Resolved
That the Joint Committee:- 1. note the financial and service performance for 2015/16; and 2. approve the Budget and Strategy for 2016/17.
South Worcestershire Shared Services Partnership Joint Committee noted this item on Thursday 26 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Joint Committee:- 1. note the financial and service performance for 2015/16; and 2. approve the Budget and Strategy for 2016/17.
This report sets out the financial and service performance of the IT Shared Service for the current year and presents the Budget and Strategy for 2016/17 for the Shared Service for approval by the Joint Committee, in line with the Partnership Agreement.
2.1That the financial and service performance for 2015/16 be noted.
2.2That the Budget and Strategy for 2016/17 be approved.
Financial Performance to end of October 2015
3.1The financial performance (budget monitoring) of the IT Shared Service for the 7 months to the end of October 2015 is shown at Appendix 1. The overall position is that there is an underspend against profiled budget of £43,951, of which £64,776 is shown against the employee costs budget head.
3.2There has been some significant staff vacancies during the year which have not been filled pending the ICT staff restructure. These have resulted in a salary underspend of £83,868 along with £2,239 for additional leave purchased by staff. However, some of this has been used to fund agency staff with a cost and commitment of £24,835. There are also underspends on other staff related budgets totalling £3,504.
3.3In addition there is an overspend of £24,275 on the Supplies and Services budget. This is due to the cost of the telephone maintenance contract being transferred to the shared service for which no budget was provided in the original estimate. There will be a corresponding saving within partner councils’ non shared service IT budgets.
3.4Finally income has been affected by the decision to not continue with the Civica Coventry support contract after June 2015. A full year’s budget was provided resulting in an income shortfall of £5,000 in the year to date. However, there is additional unbudgeted income from Civica for the Mitel telephony system (£8,100) and for server work (£350). This has resulted in additional income of £3,450 in total.
3.5There is no requirement to revise the 2015/16 budget or the level of contributions from partner councils.
Proposed Budget 2016/17
3.6The proposed budget for 2016/17 is shown at Appendix 2. The increase in budget of £81,110 between 2015/16 and 2016/17 is attributed to the following items:
£44,500 to cover a pay award of 1% and changes to Employers’ NI contributions has been applied.
£6,610 for inflation on Hardware Maintenance / Software Licenses.
£30,000 as the cost of Telephone Maintenance has been moved from council budgets to the ICT shared service budget. There are corresponding savings in the councils’ budgets.
3.7Income is reduced following the decision to cease the Coventry support contract to allow key IT staff to concentrate on other priorities. This reduction has been offset by additional income for support to the Civica Hub of £2,100 per year. The remainder of the reduction in income (£17,900) will be met through savings in the Hardware and Software licenses budget with no impact on the overall budget.
Service Performance / Strategy for 2016/17
3.8Our annual PSN compliance renewal has been completed and submitted. The volume of work resulting from the ICT health check was significantly lower than the previous year due to the ongoing security updates and review processes now in place.
3.9The staff consultation on the restructure of the ICT shared service teams is due to commence later this month. The restructure is necessary to improve resilience and flexibility of ICT resource provision. It is currently planned to implement the new structure from April 2016. An additional South Worcestershire Shared Services Partnership Joint Committee will be called early in the New Year to approve the changes following completion of the consultation.
3.10Other highlights in the current year include:
The Garden Waste sign up self-service development for Worcester has gone live since the last meeting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring Summary to end of OctoberAppendix 1 | 1 pages | Download |
PDF |
Budget for 2016-17Appendix 2 | 1 pages | Download |
PDF |
IT Shared Service Budget and Strategy ReportReport | 3 pages | DownloadRead as text |
Follow South Worcestershire Shared Services Partnership Joint Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Nov 2016 | MinutesThat the minutes of the meeting held on 16 th September 2016 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 25 Nov 2016 | Revenues & Benefits Shared Service Performance Report April to October 2016That the Joint Committee note the performance of the Revenue and Benefits Shared Services for the period April – Octo... | Noted | Open |
| 25 Nov 2016 | South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2016-17 and Budget for 2017-2018That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month... | Noted | Open |
| 25 Nov 2016 | Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetThat the Joint Committee: 1. note the operational performance and levels of customer satisfaction for the Worcestersh... | Noted | Open |
| 25 Nov 2016 | IT Shared Service Budget And Strategy ReportThat the Joint Committee: 1. note the Financial and Service Performance for 2016/17 to the end of October 2016; and 2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.