That the Cabinet: 1. approve a maximum contribution of £400,000 of NHB funding, available for the 2014/2015 year, to Cathedral Square; 2. agree to enter into a tripartite contract with Salmon Asset Management and Worcestershire County Council to jointly fund and deliver the scheme; and 3. delegate the signing of the contract to the Managing Director, in consultation with the Section 151 Officer and Portfolio Holder for Economic Prosperity.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1To ask Cabinet to approve £400,000 of NHB funding for Cathedral Square.
1.2To ask Cabinet to agree to enter into a tripartite Heads of Terms agreement with Salmon Asset Management and Worcestershire County Council to jointly fund and deliver the scheme.
1.3To ask Cabinet to delegate the signing of the contract to the Managing Director, in consultation with the Section 151 Officer and Portfolio Holder for Economic Prosperity.
Background
2.1Cathedral Square was one of the priority opportunity areas within the City Centre Masterplan. It was identified as having the potential for redevelopment with the aim of delivering an improved retail offer in the city centre. The Masterplan said it could be given a new lease of life if non-essential road surface were given over to the creation of pedestrian space.
2.2The July 2014 Cabinet paper on Regeneration Projects provided a progress report on Cathedral Square.
2.3Subsequent to that report, planning permission has been granted to Salmon Asset Management, the owners of Cathedral Plaza for the re-development of the shopping centre, re-modelling of the highways layout and the creation of a new public space.
2.4Salmon Asset Management will fund and manage the re-development of the shopping centre (which will be re-named Cathedral Square) with an intended construction start date of April 2015; and for the Centre to be completed by August 2016.
3. Progress
3.1Subsequent to the July Cabinet report and the granting of planning permission, considerable progress has been made in our discussions with Salmon Asset Management and the County Council on the highways and public realm scheme.
3.2Salmon Asset Management, as part of their development of the overall plan, commissioned surveyors to provide cost estimates for the scheme. The initial estimate they provided for both the highways and public realm works was £1.5 million, including a significant contingency pending on site investigations.
1 3.3 As part of the cost analysis process, the County Council have revised downwards the basis for the costs, and have provided an estimate of circa £1 million. This scheme assumes that the types of materials to be used, particularly in the public realm element will achieve a high quality space.
3.4Salmon Asset Management have indicated their willingness to invest up to a maximum of £300,000 into the scheme as a contribution, subject to confirmation of financial commitment from the City and County Councils.
3.5However, with the details of the design still being developed, and in recognition of the contingent liabilities, outstanding risks, and un-known costs (including archaeology) it is felt prudent at this stage to set a budget estimate at £1.1m. This also acknowledges the fact that the scheme must not be value-engineered to such a level that the end result provides a mediocre public space with lower quality materials.
3.6Based on the above estimate, it is proposed that each of the Councils will contribute a maximum of £400,000 investment, and it is this amount that is being sought from the NHB infrastructure/regeneration allocation.
3.7The scheme will be put on a legal footing through a formal tripartite Heads of Terms agreement between the three partners.
3.8Salmon Asset Management, at their cost, have engaged McFarlane and Associates as landscape architects to enable the design to be further advanced to meet the conditions in the planning approval.
3.9Discussions have been held with the Cathedral and they are in the process of developing a new strategic plan, which includes enhancement to the public space in front of the Cathedral. Whilst it is unlikely that the Cathedral’s proposals will come forward before the development of Cathedral Square, we will continue to keep them informed of the progress with our scheme and provide an input into the Cathedral’s plans.
4. Delivery
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.