South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2015-16 and Budget for 2016-2017
NotedCommittee1 paper
South Worcestershire Shared Services Partnership Joint Committee noted this item on Thursday 26 November 2015. Below is the council's own wording, with the papers it was decided on.
That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month period April 2015 to October 2015 as detailed in Appendix A. 2. approve the revised budget for 2015/16 as set out in Appendix A (final column). 3. approve the budget for 2016/17 for the Revenues and Benefits Shared Service and the proposed contributions by each of the member authorities as shown at Appendix B.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to South Worcestershire Shared Services Partnership Joint Committee, 5 pages
Summary
1.1The purpose of this report is to present the financial performance to date and the revised budget for 2015/16 and the proposed budget for 2016/17 for the South Worcestershire Revenues and Benefits Shared Service.
Recommendations
2.1That the Joint Committee notes the financial performance (budget monitoring) of the Shared Service for the 7 month period April 2015 to October 2015 as detailed in Appendix A.
2.2That the Joint Committee approves the revised budget for 2015/16 as set out in Appendix A (final column).
2.3That the Joint Committee approves the budget for 2016/17 for the Revenues and Benefits Shared Service and the proposed contributions by each of the member authorities as shown at Appendix B.
Background
3.1Appendix A to the report details the financial performance (budget monitoring) of the Revenues and Benefits Shared Service for the 7 month period April to October 2015. This shows that:
The estimated payment in respect of the Civica Main contract has reduced, mainly due to the net impact of the transfer of the Fraud team to the DWP Single Fraud Investigation Service. Contract Change Notes to the value of £163,798 have been agreed in addition to the Civica main contract, of which £153,582 will be funded by DWP / DCLG grants received by the Districts. The expected pensions top up for the year is now expected to be
Page 1 of 5 £20,000, based on the actual costs currently being incurred. The projected year end spend at £3,083,113 is now expected to be £22,987 less than the original estimate for the year and members of the Joint Committee are asked to agree the sum of £3,083,113 as the revised budget for 2015/16.
3.2The proposed budget for 2016/17 for the Revenues and Benefits Shared Service, including Wychavon DC support services and hosting costs, is shown at Appendix B. The budget reflects a net reduction in cost due to the impact of the transfer of the Fraud team to the Single Fraud Investigation Service at the DWP. Estimated inflation on the Civica contract is assumed to be nil from both October 2015 and from October 2016 (based on CPI being expected to be below 2% and in line with the legal agreement). An estimated employers’ pensions cost ‘top up’ has also been included, based on current levels of spend. However there is a likelihood that this could reduce during the year if movement of Civica staff to new roles and therefore away from the Local Government Pension Scheme continues to occur. Finally, the estimated support / hosting costs of Wychavon District Council have been clearly identified and have been included at the same level as in 2014/15 and 2015/16, reflecting the fact that the Council is endeavouring to contain the costs of inflation on the service by finding efficiency savings within the support areas.
3.3The proposed charges to the individual member authorities for 2016/17 are also shown at Appendix B. These reflect the simplification changes to the charging methodology that were agreed by the Joint Committee in November 2013, following the commencement of the strategic partnership with Civica. Due to the transfer of the Fraud team to the Single Fraud Investigation Service at the DWP and the effort to keep costs as low as possible, as detailed in the paragraphs above, there will be a saving of 2.3% for each Council between 2015/16 and 2016/17.
Page 2 of 5 APPENDIX A Revenues and Benefits Shared Service – Budget Monitoring April to October 2015
Original Actual Expenditure and Commitments Total Projected Spend Estimate to end October Expenditure at Year end 2015/16 to end and Revised October Budget 2015/16
Benefits Council Tax NNDR
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South Worcestershire Shared Services Partnership Joint Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.