That the Cabinet:- 1. recommend to Council on 30 th September, Option C, (8 lane pool) which is in line with Council's original aspirations in March 2013; and 2. assuming Council agree a preferred option in September 2014, the Cabinet agree to delegate to the Chair of the Perdiswell Programme Board (Managing Director) in consultation with the Cabinet Member for Safer and Stronger Communities, to proceed with the following: · to extend the Turner & Townsend scope of works beyond the initial work to RIBA Stage C/D, subject to the granting of planning permission ; · the finalisation and approval of the RIBA stage C/D design; · the development of an evaluation matrix for the construction contract procurement; · the market testing of the construction contract following the restricted OJEU procurement route, and; · the evaluation of the construction tender returns and the drafting of a further report to Cabinet for approval of the preferred construction contractor.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
• New construction (Swimming Pool) areas are: o Option A 2188m2, Option B 2425m2, Option C 2856m2 • Level 1 Refurbishment – making good and redecoration is for 375m2 at £250m2 • Level 2 Refurbishment – minor alterations and redecoration is for 586-472m2 at £750m2 • Level 3 Refurbishment – full refurbishment is for 297-411m2 at £1,100m2 • Allowances: Design Reserve 2.5%, Contractor Preliminaries 13.5%, Overhead and Profit 4% • Average construction cost: Options A/B £1600m2, Option C £1650m2. • Estimates based on RIBA stage A/B. • Stage D to be completed prior to tender due March 2015, subject to September decision • Contingency 10% of construction cost, recommended at RIBA stage A/B • Fixtures and fitting £100k • Inflation based on mid-point construction in Q3 2015, based on BCIS. • VAT on construction and project costs is excluded on the basis that an external provider will operate the facility when it opens. • Project management/client side costs are estimated for two years. • Highways: estimate based on discussions with County Highways during the process to obtain outline planning permission, estimated cost of likely required improvements. • Moveable floors are based on £236k for the learner pool and £661k for both pools.
INTEREST RATES
• The Public Works Loans Board interest rates are variable and updated on a daily basis. 40 year borrowing rates have been used for the new build element and 25 years for the refurbishment. New build equates to circa 80% of the total capital cost. • The Council qualifies for a PWLB certainty rate discount of 0.2%. The market forecast is that interest rates on long term loans are likely to increase by 0.5% by 2016. A Q2 2015 loan draw down is assumed on forecast interest rates of 4.23% for the refurb and 4.47% for the new build.
INCOME GENERATION AND RUNNING COSTS
• It is assumed that there will be an external Leisure Partner operator in place from the opening of the new facility. For the purposes of modelling it is assumed that the operator has charitable status to attract NNDR and VAT benefits. • Income generation estimates are based on latent demand analysis from Leisure Database Company and participation and revenue modelling from Strategic Leisure. • Income per fitness station is estimated at £7k per station p.a. at its peak operation (Strategic Leisure). • Utilities estimates have been benchmarked against other similar operations. • The modelling is based on average figures over a ten year contract period, and on income it assumes a five year maturity. The modelling is informed by comparative data from a number of recent similar facilities and tender bid submissions. • Profit for the operator is based on 8% of total income, and overheads are based on 4% of total income. • It is assumed that the building lifecycle costs will become an operator cost (i.e. on a full repairing lease basis), whereas it is not determined at this stage, who is responsible for the fit-out and equipment lifecycle costs. • No inflationary allowance has been built into the income or expenditure figures, it is assumed these will effectively cancel each other out. Growth at 2.5% has been applied to the income modelling. APPENDIX 2
Option A Option B Option C CONSTRUCTION & PROJECT COSTS 6 Lane 6 Lane 8 Lane Base Case Base Plus Base Plus £000s £000s £000s Demolition 50 50 85 Superstructure 3,549 3,880 4,712 Internal Finishes/Refurbishment 889 890 929 External Works 210 210 330 Total Build 4,698 5,030 6,056 Preliminaries/Overheads/Profit 960 1,056 1,250 Sports Hall 0 300 300 Total Construction 5,658 6,386 7,606 Professional Fees 732 769 911 Client FF&E 100 100 100 Client Contingency 566 639 761 Inflation 281 302 336 Total Project Cost 7,337 8,196 9,714 Highways work provision 275 275 400 Project /Client Management 103 103 103 Moveable floors 0 661 236
Total Cost 7,714 9,234 10,452
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.