Repairs to Perdiswell Culvert - Key Decision

Decided Executive 1 paper

Cabinet decided this item on Tuesday 9 December 2014. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

That the Cabinet authorise the Corporate Director, Service Delivery to proceed with procurement of the proposed works to repair the culvert within existing delegations and capital allocations.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 3 pages

Background

2.1The Barbourne Brook passes through Worcester from Hindlip to the north, discharging into the River Severn at Gheluvelt Park.

2.2The section that runs through Perdiswell Park passes within a concrete culvert under the golf course.

2.3The culvert lies at a depth of up to 9m and surveys have shown that the lower sections are in a poor condition and require remedial work to deal with the risk of collapse.

3. Progress to date

3.1Working closely with the Environment Agency officers have developed and submitted a detailed bid to the Environment Agency for funding to support the work required.

3.2A number of options were considered which included installing a replacement concrete culvert, excavation and creation of an open channel, and the installation of a structural liner to the existing culvert.

3.3The proposed scheme, approved by the Environment Agency, involves the installation of a structural resin liner. This is installed as a flexible liner that then sets into solid material that provides the required structural strength.

3.4The work is to repair the defective areas of the concrete culvert which are found in the lower section. This is projected to cost £505k, with a confirmed grant contribution of £345k from the Environment Agency to complete the work within 2014/15. There is provision for £160k for this project within the Council’s Capital Programme spread over two years from 2014/15.

3.5The work will involve a minimal amount of disruption to users of Perdiswell Park, with the impact limited to one or two excavations to install inspection chambers between which the liner will be installed. The construction period is expected to be no more than 6 weeks and is scheduled to start in early 2015.

3.6Consultation with the golf course professional has identified that the work can be accommodated with no alteration to the playing areas of the golf course, with the impact limited to a diversion on the route between the 18th green and the club house. 4. Further Work

4.1Subject to Cabinet approval Officers will proceed with procuring the work to be carried out during 2014/15.

4.2The entire culvert will continue to be surveyed periodically in conjunction with the Environment Agency to monitor its condition.

5. Equalities, Financial, Health and Safety, HR, Legal, Policy, and Risk Management Implications

5.1Equalities Implications No significant implications are associated with the content of this report.

5.2Financial Implications The Council has budgeted for £160k within 2014/15 and 2015/16 to part fund this work. Grant funding of £345k has been confirmed by the Environment Agency. This funding covers the cost of the work including a contingency sum.

5.3Health and Safety Implications Health and Safety implications will be dealt with within standard procedures for procuring a construction project of this size.

5.4HR Implications No significant implications are associated with the content of this report. The project will be managed by Officers from the Shared Property Service. These costs are included in the overall project cost.

5.5Legal Implications As owner of the asset the City Council is responsible to keep it in reasonable repair.

5.6Policy Implications No significant implications are associated with the content of this report.

5.7Risk Management Implications The completion of this work reduces the risk of collapse of the culvert. Such a collapse could result in flooding upstream of the culvert and require significant emergency works. This would lead to reputational damage to the Council and incur a significant unbudgeted cost. If the work is not carried out at this time the external grant funding may be lost.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Repairs to Perdiswell Culvert: Key DecisionDecisions 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Repairs to Perdiswell Culvert - Key DecisionThis decision
  2. Perdiswell Culvert Repairs - Award Of Contract - Key DecisionDecided
  3. Temporary Change to Golf Provision to Allow for Repairs to the Perdiswell CulvertApproved

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies