Resolved
That Cabinet note the content of this report and the urgent decision made by the Acting Head of Paid Service.
Cabinet noted this item on Tuesday 28 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet note the content of this report and the urgent decision made by the Acting Head of Paid Service.
1.1To inform Cabinet of an Executive Decision made by the Head of Paid Service in consultation with the Leader of the Council to increase the capital budget allocation for the Crematorium refurbishment by up to £50k.
2.1Cabinet authorised officers to proceed with the refurbishment of Astwood Crematorium Chapel, public areas and back of house office facilities at the Cabinet meeting in October 2014.
2.2The work is intended to update the public areas, providing a more welcoming environment and better facilities. It will also allow the bereavement services team to co locate at the main crematorium building, bringing efficiencies and improved customer service supporting changes being implemented following a Lean Review of the service.
2.3The report stated that there was a provisional capital allocation of up to £300k available for this work.
2.4Officers developed a specification for refurbishment works and a project timetable to enable the work to be carried out during August 2015, that month usually having the lowest demand for cremations.
2.5Arrangements for an alternative chapel facility had been made to allow the crematorium to continue to operate during the works, including a four week period when the chapel will be unavailable. This mitigates any disruption to customer service and loss of income.
2.6The specification for works had been developed in detail by Property Services, using the County Council’s framework consultants, Jacobs. Whilst the original cabinet report gave an outline costing of c£200k, it had become apparent that in order to carry out an appropriate standard of refurbishment works a greater budget would be required, within the capital allocation referred to above at 2.3.
2.7The Architect was briefed to deliver works within a budget of £320k, which included £20k of routine maintenance works to be carried out as part of the project, and funded from revenue budgets.
2.8The specification was assessed by the appointed Quantity surveyor as being within budget and the work was put out to tender. Tenders were received ranging between £266k and £348k for the building works. Accepting the lowest tender would give a total project cost of £370k, including fees (£49k), and additional works with regard to asbestos (£10k) and audio visual equipment and installation (£20k) that will be tendered separately. 2.9 The disparity between the quantity Surveyors estimates and the total cost is due in large part to an under estimation of the additional costs of working around an operating crematorium and cemetery (£20k) (the works to back of house will be carried out whilst the chapel is open as usual) and omission from the original scheme of audio visual works (provisional sum £20k).
3. Executive Decision
3.1An urgent decision was required in order to appoint contractors and keep to the project schedule. Delay at this point would have incurred a risk of being unable to secure temporary chapel facilities, and risk a loss of availability of contractors. These are both reputational and substantial financial risks.
3.2The following options were considered;
Option 1 was to re-tender to seek a lower price. This was rejected due to inherent delay and uncertainty of lower prices being obtained.
Option 2 was to reduce the scope of works. This was rejected as the project team could not identify a significant omission that could be made without failing to deliver the project objectives for front and back of house areas. Minor reductions could have been made by delaying sundry items such as audio visual equipment but this would have resulted in a “half finished” appearance when the chapel is re opened, leading to reputational damage whilst merely delaying expenditure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Crematorium RefurbishmentDecisions | 4 pages | DownloadRead as text |
Follow Cabinet at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2017 | MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 21 Mar 2017 | The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... | Agreed | Open |
| 21 Mar 2017 | Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... | Agreed | Open |
| 21 Mar 2017 | Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... | Agreed | Open |
| 21 Mar 2017 | Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.