That the scope of the investigations into the ‘extend and refurbish’ option at Perdiswell is broadened, to include an options appraisal of additional and enhanced facilities including increased water space and improved sports hall facilities, for consideration in a report to Cabinet in September.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1On 15 April 2014, Cabinet approved the recommendations of the Perdiswell Programme Board to progress a detailed cost estimate and prepare a business case for the ‘extend and refurbish’ option at Perdiswell, based on a six-lane pool.
1.1This report sets out the corresponding progress made and proposes a variation to this previous recommendation. The variation is that the scope of the work on the ‘extend and refurbish’ option is broadened to include an options appraisal of additional and enhanced facilities including increased water space and improved sports hall facilities. A report on this will be presented to Cabinet in September 2014.
Background
2.1At its meeting of 26th March 2013, Worcester City Council agreed that the preferred option for a new swimming pool for Worcester was an eight-lane 25 metre pool, and the minimum acceptable specification was a six-lane 25 metre pool. The capital costs at that time were estimated to be £13.5m and £10.7m respectively. These figures were based on “new build’’ assumptions.
2.2At its meeting of 11th June 2013, Cabinet agreed that the new pool should be procured on a “Develop and Construct” basis.
2.3At its meeting of 15th October 2013, Cabinet noted that a contribution to capital funding might be available from Sport England. It was also noted that the Amateur Swimming Association had a preference for the eight-lane option.
2.4On 15 April 2014 Cabinet approved to progress a detailed cost estimate and prepare a business case for the ‘extend and refurbish’ option, based on a six-lane pool.
2.5At its meeting of 18 June 2014, Cabinet was informed by the Cabinet Member for Safer and Stronger Communities, that he was minded to ensure that a broader range of options were considered over and above those identified in the Cabinet report of 15 April 2014, before making any recommendation to Council as to how to proceed.
3. Body of the Report
3.1The instruction of the Cabinet of 15 April 2014 has been progressed on the following basis:
o Independently produced and updated Latent Membership Demand Figures o Independent Revenue and Participation Modelling o Independent RIBA Stage A/B Detailed Construction Cost Estimates o Medium Term Financial Forecast
3.2In light of discussions with key funders and stakeholders during this process, such as Worcester Swimming Club and the Amateur Swimming Association, it is subsequently proposed to extend the scope of the analysis of the recommended ‘extend and refurbish’ option. This is to ensure that a detailed options appraisal is prepared which includes an analysis of the feasibility of providing additional and enhanced facilities over and above those itemised in the April 2014 Cabinet report.
3.3This analysis of additional and enhanced facilities will include reviewing the layout and size of the available water space and further improving the sports hall provision.
3.4The review will include the capital and revenue cost implications as well as the effect on public participation.
3.5The review will also consider the wider economic benefits which may be accrued as a consequence of Worcester’s new swimming facility.
3.6The options appraisal will assess affordability based on available funding, which will be based on the revenue and participation models for the proposed facilities: this can be used to fund prudential borrowing, over 40 years for the new build element and 25 years for the refurbishment. The net loan funded as compared to the total capital cost, is the net capital surplus/deficit. This will then be reviewed against the availability of additional/external sources of capital funding.
3.7Discussions are being held with Sport England and other potential funding organisations as part of this process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.