.00pm

Regeneration Projects Update - Key Decision

Approved Executive 1 paper

Cabinet approved this item on Tuesday 29 July 2014. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That the Cabinet:- 1. notes the progress on the three Priority Projects; 2. approves an additional £65,000 of New Homes Bonus to be allocated to Angel Place; 3. approves the surrender of the existing concession contract with the Crown Estate for the operation of Angel Place Market; and 4. delegates responsibility for awarding the Operation of Markets in Worcester concessionary contract to the Service Manager for Economic Development and Planning Policy in consultation with the Cabinet Member for Economic Prosperity and the Section 151 Officer.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 5 pages

Purpose of report

1.1To provide Cabinet with an update on progress with Priority Projects in the City Centre.

1.2To ask Cabinet to agree to the surrender of the current Angel Place market concession contract with the Crown Estate.

1.3To ask Cabinet for approval to delegate responsibility for agreeing a new concession contract for markets operation in Worcester.

1.4To ask Cabinet to approve £65,000 additional NHB funding for Angel Place.

Background

2.1A report to Cabinet in September 2013 reported progress on two of the priority regeneration projects – Cornmarket and Cathedral Square. A report on Angel Place, the third priority project went to Cabinet in November 2013. Since these reports there has been further progress on all three projects.

2.2The “Worcester City Centre Regeneration Progress Review” 2013, published by Zeta Environmental, sets out the considerable progress that has been made over recent years: “To date, City centre regeneration in support of the Masterplan has seen circa £70m of public funding invested, which has leveraged more than £370m of private investment (including the education sector) since 2007.”

2.3The report identified future potential to “attract more than £800-£855 million of private sector investment which needs to be leveraged by public funding of between £31-£53 million - giving a leverage ratio for public funding of at least £16 for every £1 of public investment”.

3. Angel Place

3.1Agreement has been reached with the County Council and the Crown Estate on the regeneration scheme for which Cabinet approval was given to contribute £120,000, towards a total estimated cost of £360,000. A more comprehensive scheme specification and costing carried out by the County Council has shown the total cost of the project to be £555,000. Each of the three partners has agreed in principle to contribute one third (£185,000) towards the total cost of the regeneration costs.

3.2The work will be delivered through a single contract managed by the County Council. The work will start at the beginning of September with a 10-week build programme. The approach will be similar to that taken with the successful refurbishment of the High Street, with the two Councils working with the Crown Estate and local businesses and residents to minimise impact. 3.3 In negotiations to secure funding for the scheme, the Crown Estate has expressed its desire to surrender the current Angel Place concessionary agreement for which Crown Estate pays the City Council £72,000 per annum. This contract is due to end in July 2017.

3.4With regard to a new contract for the operation of the Angel Place market, enquires have been made with major national markets operators and other local authorities who operate concessionary contracts. These enquiries have shown that, due to the limited nature of the opportunity, a contract based solely on Angel Place would not be attractive to prospective market operators.

3.5The letting of a wider market concession would be far more attractive and could deliver enhanced value to the city centre. This is in line with the Worcester Economic Prosperity Strategy aim “to develop the city centre as a unique selling point for Worcester, making it the retail, cultural, residential and leisure destination of choice for the West Midlands with a unique sense of place”

3.6The objectives of such a concession would be to:

• Increase visitor numbers and spend in Worcester • Increase footfall within the City Centre • Promote and grow markets within Worcester as part of an overall tourism strategy • Provide shoppers with an improved market experience and variety of offer that reflects the requirements of all age groups and social classes within Worcester • Provide opportunities for new enterprises to be created

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regeneration Projects Update: Key DecisionDecisions 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Regeneration Projects Update - Key DecisionThis decision
  2. City Centre Regeneration Projects - Cathedral Square - Key DecisionApproved
  3. Priority Regeneration Projects UpdateNoted

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies