That the Cabinet: 1. approve award of contract to Contractor A for the new build and refurbishment project at Perdiswell Leisure Centre in accordance with the evaluation report in Appendix 1 (Exempt); 2. agree to delegate to the Corporate Director – Service Delivery in consultation with the Portfolio holder for Sport, Leisure and Retail the finalisation of the contract and award of contract to Contractor A following the end of the standstill period; 3. agree to delegate to the Corporate Director – Resources in consultation with the Portfolio holder for Resources the finalisation of capital financing arrangements in accordance with the financial details in Appendix 2 (Exempt); and 4. agree to delegate to the Corporate Director – Service Delivery in consultation with the Portfolio Holder for Sport, Leisure and Retail, finalisation of legal agreements with Heart of Worcestershire College to carry out additional improvement works to the Perdiswell Leisure Centre.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1The purpose of this report is to update Cabinet on progress with the proposed swimming pool and leisure facilities on the Perdiswell site.
1.2To request approval to appoint Contractor A as the preferred construction contractor to build the Perdiswell Swimming Pool and Leisure Centre Project.
1.3To request approval for Heart of Worcestershire College to invest in Perdiswell Swimming Pool and Leisure Centre by way of a direct works package to an approximate value of £300,000. These works will be contracted by and paid for by the College at the end of the City Council’s main works programme.
Background
2.1At its meeting on 30th September 2014, Full Council agreed to proceed with an 8 lane swimming pool on an ‘extend and refurbish’ basis at Perdiswell Leisure Centre. This was in line with Council's original aspirations, in March 2013, to develop the preferred option of an 8 lane pool at Perdiswell, albeit at that stage the preferred option was based on an assumption of ‘new build’.
2.2The financial modelling for the ‘extend and refurbish’ option indicated that an 8 lane pool could be delivered in line with the approved budget of £10.5m. In agreeing to proceed on this basis, Full Council approved a number of delegations to the Chair of the Perdiswell Programme Board (Managing Director) in consultation with the Cabinet Member for Safer and Stronger Communities as follows:
to extend the scope of the Project Management partner works beyond the initial work to RIBA Stage C/D, subject to the granting of planning permission; the finalisation and approval of the RIBA stage C/D design; the development of an evaluation matrix for the construction contract procurement; the market testing of the construction contract following the restricted OJEU procurement route; the evaluation of the construction tender returns, and; the drafting of a further report to Cabinet for approval of the preferred construction contractor.
3. Progress Update on Recommendations from September 2014
Planning Permission, Design and Scope of Works
3.1Planning Permission was granted (subject to conditions) on the 21 May 2015.
3.2Stage D design was finalised and approved on the 18 May 2015. This was based on the scope of works agreed by Full Council in September 2014, as follows: 8 Lane Regional Competition Standard Pool 250 Spectator Seats and a further 120 Poolside Seats A large 180m2 Secondary Pool with Moveable Floor to provide for a range of uses including confidence water 8 Court Sports Hall fitted with up to date acoustic equipment State of the Art 120 Station Gymnasium Consultation room Three studios Two external 5-a-side football pitches Cafe
3.3The facilities have been designed with full input from funders and partner and stakeholder organisations including Sport England, The County Sports Partnership, Heart of Worcestershire College, The Amateur Swimming Association, Worcester Swimming Club, and Disability Sport Worcester
3.4A public consultation event was also held at Perdiswell where the plans for the New Swimming Pool and Leisure Centre were put on display. They were met with an overwhelmingly positive response.
Procurement and Evaluation
3.5The process of market testing, including the development of the evaluation matrix, of the construction contract following the restricted OJEU procurement route was commenced in February 2015 and completed in August 2015 with a preferred bidder identified.
3.6The procurement of the contractor to build Perdiswell has followed the restricted OJEU route. The OJEU notice was posted on the 25 February 2015 and several requests for the Preliminary Qualification Questionnaire (PQQ) were received.
3.7These expressions of interest resulted in 9 completed PQQ submissions. These were then subject to a detailed evaluation and the top ranked 6 were Invited to Tender (ITT).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.